  • Wyrallah Road - Pavement Works (Jan 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Following the 2022 natural disaster, Wyrallah Road suffered extensive damage. Works will begin from the end of January for pavement rehabilitation, please refer to the map provided for an overview of the location.


    All works will be completed under single lane traffic control, this will be implemented from January 30th 2023 for 4 months with a planned completion in late May 2023, subject to fine weather, between the hours of 7am and 5pm. This planned single lane road closure will allow Council to preform reconstruction work on Wyrallah Road preforming numerus tasks mentioned within this letter throughout the 500m stretch of the road.


    Funding has been secured through Transport for NSW. This funding is allocated to repair damage sustained during the February 2022 natural disaster only. Additional works required and subsequent funding for Wyrallah Road are being reviewed.


    We apologise in advance for access disruptions you may experience during these construction activities, and we thank you in anticipation of your cooperation and patience during these essential works.

    Map outlining approximate location of the Wyrallah Road single lane closure

    What are the works?


    The works will reconstruct and rehabilitate approximately 500m of Wyrallah Road. These works include removing approximately 400mm of shoulder material and replacing this section with roadbase through the first 100m of the project from Lismore. Then, approximately 100mm of the existing surface will be overlaid and stabilised. Throughout the remaining 250m length of the road, crews will remove unsuitable material to an approximate depth of 600mm below existing heights and replace it with 500mm of rock, and 350mm of roadbase. This will result in an increased road height of approximately 250mm from the existing height to the finish surface height. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed.


    When are the works taking place?

    Works are scheduled to start from January 30th and are expected to take about four months to complete, subject to fine weather conditions. Daily work hours will mostly be between 7am and 5pm weekdays, although there may be some weekend work.


    What will be the traffic controls/detours?

    Due to the intensive nature of roadworks and associated traffic controls, there will unfortunately be some traffic disruptions. These traffic controls will include single land road closure. This will ensure the roadworks are completed in a timely manner, with safety as a predominant factor, by eliminating traffic through a single lane of this road throughout the construction footprint. Throughout the construction period there may be periods where 24/7 portable traffic lights will be needed to keep a travel lane closed overnight.

    Local access to residences will be maintained by actively managing residents’ needs within the construction footprint to allow access to homes, however, please be aware of delays. Electronic billboard signage will notify motorists of detours via Lismore and Tregeagle Road. Updates will also be available via Live Traffic NSW and Your Say (page details below). Road users are advised to seek alternate routes, as single lane closures are likely to cause heavy traffic delays.

    Please commute through the job sites at low speed, obey traffic control instructions and drive carefully.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Wyrallah Road – Pavement Works.’

  • Current Road Project Updates July 22 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Fernside Bridge

    The side-track is still on schedule to be open to traffic by 29th July, pending weather. Additional pipes for higher creek flows have been installed as an added precaution.

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 25th – 29th July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation. (Updated and postponed due to illness in the specialist contracting team)

    Koonorigan Road

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Regional Roads - Damaged Sealed Roads

    Approval has been received for the proposed scope of work to heavy patch six sections of Nimbin Road. Heavy patching consists of cutting off high shoulders, box out soft spots, overlay gravel where required, stabilise (nominal 1.5% slag/lime), compact, trim and seal. The procurement of a specialist stabilising subcontractor is underway. Scope has also been approved for Blue Knob Road, Dunoon Road, Kyogle Road and Wyrallah Road (excluding the Wyrallah Village). Wyrallah Village will be the subject to a reconstruction as it is not suitable for heavy patching.

    Precinct 1 - Damaged Sealed Roads

    Heavy patching has been approved for Graham Road, Gundurimba Road, River Bank Road, Rous Road, Skyline Road and Tuckurimba Road.

    Wyrallah Road Landslips

    Geotechnical drilling will take place under traffic control lane closures at 257 Wyrallah Road and 896 Wyrallah Road at the end of July.

    Johnston Road (Clunes)

    Geotechnical works will take place on the week of the 1st of August. This road, currently accessible to locals, will be fully closed during the works.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week (subject to weather)

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is still underway.

    Mountain Top Road

    Geotechnical drilling is still underway.