Category Skyline Road   Show all

  • Skyline Road South (Dec 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    TEMPORARY ROAD CHANGES

    Council wishes to advise that geotechnical investigations on Skyline Road South require a temporary road change. The works will involve closing one lane of the road for three days, 13 to 15 December 2023, from 8:00am to 5pm, subject to change pending weather conditions.

    A single lane closure will be required around the works zone with the section located approximately 1.5kn north of the Skyline South Road and Tregeagle Road Intersection.

    Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.


    What are the works?

    Following the February 2022 natural disaster, Skyline Road South suffered extensive damage. Funding has now been secured to complete geotechnical investigations using a drilling rig to understand subsurface conditions.


    Further Information

    We apologise in advance for any disruptions you may experience while we carry out this essential work. Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Skyline Road South – Dec 2023 Update.’

  • Flood Restoration - Roads & Bridges Update (Sept 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Bungabbee Road

    Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Dudgeon Road Bridge

    Works were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Major Flood Recovery Works Map

    Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.


    CURRENT WORKS

    Nimbin Road

    Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.


    Keerrong Road

    Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.


    Geotechnical Investigations

    The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.

    Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.

    Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.


    Cawongla Road

    Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.

  • Geotechnical Investigations & Survey (Aug 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Interim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.


    Commencing - 4th of September
    Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.


    Commencing - 18th of September

    Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.


    Commencing - 16th of October

    Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road


    There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’

  • Skyline Road - Geotechnical Drilling

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ***Update Thursday 1 September, 2022***

    South Skyline Road closure will be extended until Wednesday 7/9/2022 next week due to difficult drilling conditions. We are aiming to have the rig off the road, and the road opened up over the weekend.***



    Following the February 28 and March 2022 events, Skyline Road has suffered damage due to a landslip, adjacent to 353 Skyline Road. Funding has now been secured to complete remediation works.

    To undertake remediation, geotechnical drilling under engineer supervision is required. Instruments to monitor further ground movement and water table will be installed for monitoring, to assist designers and determine the scope of works.

    Drilling is expected to commence this week. Motorists will be advised via roadside signage. A track is available each way allowing access past the slip. Please use caution and drive carefully.

    Further updates, including commencement of construction for remediation at a later date will be shared via the News Feed tab of this page.

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Skyline Road Landslip’ in your correspondence.

  • Current Road Project Updates July 22 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Fernside Bridge

    The side-track is still on schedule to be open to traffic by 29th July, pending weather. Additional pipes for higher creek flows have been installed as an added precaution.

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 25th – 29th July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation. (Updated and postponed due to illness in the specialist contracting team)

    Koonorigan Road

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Regional Roads - Damaged Sealed Roads

    Approval has been received for the proposed scope of work to heavy patch six sections of Nimbin Road. Heavy patching consists of cutting off high shoulders, box out soft spots, overlay gravel where required, stabilise (nominal 1.5% slag/lime), compact, trim and seal. The procurement of a specialist stabilising subcontractor is underway. Scope has also been approved for Blue Knob Road, Dunoon Road, Kyogle Road and Wyrallah Road (excluding the Wyrallah Village). Wyrallah Village will be the subject to a reconstruction as it is not suitable for heavy patching.

    Precinct 1 - Damaged Sealed Roads

    Heavy patching has been approved for Graham Road, Gundurimba Road, River Bank Road, Rous Road, Skyline Road and Tuckurimba Road.

    Wyrallah Road Landslips

    Geotechnical drilling will take place under traffic control lane closures at 257 Wyrallah Road and 896 Wyrallah Road at the end of July.

    Johnston Road (Clunes)

    Geotechnical works will take place on the week of the 1st of August. This road, currently accessible to locals, will be fully closed during the works.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week (subject to weather)

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is still underway.

    Mountain Top Road

    Geotechnical drilling is still underway.

  • Flood Recovery Heavy Patching Program

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Flood Recovery Heavy Patching Program –

    Restoration of road surface, possible change in road level.

    Segments of the following have been identified for heavy patching works to repair flood damage to road surface.

    Precinct 1

    Graham Road

    Gundarimba Road

    River Bank Road

    Rous Road

    Skyline Road

    Tregeagle Road

    Tuckurimba Road

    Tucki Road

    Wybelena Road

    Precinct 2

    Bagotville Road

    Broadwater Road

    Kilgin Road

    Mathieson Lane

    Precinct 3

    Tatham Road

    Precinct 4

    Nimoola Road

    Pelican Creek Road

    Precinct 6

    Back Creek Road

    Precinct 7

    Axford Road

    Martin Road

    McGuinness Road

    Rock Valley Road

    Precinct 8

    Boggumbil Road

    Davis Road

    Jacobson Road

    Jiggi Road

    Potessu Road

    Rosehill Road

    Precinct 9

    Anderson Road

    Basil Road

    Cecil Street

    Crofton Road

    Gungas Road

    Lillian Rock Road

    Moffitt Road

    Sibley Street

    Symonds Road

    Thorburn Street

    Precinct 10

    Booerie Creek Road

    Boyle Road

    Keerrong Road

    Precinct 11

    Koonorigan Road

    Pinchin Road

    Terania Creek Road

    The Channon Road

    Tuntable Creek Road

    Precinct 12

    Dorroughby Road

    Duncan Road

    James Street (Dunoon)

    Middleton Way

    Nightcap Range Road

    Rocky Creek Dam Road

    Precinct 13

    Corndale Road

    Hunters Hill Road

    Grace Road

    James Gibson Road

    Precinct 14

    Boatharbour Road

    Eltham Road

    Humpty Back Road

    Regional Roads

    Blue Knob Road

    Coraki Road

    Dunoon Road

    Nimbin Road

    Wyrallah Road

    Bridge Street (Wyrallah)

    Kyogle Road


    These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.


    Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.


    How will the works affect traffic?

    Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.


    What do the works involve?

    These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.


    The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.

    This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.


    All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.

    What happens now?

    If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:

    • Via the ‘Submissions’ tab of this article HERE.
    • Email to council@lismore.nsw.gov.au
    • Call to Council (02) 6625 0500
    • In writing to Lismore City Council, PO Box 23A, Lismore 2480