31 May 2022

Geotechnical works are progressing on Terania Creek Road. Unforeseen geological conditions means drilling to a greater depth than planned, as such will be working on this site until early next week. A full closure is no longer in place, the road is open for light vehicle access only to ensure safety for motorists.

Works on Wallace Road (due to delays on Terania Creek Road) will commence early next week. There will be light vehicle access past works on Wallace Road, however closed to heavy vehicles to ensure safety for motorists.

A temporary crossing will be in place for Black Rd by the end of next week.

The culvert on Ross Road will be cleaned out after completion of Black Road works.

We thank you for your ongoing patience as we work through unforeseen delays. Shall you have any further concerns, please consider posting in the Q&A so we may answer and share updates with the community.

Share 31 May 2022 on Facebook Share 31 May 2022 on Twitter Share 31 May 2022 on Linkedin Email 31 May 2022 link

All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>