We are pleased to advise the community that we have achieved our first major milestone on Union Street Stage 1, with the southern side of the road now complete and open to one-way traffic.
Works to date have included vegetation removal, installation of stormwater drainage infrastructure including new pits, pipes, kerb and gutters, formalisation of car parking and re-construction of the road pavement.
Works have now transferred to the northern side of the road where we will repeat the road pavement re-construction process.
Works are scheduled to be completed on the northern side of the road by late November (weather dependent), which will then be followed by asphalt works to complete Stage 1.
The full completion of Stage 1 is scheduled for early December.