July 6 2022
Dunoon Road
Dunoon Road works at Boomerang Creek were completed on June 28th. Additional pothole repair works for Dunoon Road will be completed over the coming weeks.
The Channon Road
Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.
The Channon Road (Robertson Bridge)
Remediation works of the abutments is planned for week starting July 4th. Traffic control will be present, and motorists are advised to drive carefully.
Pinchin Road Embankment failure
Embankment reconstruction works are substantially complete. Pavement repair to the road surface will commence shortly.
Wallace Road
Geotechnical drilling has been completed. Inclinometers have been installed to monitor ground movement over the next month before design to build back better commences.
Keerrong Road
Bridge construction works are now underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August
Tuntable Creek Road
Investigation works north of rose road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.
Duncan Road- Corndale Road
Works have started to heavy patch and stabilise damaged sections.
Nimbin Road (slip north of Stoney Chute)
80% design drawings received and under review. Procurement of contractor proposed for this month.
Stoney Chute Road
Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.
Cawongla Road
Geotechnical drilling is underway.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.