Category Tatham Road Show all
-
Flood Restoration - Roads & Bridges Update (Dec 2023)
Share Flood Restoration - Roads & Bridges Update (Dec 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Dec 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Dec 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Dec 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
CURRENT WORKS – SEALED & UNSEALED ROADS
Jiggi Road
Works have been completed on Jiggi Road to address immediate issues caused from the February and March 2022 floods. This has involved DGB20 overlay, pavement stabilisation, trimming and sealing of the road surface to repair flood damages. Further assessment is required and works will continue in 2023-24.
Ashlin Road
Overlay and drainage works are now completed on Ashlin Road to repair damages caused from the February and March 2022 floods. Leeson Road
Overlay and drainage works are now completed on Leeson Road to repair damages caused from the February and March 2022 floods.
Upper Tuntable Falls Road
Repair work was recently carried out for Upper Tuntable Falls Road. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.
Wallace Road
Wallace Road has recently undergone repair work up to the landslip. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.
COMPLETED WORKS – EMERGENCY ROAD REPAIRS
Tatham Road
Works were completed on Tatham Road to remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Tucki Road
Tucki Road works have removed and replaced existing material from the road surface, graded and rolled the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
CURRENT WORKS – SEALED ROADS
Riverbank Road
Works are continuing for Riverbank Road to repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stabilise, trim and seal road surface to repair flood damages.
CURRENT WORKS – UNSEALED ROADS
Corndale Road
Corndale Road continues to undergo works to replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March 2022 floods.
East Road
Overlay and drainage works are currently being carried out on East Road to restore damages caused from the February and March 2022 floods.
Terania Creek Road
Work is currently underway between The Channon and Lawler Road on Terania Creek Road due to a landslip after Lawler Road. Overlay and drainage work are underway to repair damages caused from the February and March 2022 floods.
CURRENT WORKS – EMERGENCY ROAD REPAIRS
Keerrong Road
Works are continuing along Keerrong Road to overlay, stabilise, trim and seal road surface to repair damages from the February and March, 2022 floods.
Tuntable Creek Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Leycester Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
CURRENT WORKS – DRAINAGE WORKS
Keerrong Road
Drainage works are continuing for Keerrong Road these include desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.
CURRENT WORKS – RESTORATION WORKS
Restoration works are continuing along Tuntable Creek Road. Landslip repairs are currently underway through stabilisation works to allow rehabilitation of landslip and reinstatement of road and guardrail barrier.Tuntable Creek Road
The photos below outline the restoration effort including works performed by a 16-tonne hydraulic crawler mounted drill rig. This remote operated machine is designed for geotechnical site investigations and is drilling around 8m into the embankment.
FUTURE WORKS - SEALED ROADS
Cawongla Road / Quilty Road
All preliminary works on Cawongla Road are completed ready to commence works on the 3rd of January 2023. Quilty road has been graded and prepared for the detour route to commence on the 3rd of January 2023, vegetation trimming has been completed and drainage works have also been completed. These works have been completed with great cooperation for the public. For further information on the work, visit the Cawongla Road update -
Flood Restoration - Roads & Bridges Update (12th Dec 2022)
Share Flood Restoration - Roads & Bridges Update (12th Dec 2022) on Facebook Share Flood Restoration - Roads & Bridges Update (12th Dec 2022) on Twitter Share Flood Restoration - Roads & Bridges Update (12th Dec 2022) on Linkedin Email Flood Restoration - Roads & Bridges Update (12th Dec 2022) linkROAD PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
CURRENT WORKS – SEALED ROADS
Riverbank Road
To repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stablise, trim and seal road surface height to repair damages.
Jiggi Road
Likewise, Jiggi Road has undergone recent works to address issues caused from the February and March 2022 floods. This has involved overlay, stabilise, trim and seal road surface height to repair damages.
CURRENT WORKS – UNSEALED ROADS
Braidwood Road
Braidwood Road has recently had unsealed road works completed, the below image outlines the after result for the road.
Ashlin Road
Ashlin Road recently underwent repair works, these are now completed. The image below shows the before image of the roads condition.
Leeson Road
Unsealed road works were recently completed for Leeson Road. The below image outlines the before condition of the road.
Upper Tuntable Falls Road
Repair work was recently carried out and are now completed for Upper Tuntable Falls Road. The image below shows the before image of the roads condition.
CURRENT WORKS – EMERGENCY ROAD REPAIRS
Tatham Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Tucki Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
CURRENT WORKS – DRAINAGE WORKS
Keerrong Road
Desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.
FUTURE WORKS – SEALED ROADS
Corndale Road
Replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March, 2022 floods.
Keerrong Road
Overlay, stabilise, trim and seal road surface height to repair damages from the February and March, 2022 floods.
FUTURE WORKS – UNSEALED ROADS
East Road, Mountain Top Road, East Road, Terania Creek Road & Wallace Road
Planning is in place to perform works shortly on the following unsealed roads: Terania Creek Road (Section before the landslip), Wallace Road, Mountain Top Road, and East Road.
FUTURE WORKS – EMERGENCY ROAD REPAIRS
Tuntable Creek Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.
Leycester Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
Keerrong Road
Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.
-
Flood Restoration - Roads & Bridges Update (5th Dec 2022)
Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Facebook Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Twitter Share Flood Restoration - Roads & Bridges Update (5th Dec 2022) on Linkedin Email Flood Restoration - Roads & Bridges Update (5th Dec 2022) linkROAD PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.
Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
Sealed Pavements
Nimbin Road
Pavement works have been completed at Nimbin Road near the intersection of Shipway Road.Riverbank Road
Works have started at Riverbank Road to complete permanent pavement stabilisation works consisting of overlaying 150mm of DGB20 then mixing a conforming road pavement.
Jiggi Road
The team are continuing to undertake pavement repairs on various sections of Jiggi Road.
Drainage Work
Riverbank Road
The following photos outline the completed drainage work for Riverbank Road.
Emergency Temporary Pavement Repair
Rock Valley Road / Cawongla Road
Sections of temporary road pavement which have been identified and planned for return early next year.
Tatham Road
Sections of road pavement which have been temporarily with a planned return early next yearUnsealed Pavements
The team have completed unsealed pavement works at Gordon Road, Parmenter Road, Savins Road, Houlden Road, Nightcap Range Road and Whian Whian Road.
Culverts
Cawongla Road
Multiple culvert works are now complete along Cawongla Road. These include culverts near Larnook School with 1 x 900mm and 1 x 600mm culvert successfully replaced and material being stockpiled for replacement of a twin cell 1350mm culvert (culvert with deep depression within the roadway). These works will continue until Christmas, after which the road closure and replacement works can be undertaken. Additionally, material is being stockpiled for replacement of Twin cell 1800mm culvert at 169 Cawongla Road, these works will continue until Christmas, after which the road closure and replacement works can be undertaken. It is anticipated that the tree lopping within this area will be completed prior to Christmas.
Quilty Road detour route works
Currently works are being undertaken to upgrade Quilty Road to ensure adequate width of the gravel pavement for two lane traffic and to improve road pavement surface.
-
Tatham Road - Temporary Flood Restoration Works
Share Tatham Road - Temporary Flood Restoration Works on Facebook Share Tatham Road - Temporary Flood Restoration Works on Twitter Share Tatham Road - Temporary Flood Restoration Works on Linkedin Email Tatham Road - Temporary Flood Restoration Works linkCouncil will be completing temporary patching works to improve road surface conditions for Tatham Road during November and December 2022. These works are a temporary measure, until permanent pavement rehabilitation works are scheduled.
Works will apply only to five sections of Tatham Road that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments. Funding has been secured through Transport for NSW. This funding is allocated to repair damage sustained during the February 2022 natural disaster only. Additional works required and subsequent funding for Tatham Road are being reviewed.
The temporary works are expected to start mid November 2022 – end of December 2022 subject to weather, contractor, and material availability. Single lane traffic control will be in place during the works period.
These temporary works will involve removing damaged road sections and replacing with gravel road base, with an emulsion sacrificial seal.
Future pavement repair works, expected to be carried out in mid-2023 will include:
- Road surface: Improve the surface of the road in places.
- Signs and line marking: Line marking and guideposts.
- Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
- Drainage maintenance: Re-excavate open drains and remove flood sediment as required. Minor drainage works will be completed prior to pavement works commencing.
- Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.
Road users are advised to follow signage and expect delays as these works are completed.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Tatham Road – Temporary Patching Works.’
-
Flood Recovery Heavy Patching Program
Share Flood Recovery Heavy Patching Program on Facebook Share Flood Recovery Heavy Patching Program on Twitter Share Flood Recovery Heavy Patching Program on Linkedin Email Flood Recovery Heavy Patching Program linkFlood Recovery Heavy Patching Program –
Restoration of road surface, possible change in road level.
Segments of the following have been identified for heavy patching works to repair flood damage to road surface.
Precinct 1
Graham Road
Gundarimba Road
River Bank Road
Rous Road
Skyline Road
Tregeagle Road
Tuckurimba Road
Tucki Road
Wybelena Road
Precinct 2
Bagotville Road
Broadwater Road
Kilgin Road
Mathieson Lane
Precinct 3
Tatham Road
Precinct 4
Nimoola Road
Pelican Creek Road
Precinct 6
Back Creek Road
Precinct 7
Axford Road
Martin Road
McGuinness Road
Rock Valley Road
Precinct 8
Boggumbil Road
Davis Road
Jacobson Road
Jiggi Road
Potessu Road
Rosehill Road
Precinct 9
Anderson Road
Basil Road
Cecil Street
Crofton Road
Gungas Road
Lillian Rock Road
Moffitt Road
Sibley Street
Symonds Road
Thorburn Street
Precinct 10
Booerie Creek Road
Boyle Road
Keerrong Road
Precinct 11
Koonorigan Road
Pinchin Road
Terania Creek Road
The Channon Road
Tuntable Creek Road
Precinct 12
Dorroughby Road
Duncan Road
James Street (Dunoon)
Middleton Way
Nightcap Range Road
Rocky Creek Dam Road
Precinct 13
Corndale Road
Hunters Hill Road
Grace Road
James Gibson Road
Precinct 14
Boatharbour Road
Eltham Road
Humpty Back Road
Regional Roads
Blue Knob Road
Coraki Road
Dunoon Road
Nimbin Road
Wyrallah Road
Bridge Street (Wyrallah)
Kyogle Road
These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.
Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.
How will the works affect traffic?
Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.
What do the works involve?
These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.
The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.
This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.
All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.
What happens now?
If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:
- Via the ‘Submissions’ tab of this article HERE.
- Email to council@lismore.nsw.gov.au
- Call to Council (02) 6625 0500
- In writing to Lismore City Council, PO Box 23A, Lismore 2480