Corndale Road
Corndale Road is scheduled to undergo stabilisation repairs on a section of severely damaged road pavement from Tuesday, 5 July 2022. Initially drainage works will be completed, installing table drains and clearing shoulders allowing water to escape the pavement.
Following these works, there will be a pavement stabilisation crew mobilising on site to rip up the existing damaged pavement. The road material quality will be improved, by mixing 100mm of new material with the existing road base.
Council expects this work to be completed within 1 week from start to finish, weather permitting.
Signage will be installed over the coming weeks to advise of 'raising road levels'.
A single lane road closure will be provided to allow traffic to travel through the site, with the appropriate signage. Please note this work is scheduled to take place during the school holidays.
If you have questions, please consider utilising the Q+A function of this page. This allows the same information to be shared with our community members. Feedback and questions can also be submitted to Council via email council@lismore.nsw.gov.au or calling (02) 6625 0500.
We thank the community for their patience as we complete this work.