  • Flood Restoration - Roads & Bridges Update (July 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Pavement Investigations

    During July, Council completed pavement investigations involving drilling operations on the following roads:

    • Rock Valley / Cawongla Road
    • Crofton Road


    Cawongla Road

    During July, flood remediation drainage works were completed on Cawongla Road.


    CURRENT WORKS

    Nimbin Road

    Roadworks have commenced on two landslip sites on Nimbin Road that have been identified as significantly impacted by the February 2022 natural disaster. Funding was secured through the Disaster Recovery Funding Arrangement (DRFA). This funding is allocated to repair damage sustained during the February 2022 natural disaster only.

    Works have already commenced at both sites, with Site 1 is approximately 1 km from Nimbin and Site 2 is approximately 4 kms from Nimbin. The works are currently on program at Site 1 with bulk earthworks now completed and 80 piles out of 240 are now installed. In the following weeks, concrete works are due to commence. At Site 2, there is an approximately 2 weeks delay due to the requirement to construct additional erosion protection to stop the soil washing away in heavy rain. The gabion erosion protection will be completed this week and pile installation will commence in 2 weeks’ time.

    The works are expected to occur over 9 months from mid-May 2023 subject to weather, contractor, and material availability. This will involve piling and retaining wall construction works to allow repair of the landslips, reconstruction of pavement, reinstatement of road and guardrail barriers along with installing signs, guideposts, and line marking. Traffic control lights remain in place and existing single lane traffic control will remain in place during the works period. Council would like to thank the residents of the region for their patience during this time.


    Pavement Investigations

    Council staff are continuing to perform pavement investigations involving drilling operations on the following roads:

    • Blue Knob Road
    • Jiggi Road
    • Gwynne Road
    • Nimbin Road

  • Flood Restoration - Roads & Bridges Update (Dec 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au


    CURRENT WORKS – SEALED & UNSEALED ROADS

    Jiggi Road

    Works have been completed on Jiggi Road to address immediate issues caused from the February and March 2022 floods. This has involved DGB20 overlay, pavement stabilisation, trimming and sealing of the road surface to repair flood damages. Further assessment is required and works will continue in 2023-24.

    Jiggi Road before and after images

    Ashlin Road

    Overlay and drainage works are now completed on Ashlin Road to repair damages caused from the February and March 2022 floods. Ashlin Road before and after images Leeson Road

    Overlay and drainage works are now completed on Leeson Road to repair damages caused from the February and March 2022 floods. Leeson Road before and after images

    Upper Tuntable Falls Road

    Repair work was recently carried out for Upper Tuntable Falls Road. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.

    Upper Tuntable Falls Road before and after images


    Wallace Road

    Wallace Road has recently undergone repair work up to the landslip. Overlay and drainage works are now completed to restore damages caused from the February and March 2022 floods.

    Wallace Road before and after images

    COMPLETED WORKS – EMERGENCY ROAD REPAIRS

    Tatham Road

    Works were completed on Tatham Road to remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.

    Tatham Road before and after images

    Tucki Road

    Tucki Road works have removed and replaced existing material from the road surface, graded and rolled the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.

    Tucki Road before works image

    CURRENT WORKS – SEALED ROADS

    Riverbank Road

    Works are continuing for Riverbank Road to repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stabilise, trim and seal road surface to repair flood damages.

    Riverbank Road before and after

    CURRENT WORKS – UNSEALED ROADS

    Corndale Road

    Corndale Road continues to undergo works to replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March 2022 floods.

    Corndale Road before and after images


    East Road

    Overlay and drainage works are currently being carried out on East Road to restore damages caused from the February and March 2022 floods.

    East Road before and after images


    Terania Creek Road

    Work is currently underway between The Channon and Lawler Road on Terania Creek Road due to a landslip after Lawler Road. Overlay and drainage work are underway to repair damages caused from the February and March 2022 floods.

    Terania Creek Road before and after images


    CURRENT WORKS – EMERGENCY ROAD REPAIRS

    Keerrong Road

    Works are continuing along Keerrong Road to overlay, stabilise, trim and seal road surface to repair damages from the February and March, 2022 floods.

    Keerrong Road works


    Tuntable Creek Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.

    Tuntable Creek Road works

    Leycester Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.


    Leycester Road before works



    CURRENT WORKS – DRAINAGE WORKS

    Keerrong Road

    Drainage works are continuing for Keerrong Road these include desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.

    Keerrong Road works


    CURRENT WORKS – RESTORATION WORKS

    Tuntable Creek Road

    Restoration works are continuing along Tuntable Creek Road. Landslip repairs are currently underway through stabilisation works to allow rehabilitation of landslip and reinstatement of road and guardrail barrier.
    Embankment failure before restoration works


    The photos below outline the restoration effort including works performed by a 16-tonne hydraulic crawler mounted drill rig. This remote operated machine is designed for geotechnical site investigations and is drilling around 8m into the embankment.

    Restoration works


    FUTURE WORKS - SEALED ROADS

    Cawongla Road / Quilty Road

    All preliminary works on Cawongla Road are completed ready to commence works on the 3rd of January 2023. Quilty road has been graded and prepared for the detour route to commence on the 3rd of January 2023, vegetation trimming has been completed and drainage works have also been completed. These works have been completed with great cooperation for the public. For further information on the work, visit the Cawongla Road update
  • Flood Restoration - Roads & Bridges Update (12th Dec 2022)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROAD PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au


    CURRENT WORKS – SEALED ROADS

    Riverbank Road

    To repair the issues caused from the February and March 2022 floods, restoration works have been performed on Riverbank Road. These involved overlay, stablise, trim and seal road surface height to repair damages.

    Image: Riverbank Road flood damage


    Jiggi Road

    Likewise, Jiggi Road has undergone recent works to address issues caused from the February and March 2022 floods. This has involved overlay, stabilise, trim and seal road surface height to repair damages.

    Image: Jiggi Road flood damage



    CURRENT WORKS – UNSEALED ROADS

    Braidwood Road

    Braidwood Road has recently had unsealed road works completed, the below image outlines the after result for the road.


    Image: Braidwood Road completed works


    Ashlin Road

    Ashlin Road recently underwent repair works, these are now completed. The image below shows the before image of the roads condition.


    Image: Ashlin Road before works


    Leeson Road

    Unsealed road works were recently completed for Leeson Road. The below image outlines the before condition of the road.


    Image: Leeson Road before works


    Upper Tuntable Falls Road

    Repair work was recently carried out and are now completed for Upper Tuntable Falls Road. The image below shows the before image of the roads condition.


    Image: Upper Tuntable Falls Road before works



    CURRENT WORKS – EMERGENCY ROAD REPAIRS

    Tatham Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.


    Image: Tatham Road before works


    Tucki Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.


    Image: Tucki Road before works



    CURRENT WORKS – DRAINAGE WORKS

    Keerrong Road

    Desilt and reshape table drainage, while installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.


    Image: Keerrong Road



    FUTURE WORKS – SEALED ROADS

    Corndale Road

    Replace existing road surface, stabilise, trim and seal of existing road surface height to repair damages from the February and March, 2022 floods.


    Image: Corndale Road


    Keerrong Road

    Overlay, stabilise, trim and seal road surface height to repair damages from the February and March, 2022 floods.


    Image: Keerrong Road



    FUTURE WORKS – UNSEALED ROADS

    East Road, Mountain Top Road, East Road, Terania Creek Road & Wallace Road

    Planning is in place to perform works shortly on the following unsealed roads: Terania Creek Road (Section before the landslip), Wallace Road, Mountain Top Road, and East Road.



    FUTURE WORKS – EMERGENCY ROAD REPAIRS

    Tuntable Creek Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. A planned return is scheduled for 2023 to complete permanent works.


    Image: Tuntable Creek Road


    Leycester Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.


    Image: Leycester Road before works


    Keerrong Road

    Remove and replace existing material from the road surface, grade and roll the road with a temporary seal over the new surface. With a planned return to complete permanent works in 2023.

  • Flood Restoration - Roads & Bridges Update (5th Dec 2022)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROAD PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au


    Sealed Pavements

    Nimbin Road
    Pavement works have been completed at Nimbin Road near the intersection of Shipway Road.

    Pavement works for Nimbin Road near Shipway Road intersection

    Riverbank Road

    Works have started at Riverbank Road to complete permanent pavement stabilisation works consisting of overlaying 150mm of DGB20 then mixing a conforming road pavement.

    Riverbank Road pavement stabilisation works

    Jiggi Road

    The team are continuing to undertake pavement repairs on various sections of Jiggi Road.Identified pavement repairs required on Jiggi Road


    Drainage Work

    Riverbank Road

    The following photos outline the completed drainage work for Riverbank Road.

    Completed Riverbank Road drainage works


    Emergency Temporary Pavement Repair

    Rock Valley Road / Cawongla Road

    Sections of temporary road pavement which have been identified and planned for return early next year.


    Pavement identified are requiring works for Rock Valley Road and Cawongla Road


    Tatham Road

    Sections of road pavement which have been temporarily with a planned return early next year


    Tatham Road temporary pavement identified are requiring works



    Unsealed Pavements

    The team have completed unsealed pavement works at Gordon Road, Parmenter Road, Savins Road, Houlden Road, Nightcap Range Road and Whian Whian Road.


    Unsealed pavements completed for Houlden Road, Gordon Road, Savins Road and Parmenter Road


    Culverts

    Cawongla Road

    Multiple culvert works are now complete along Cawongla Road. These include culverts near Larnook School with 1 x 900mm and 1 x 600mm culvert successfully replaced and material being stockpiled for replacement of a twin cell 1350mm culvert (culvert with deep depression within the roadway). These works will continue until Christmas, after which the road closure and replacement works can be undertaken. Additionally, material is being stockpiled for replacement of Twin cell 1800mm culvert at 169 Cawongla Road, these works will continue until Christmas, after which the road closure and replacement works can be undertaken. It is anticipated that the tree lopping within this area will be completed prior to Christmas.


    Quilty Road detour route works

    Currently works are being undertaken to upgrade Quilty Road to ensure adequate width of the gravel pavement for two lane traffic and to improve road pavement surface.


  • Flood Restoration - Roads & Bridges Update (Nov 2022)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROAD PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au


    Tuntable Creek Road temporary access works

    Geotechnical drilling is continuing to refine the design to provide temporary road access.

    The road is completed closed to pedestrians from Monday, 28 November 2022 to allow emergency soil nailing works to take place.

    Image 1: “Slikenslide” (Geotech term) – evidence of historic landslip at this location (Note: the yellow flecks are unfortunately not gold!) Image 2: Tuntable Creek Road – current landslip site

    Gravel roads repair works continuing in Precinct 12 (Fraser and Ridgewood Roads)

    Image: Fraser & Ridgewood Roads


    Temporary stabilisation of landslip on Stony Chute Road

    Currently one lane of traffic is open between Whitney and Stanger Roads. During investigation works for the permanent design it was noted that the open lane was at risk of failure due to scour and erosion. A temporary solution using rock to buttress the open face was developed and works were completed last week. Further works are ongoing to repair damaged temporary pavement along Stony Chute Road.

    Image: Stony Chute Road Landslip


    Heavy patch pavement

    Works are continuing on Blue Knob Road, Jiggi Road, Nimbin Road and Riverbank Road. Riverbank Road has traffic restrictions in place for driver safety through the work sites.Image: Blue Knob & Nimbin Pavement Works





  • Jiggi Road - Flood Restoration Works Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Council will be completing works to improve road conditions and associated safety for Jiggi Road during November 2022 and February 2023, subject to weather, contractor, and material availability.

    These works were scheduled and started earlier this year, however delayed due to weather. Scope of works have been reviewed to ensure damages due to heavy rainfall are remediated. Single lane traffic control will be in place during the works period.

    Works will apply to six sections of Jiggi Road only, that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments. Funding has been secured through Transport for NSW and is allocated to repair damage sustained during the February 2022 natural disaster only. Additional works required and subsequent funding for Jiggi Road are being reviewed.

    A map of the allocated sections is attached below. Please note, only temporary works will be completed for Patch 5 at this time. Due to the scope of works required, this section is scheduled for reconstruction at a later date.

    What do the roadworks involve?

    • Road surface: Improve the surface of the road in specified sections.
    • Signs and line marking: Line marking and guideposts.
    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required. Minor drainage works will be completed prior to pavement works commencing.
    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    Road users are advised to follow signage and expect delays as these works are completed.

    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Jiggi Road – Flood Restoration Works.’

  • Current Project Updates Tuesday, 11 October 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au

    Caniaba Road - Shoulder widening and kerb and gutter installation completed, awaiting pavement backfill against kerb.

    Caniaba Road

    Blue Knob Road - Drainage and preparation work started this week, with further stabilisation works scheduled on various sections for next week - subject to weather, contractor and material availability. The landslip is being monitored as scope of works is determined.

    Gravel road repairs - Young Road, Noble Road, Robb Road, Milgate Road, Beardow Road, Browning Road, Fairfull Road, Gibson Lane have all undergone maintenance. Upcoming maintenance is scheduled for Webber Road, Cook Road, Tulk Road, Fraser Road, Rose Road, Wybelena Road and Gray Road.

    Gundurimba Road - Drainage works are scheduled for completion on various sections.

    Gungas Road - Emergency culvert repair on Gungas Road, following damage sustained after recent heavy rainfall.

    Gungas Road - emergency repairs

    James Gibson Road - Temporary patching is scheduled, while scope of works for remediation is finalised.

    Jiggi Road - First section has been completed, with an additional five to be completed. There have some delays due to weather, with scope of works reviewed to ensure damages due to heavy rainfall are remediated. Proposed works include pavement rehabilitation and drainage works.

    Keerrong Road - Final stages of works, with a tidy up to be completed. Additional sections are scheduled for maintenance in December.

    Nimbin Road - Drainage and Stabilisation are being completed on Nimbin Road with four patches completed out for the six scoped for repair. Guide posting and line marking works still to be completed. Stabilisation works are also scheduled for Nimbin Road (near Shipway Drive and Swift Road) in the coming weeks - subject to weather, contractor and material availability.

    Pinchin Road - Final stages of completion on the sections of heavy patching works.

    Pinchin Road - heavy patching completed

    Sexton Bridge - Bridge deck pour and earthworks are currently being completed.

  • Current Road Project Updates 26 September 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au

    Canaiba Road - Shoulder widening and kerb gutter installation completed. Awaiting pavement backfill against the kerb.

    Cowlong Road - Final stage of construction has been completed. Drainage currently undergoing review.

    Crofton Road - Damages have been scoped, and will be submitted this week.

    Dunoon Road - Approved for heavy patch stabilising in flood damaged sections. Schedule of works to be confirmed shortly.

    Fernside Road - Fernside Bridge side-track bitumen sealing and culvert shotcrete application completed.

    Gravel road repairs - Numulgi Creek Road, Beddoes Road, Borton Road will be undergoing repairs this week. Gravel road maintenance continues for Precinct 12 (Corndale, Dunoon and Rosebank). Gravel Roads in Precinct 11 (The Channon, Terania Creek and Tuntable Creek) scheduled for October.

    Gray Road - Works are progressing, with drainage still to be completed. Vegetation management is currently being reviewed.

    Gungas Road - Erosion protection works to commence shortly.

    Jiggi Road - Some sections have been completed, with additional pavement repair works still to be scheduled. These works will continue as subsequent projects are completed in the area, to ensure efficiency.

    Keerrong Road - Culvert replacement between Keerrong Bridge Road and Nimbin Road. Single lane road closure will be in place as works are completed. Please adhere to road signage and drive with caution.

    Koonorigan Road - The landslip area has been assessed, and safe for motorists. Please drive to the conditions. This will continue to be monitored and is under review for works. Heavy patch stabilising has been approved, and received funding. Emergency patching adjacent to the hall is scheduled to commence shortly.

    Nimbin Road - A total of six heavy patching sections to be repaired. All drainage works have been completed on first three patches, with drainage works on the final three to be completed by end of next week. Approximately 1km of the first patch has been sealed, with seal on the other half of this section still to be completed.

    Northcott Road - Final stage of Northcott Road has been completed.

    Pinchin Road - Five heavy patching sections have been completed. One additional section remaining; only final trim and seal left to be completed. All drainage works and embankment failure/slip remediation completed (gabion wall constructed, damaged pipe replaced, road surface and pavement reinstated).

    Richmond Hill Road - Damaged section of pavement adjacent to Richmond Hill landslip resealed. Further shoulder work, guide posting, and line marking still to be completed.

    Sexton Bridge - Abutment works underway. Installation of both abutments’ formwork on Wednesday 14th September with concrete poured Thursday 15th September. Bridge beams have now been landed, with skirting and abutment concrete pouring scheduled for the coming week (weather permitting).

    Tuckurimba Road - Temporary pothole repairs have been completed on a number of major potholes. Due to the low lying nature of the road, a flood study is required prior to permanent heavy patching works. These heavy patching works may change the road level, further details will be shared following assessments.

  • Current Road Project Updates 5 August 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Gravel Roads (Flood Repair Works) – approximately 50% of LCC Gravel Roads have been repaired now since the Feb/March 2022 events.

    Caniaba Road – Drainage and shoulder widening works progressing well. Project is currently running to plan with minimal delays.

    Richmond Hill Road – the landslip has been repaired and pavement rehabilitation works are progressing.

    Nimbin Road near Goolmangar School – urgent maintenance works were carried out last week, the damaged sealed pavement was returned to gravel. This section of road will be overlaid with new gravel and stabilised this month

    Keerrong Road Bridge – the new concrete bridge is now complete and earthworks progressing on the approaches

    Henson Bridge – Piling is now complete, works progressing well on preparing the bridge abutments (form/reo/poor)

    Keerong Road – Landslip and drainage remediation works are commencing, leading to a road closure from August 10th - adjacent to 1265 Kerrong Road. Motorists are advised via roadside signage. Pavement strengthening works are also progressing on approximately a 1km section. Further pavement works are scheduled.

    Bruxner Highway at Northcott Road – pavement rehabilitation works are progressing which have included stabilisation of the existing material and overlay with new gravel.

    Gungas Road – shoulder widening and pavement works are progressing.

    Cowlong Road – pavement strengthening works are progressing south of McKenzie Road.

    Jiggi Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    Pinchin Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    One section of Jiggi Road, preconstruction on 04/08/22

    Wyrallah Road - Geotechnical drilling to determine scope of works.

    Drilling at Wyrallah Road 27/07/22

    Dunoon Road (near the Macadamia Factory) - Temporary patching on a section of road adjacent Macadamia factory on Dunoon Road. This section of road is due for full pavement reconstruction in October this year.

    a section of Dunoon Road before temporary patching 02/08/22

  • Planned Flood Restoration Maintenance Works – Jiggi Road

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Council plans to undertake roadworks on sections of Jiggi Road.

    This planned work is proudly funded by both the New South Wales (NSW) and the Australian Governments.

    Where are the roadworks?

    The roadworks will apply to numerous sections on Jiggi Road between Nimbin Road and Mountain Top Road.

    Why do the roadworks?

    The roadwork will improve road conditions and associated safety, and funding has been allocated due to the February and March 2022 flooding events.

    What do the roadworks involve?

    The roadwork is to improve road safety through the following:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 150mm.

    • Signs and line marking: Line marking and guideposts.

    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.

    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.

    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    These works will be completed under single lane traffic control.

    When do the roadworks start?

    Works will be undertaken between August 2022 and February 2023. Once works commence, they should take approximately 5-6 months to complete (weather permitting).