Category Zouch Road   Show all

  • Flood Restoration - Roads & Bridges Update (Mar 2024)

    Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Mar 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS
    Black Road
    Temporary repair works were completed on Black Road to restore access to properties for residents. This involved importing some additional rock, stabilising the current structure with no fines concrete, and adding some additional surface material to ensure the crossing remains trafficable while the design for a new structure is under way.


    Dorroughby Road
    The Dorroughby Road landslip restoration project is now completed with motorists excitingly driving the stretch over road in mid-March. The works involved stabilising the landslip embankment, installing drainage, and constructing a new road pavement. We would like to thank the community for their patience during the construction and the positive feedback we have received from road users who are enjoying this new section of the road.

    Industry Drive
    During March work crews constructed a gabion wall to improve drainage prevent future erosion on Industry Drive. The works were completed under the watchful eye of nearby preschool children, who demonstrated great anticipation at the fence each day as they watched eagerly what the machinery would do next. A highlight for our crews as they witnessed the children’s smiling faces observing the works. Thank you to the local community for your support during these works.

    Johnston Road
    Works are now complete on a storm water outlet on Johnston Road. These works included reinstating the rock erosion protection and the concrete around the top of the precast headwall.

    Road Maintenance Works - Gwynne Road, Stony Chute Road & Tuntable Falls Road
    A busy month for our maintenance crews with staff inspecting and providing maintenance on many roads throughout the region. After listening to community concerns Gwynne Road, Stony Chute Road and Tuntable Falls Road were added as priority maintenance works. To improve road conditions, crews provided pothole repairs on Stony Chute Road and Tuntable Falls Road along with light grading and filling potholes for the sealed section of Gwynne Road.


    CURRENT WORKS
    Crofton Road
    Road pavement restoration works have commenced on Crofton Road for the locations identified below. The works will occur for approximately two to three months, subject to weather conditions. The road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.


    Newton Drive
    Works have commenced on several minor upslope landslips and a single pipe culvert. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.

    Nimbin Road
    Works are progressing on Nimbin Road at the site near Shipway Road. During the past month, on the southbound lane, work crews have removed the asphalt and base material along with reshaping and installing drainage. The road pavement was also constructed, compacted, and rolled along the full width of the road. Following this, the steel barriers on top of the retaining wall were installed, allowing the traffic to shift back to the northbound lane. Next month, works are scheduled to construction drainage along the retaining wall and complete placement of the road base layers along the full width of the road. This will be followed by sealing and asphalting along the full width of the road, installing guardrails and construction of the gabion basket wall extension ready for the anticipated opening on the road in May.


    Milgate Road
    Works have commenced on Milgate Road involving road surface and drainage repairs.


    Rogerson Road
    The team are continuing to implement the appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We will provide further update when available. Thank you to the community for your patience and understanding.

    Rosebank Road
    Landslip restorations are underway at Rosebank Road. The works involve reinstating the property access track and restoring the batter and table drain along the road edge.


    Terania Creek – Bridge Updates
    The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.

    Tuntable Creek Road
    During March, maintenance works were completed on Tuntable Creek Road from Young Road heading back down the hill approximately 500m. These works involved reshaping of table drains, slashing and minor landslip remediation.


    Upper Tuntable Falls Road
    Works are underway on two landslip sites on Upper Tuntable Falls Road located near the Tuntable Falls Primary School. During the past month, a site office was established and works commenced to reinstate the existing open drains. Temporary ramps were also constructed to allow trucks entry to the slip area. The works are expected to take 6-8 weeks weather permitting.


    Zouch Road
    Priority works have commenced for Zouch Road. This will involve with a light grade and repairs to the road surface.


    FUTURE WORKS
    Gwynne Road
    Gwynne Road is currently out to design; the design will take approximately one month. After this, the project will go to tender with work will be starting on the road in approximately 8 weeks.

    Magellan Street
    New guardrails will be installed on Magellan Street in the location identified on the map below during April. The road will remain open with works completed under single lane traffic control to have minimal impact on road users.

  • Flood Restoration - Roads & Bridges Update (Jan 2024)

    Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Jan 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Jan 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Geotechnical Investigations
    During the month our contractors closed single lanes for works on Orion Street, Skyline Road South, Tuntable Creek Road, and Zouch Road to perform geotechnical investigations. This involved using a drilling rig to understand subsurface conditions. We would like to thank residents for your patience and resilience during this time. All landslip geotechnical investigations have now been completed with the bridge investigations underway and expected to also be completed by the middle of February.

    Eltham Road
    Recently, funding was secured to install guardrail on Eltham Road. These works were completed late January with a road closure in place around the site. There was a road closure between Houghlahans and Humpty Back roads and we thank the community for their patience during the road closure.

    Quilty Road
    Works were recently completed on Quilty Road to repair pavement damage and replace a culvert to return the road to pre-existing conditions. Thank you to the residents for their patience and support during the works.


    Tuntable Creek Road
    As the safety threshold had been exceeded, a road closure was triggered for Tuntable Creek Road on Wednesday 17 January 2024 at the landslip site, between Rose Road and Beardow Road. The shut down was to ensure the safety of motorists and to allow for further monitoring. Geotechnical experts were on site the next day to inspect the site and determined it could be reopened. The road reopened Thursday morning 18 January 2024. The new signs installed in October 2023 assisted to reduce detour times allowing Council to notify residents of the closure before reaching the closed site.



    CURRENT WORKS

    Nimbin Road
    Works are continuing for Site 4km on Nimbin Road, after the successful completion and opening of Site 1Km. Recently work crews completed implementation and maintenance of the erosion control following the heavy rainfall. Placement of approximately 70% of the GWS (No Fines Concrete Blocks) on top of the pile cap and approximately 60m of drainage layer and selected fill behind the retaining wall were also recently completed.


    Guardrails Project
    During the past month our guardrails project has been underway, replacing or installing new guardrails. This is multisite works to repair traffic barriers at road sections damaged during the 2022 natural disaster. Generally, the sites are at road sections over creek crossings. Each work site will require traffic control and the repair will generally be completed within 2 days. Recently, the work crew worked on Eltham and Boatharbour Road. Other road closures will be updated as scheduled work on Live Traffic.


    Terania Creek – Bridge Updates
    The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings completed for bridge 3. Commencement on bridge 2 is scheduled for early February.




    FUTURE WORKS

    Dorroughby Road
    The road closure for Dorroughby Road was unfortunately delayed until 12 February with expected competition approximately 26 February, subject to change pending weather conditions. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing conditions. Road closure will be required around the works zone with the section located approximately 500 meters from the Dorroughby Road/Corndale Road intersection, between 791 Corndale Road and 65 Dorroughby Road. Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.


    Rogerson Road
    A culvert replacement is planned for late February 2024. These works will require a road closure for up to 10 weeks subject to weather and resources availability. The existing culvert was damaged in the February 2022 natural disaster and has funding approved for a replacement structure with concrete pipes.

    Newton Drive
    A number of minor up slope landslips and a single pipe culvert are scheduled to be repaired during February. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.

    Rosebank Road
    Rosebank road slip will have restoration works completed during February. The works involve reinstating the property access track and restoring the batter and table drain along the road edge. Works will be completed under traffic control and will have minimal impact on the residents in this area.

    Johnston Road
    Minor works on a damaged drainage culvert along Johnston Road will be completed in February. This will involve reinstating a rock blanket that was washed away in the February 22 Flood Event. Works will be completed under traffic control and will have minimal impact on the residents in this area.

    Leycester Road
    Council wishes to advise funding has now been secured to reinstate the road to a suitable standard to ensure the community are able to travel safely along this road. The works are schedule to occur July 2024, notwithstanding another disaster event and subject to weather conditions, resources, and contractor availability. During works traffic will be impacted as the works will be carried out under Traffic Control stop/go arrangement and a reduced speed limit. At times traffic users may experience long delays to allow construction of the new pavement. Access to property driveways may be impacted or restricted at times however will ensure property owners are notified prior to this occurring. Motorists will be notified of the upcoming roadworks with VMS boards and updated through www.livetraffic.com closer to construction commencement. Emergency services vehicles will be accommodated if required. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.


    Eureka Road, Graham Road & Haywood Lane
    The design plans have changed for Eureka Road, Graham Road, and Haywood Lane. These sites were originally scheduled for culvert replacement; however, funding has been successfully acquired to upgrade these locations from box culverts to bridges. Currently, design for the project works is in final stages with the bridges due to be delivered to Council late February. The works are to be scheduled after delivery, this is subject to change pending weather conditions, resources, and contractor availability. We apologise in advance for any disruptions you may experience while we carry out this essential work. These works will involve removing the existing infrastructure at each site and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track will be established as a side road. The works will take approximately 6 weeks at each site.

  • Flood Restoration - Roads & Bridges Update (Nov 2023)

    Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Nov 2023) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Cawongla Road
    Recently work crews made the road wider on Cawongla Road around the landslip area. You can locate the exact region through viewing our IntraMaps and selecting ‘Major Flood Recovery Works’ these works are found at damage No. DM00666.


    Geotechnical Investigations
    During the month our contractors closed Wallace Road and Oakey Creek Road to perform geotechnical investigations. This involved using a drilling rig to understand subsurface conditions. We would like to thank residents for your patience and resilience during this time.


    Koonorigan Road
    Road maintenance works were recently completed for Koonorigan Road with a new seal laid to improve the road condition and impact on residents. Geotechnical investigations were also performed during this period, and we would like to thank the community for their continuing patience.

    CURRENT WORKS

    Carabeen Place
    Carabeen Place is progressing on schedule with asphalt now completed at the site. Work crews are finalising works to prepare for a reopening of the site. Thank you to the residents for your patience during the works period.


    Nimbin Road
    The works are progressing on schedule for Nimbin Road with Site Km1.0 is on track to open before the end of the year. The total extension of the remediation works for the site is 120m with 239 piles now installed with the total length of 3,226 linear meters. Additionally, 150m3 of concrete have been used for the construction of the pile cap with 611 blocks placed on top of the pile cap to allow the reconstruction of the road.


    FUTURE WORKS

    Zouch Road
    Following the February 2022 natural disaster, Zouch Road suffered extensive damage. Funding has now been secured to complete geotechnical investigations using a drilling rig to understand subsurface conditions. The full road closure will no longer be in place as work crews have been able to contract a smaller drilling rig for the works. A smaller rig allows the team to establish a temporary track for resident cars to drive through the work zone to access their properties during the works period. As a result of this change, the works will change to occur from 7am to 5pm between the 6th to 15th of December. The works are located approximately between the intersection with Stoney Chute Road and to the west along Zouch Road approximately 400m. Motorists will be notified of further information via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated during these works. Please adhere to all road closed signs and directions from any traffic controllers and expect delays. We apologise for any inconvenience. Further information can be sourced on the original works post:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/zouch-road-drilling-works-nov-2023

  • Zouch Road - Drilling Works - Temporary Track (Nov 2023)

    Share Zouch Road - Drilling Works - Temporary Track (Nov 2023) on Facebook Share Zouch Road - Drilling Works - Temporary Track (Nov 2023) on Twitter Share Zouch Road - Drilling Works - Temporary Track (Nov 2023) on Linkedin Email Zouch Road - Drilling Works - Temporary Track (Nov 2023) link

    The Flood Recovery team work crews have been able to contract a smaller drilling rig for the works occurring next week on Zouch Road. A smaller rig allows the team to establish a temporary track for resident cars to drive through the work zone to access their properties during the works period.

    As a result of this change, the works will change to occur from 7am to 5pm between the 6th to 15th of December. The works are located approximately between the intersection with Stoney Chute Road and to the west along Zouch Road approximately 400m. Motorists will be notified of further information via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated during these works.

    Please adhere to all road closed signs and directions from any traffic controllers, and expect delays. We apologise for any inconvenience.


    Further Information
    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Zouch Road – Nov 2023 Update.’

  • Zouch Road - Drilling Works (Nov 2023)

    Share Zouch Road - Drilling Works (Nov 2023) on Facebook Share Zouch Road - Drilling Works (Nov 2023) on Twitter Share Zouch Road - Drilling Works (Nov 2023) on Linkedin Email Zouch Road - Drilling Works (Nov 2023) link

    Following the February 2022 natural disaster, Zouch Road suffered extensive damage. Funding has now been secured to complete geotechnical investigations using a drilling rig to understand subsurface conditions.

    The works will involve closing a section of the road during 8am to 5pm between December 4th to 8th, 2023. Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Residents will be unable to drive through the work zone. Please adhere to all road closed signs and directions from any traffic controllers. We apologise for any inconvenience.


    Further Information
    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Zouch Road – Nov 2023 Update.’

  • Flood Restoration - Roads & Bridges Update (Sept 2023)

    Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Sept 2023) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Bungabbee Road

    Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Dudgeon Road Bridge

    Works were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Major Flood Recovery Works Map

    Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.


    CURRENT WORKS

    Nimbin Road

    Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.


    Keerrong Road

    Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.


    Geotechnical Investigations

    The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.

    Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.

    Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.


    Cawongla Road

    Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.

  • Geotechnical Investigations & Survey (Aug 2023)

    Share Geotechnical Investigations & Survey (Aug 2023) on Facebook Share Geotechnical Investigations & Survey (Aug 2023) on Twitter Share Geotechnical Investigations & Survey (Aug 2023) on Linkedin Email Geotechnical Investigations & Survey (Aug 2023) link

    Interim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.


    Commencing - 4th of September
    Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.


    Commencing - 18th of September

    Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.


    Commencing - 16th of October

    Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road


    There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’