Nimbin Rainbow Walk

Share Nimbin Rainbow Walk on Facebook Share Nimbin Rainbow Walk on Twitter Share Nimbin Rainbow Walk on Linkedin Email Nimbin Rainbow Walk link
Nimbin Rainbow Walk
October 2024 Update

Nimbin Rainbow Walk is coming along beautifully, despite recent rain which has caused a slight delay. The wet weather means we’re expecting a setback of about a week to allow the area to dry out before work continues.

On a positive note, the installation of the bridges is well underway, with galvanised steel girders and balustrades already in place. Over the next two weeks, we anticipate completing the northern bridges, with flooring, timber rails and post in-lays all set to be installed shortly.

We’re also excited to share that the concreting of the path and stairs at the southern entry is nearly complete, with just a small 20-metre section left. Once this is finished, the contractor will move on to complete the third and fourth bridges.

Several key landscaping decisions have been made, including the addition of a charming low rural-style fence for the northern entries, a large recycled timber pergola and new wayfinding signage to guide visitors along the walk.

In terms of environmental progress, our bush regeneration team has removed most of the weeds in the northern area, clearing the way for upcoming planting. A dedicated Landcare Group has also been established for the site, though the first meeting and planting day has been delayed due to last week’s rain.




Background Information

Nimbin Rainbow Walk is a project that aims to construct a concrete and boardwalk track over 750m long for the active community of Nimbin and its visiting tourists.

The project includes: concrete pathways, lighting, interpretive signage, way-finding signage, artwork, small bridges erected over the nearby creek system, park furniture and native plantings.

The total budget of $2.5m is fully funded under the Bushfire Local Economic Recovery Package, which is co-funded by the Australian and NSW governments.


Community input

Council has consulted with property owners and key community members including some of those on the Nimbin Advisory Group. The thoughts and aspirations of what this walking track would look like and how it may best serve the community of Nimbin, and provide for a wonderful tourist attraction to those visiting the township of Nimbin have been incorporated into the concept design.


About the Concept Design

  • The majority of the walk will be on private property where pedestrians will have a right of footway.
  • The track will be maintained by Lismore City Council.
  • Interpretation signage will be discussed in the coming months, but may centre around the Nimbin locality, Aboriginal Cultural Heritage and/or the Aquarius Festival held in 1973.
  • The track will provide for a preferred route for pedestrians from Alternative Way to and from the CBD.
  • A future artwork project to involve local artists
  • Make additional improvements to the creek line flora with weed control and native plantings.
Nimbin Rainbow Walk
October 2024 Update

Nimbin Rainbow Walk is coming along beautifully, despite recent rain which has caused a slight delay. The wet weather means we’re expecting a setback of about a week to allow the area to dry out before work continues.

On a positive note, the installation of the bridges is well underway, with galvanised steel girders and balustrades already in place. Over the next two weeks, we anticipate completing the northern bridges, with flooring, timber rails and post in-lays all set to be installed shortly.

We’re also excited to share that the concreting of the path and stairs at the southern entry is nearly complete, with just a small 20-metre section left. Once this is finished, the contractor will move on to complete the third and fourth bridges.

Several key landscaping decisions have been made, including the addition of a charming low rural-style fence for the northern entries, a large recycled timber pergola and new wayfinding signage to guide visitors along the walk.

In terms of environmental progress, our bush regeneration team has removed most of the weeds in the northern area, clearing the way for upcoming planting. A dedicated Landcare Group has also been established for the site, though the first meeting and planting day has been delayed due to last week’s rain.




Background Information

Nimbin Rainbow Walk is a project that aims to construct a concrete and boardwalk track over 750m long for the active community of Nimbin and its visiting tourists.

The project includes: concrete pathways, lighting, interpretive signage, way-finding signage, artwork, small bridges erected over the nearby creek system, park furniture and native plantings.

The total budget of $2.5m is fully funded under the Bushfire Local Economic Recovery Package, which is co-funded by the Australian and NSW governments.


Community input

Council has consulted with property owners and key community members including some of those on the Nimbin Advisory Group. The thoughts and aspirations of what this walking track would look like and how it may best serve the community of Nimbin, and provide for a wonderful tourist attraction to those visiting the township of Nimbin have been incorporated into the concept design.


About the Concept Design

  • The majority of the walk will be on private property where pedestrians will have a right of footway.
  • The track will be maintained by Lismore City Council.
  • Interpretation signage will be discussed in the coming months, but may centre around the Nimbin locality, Aboriginal Cultural Heritage and/or the Aquarius Festival held in 1973.
  • The track will provide for a preferred route for pedestrians from Alternative Way to and from the CBD.
  • A future artwork project to involve local artists
  • Make additional improvements to the creek line flora with weed control and native plantings.
  • Project Update - May 2024

    Share Project Update - May 2024 on Facebook Share Project Update - May 2024 on Twitter Share Project Update - May 2024 on Linkedin Email Project Update - May 2024 link

    Nimbin Rainbow Road Walking Track
    May 2024 Update

    Lismore City Council is moving ahead with the project despite recent wet weather causing delays to construction by about 3-4 weeks.

    A contractor has now been appointed to manage vegetation along the track. Small design changes have been finalised such as the addition of a new ramp linking the Nimbin Recreation Precinct to improve accessibility to the track.

    Local artists are also progressing beautifully with the construction of the Kombi Konvoy, a series of unique seating designs for placement along the track. Decisions have also been made on furniture, including bespoke sandstone seating and special features to further enhance the beauty, interest and user experience along the trail.

    Wheelchair accessible carparks have also now been identified for placement and wayfinding signage designs are nearing completion.

    Council will post regular updates as the project progresses. To stay up to date on the project, access design plans, explore frequently asked questions, or to find out more, please visit yoursay.lismore.gov.au and visit the Nimbin Rainbow Road Walking Track page.

    Lismore City Council wishes to thank the Nimbin Community, Community Centre, Nimbin Chamber of Commerce and private landowners for making this project possible and for their continued support throughout construction. The project is fully funded under the NSW and Federal Government Bushfire Local Economies Fund.

  • Project Update - April 2024

    Share Project Update - April 2024 on Facebook Share Project Update - April 2024 on Twitter Share Project Update - April 2024 on Linkedin Email Project Update - April 2024 link

    Nimbin Rainbow Road Walking Track
    April 2024 Update

    Lismore City Council is pleased the construction of the Nimbin Rainbow Road Walking Track is underway, with construction of the track expected to be completed in the middle of the year, followed by final art installations, landscaping and wayfinding signage, ready for opening to the public in the second half of 2024.

    The Nimbin Rainbow Road Walking Track is an exciting project to construct a 750m long track, providing the community of Nimbin and its visitors with a safe, fun and active way to enjoy the beauty of the natural environment, as well as connect with cultural and artistic expressions.

    The project includes formed pathways, boardwalks and bridges, providing access to natural areas and landscape views, interpretive and wayfinding signage, local artworks, park furniture and native plantings, including the addition of 5,800 new plantings, providing additional shade and natural beauty to the area, connecting Nimbin’s recreation precinct and Aquarius Way to the vibrant village.

    Construction is underway, along with the installation of one of six installations by local artists, with the remainder being erected throughout the track construction phase. The artwork installations were chosen through an expression of interest process, to provide a wonderful opportunity for the community and visitors to experience local art while exploring the parklands and natural environment. Work is also progressing by chosen production designer, Ross Wallace, on the design of the visual material and signage on and off the track.

    Council will post regular updates as the project progresses and highlight any information that may be relevant to you as a community member or local business.

    To stay up to date, for further information on project updates, design plans, frequently asked questions, or to find out more, please visit www.yoursay.lismore.nsw.gov.au and visit the Nimbin Rainbow Road Walking Track page.

    Lismore City Council wishes to thank the Nimbin Community, Community Centre, Chamber of Commerce and private landowners for making this project possible, delivering an attraction that will be enjoyed for many years to come, as well as providing benefits and opportunities for experiences and businesses in Nimbin.

  • Project Update - February 2024

    Share Project Update - February 2024 on Facebook Share Project Update - February 2024 on Twitter Share Project Update - February 2024 on Linkedin Email Project Update - February 2024 link

    A contractor has been chosen and site works are due to begin in March. The works will take approximately 4 months, with completion expected in June, weather permitting. The artworks have progressed to the extent where a number of them are nearing on-site construction. The artworks will be erected during the process of track construction.

  • Project Update - December 2023

    Share Project Update - December 2023 on Facebook Share Project Update - December 2023 on Twitter Share Project Update - December 2023 on Linkedin Email Project Update - December 2023 link

    Six artwork installations have been chosen through the Expression of Interest. These will be developed and installed by six local artists, and will provide a wonderful opportunity for the community and tourists to experience the artwork whilst exploring the park and the natural environment its set in. The wayfinding signage is also progressing with another local artist. Both artworks and wayfinding is an exciting part of the Nimbin Rainbow Walking Track project, and opening it all to the community is very much anticipated. Opening of the walking track is not expected until approximately July next year.

    There have been minor changes to CBD access for the Track following negotiations with private land owners. The silver lining for the project in this instance is a focus on extending the track towards the caravan park, taking advantage of carparking and providing a recreational link between the caravan park pool, playground, skatepark, bowling club and the walking track.

    Plans for the walking track are currently being tendered. The final costings and estimates will provide a full understanding of the extent of works.

  • Design Stage Completed

    Share Design Stage Completed on Facebook Share Design Stage Completed on Twitter Share Design Stage Completed on Linkedin Email Design Stage Completed link

    The Nimbin Rainbow Road Project has completed the design stage following consultation received. Consultation has brought to the table a good mix of traditional and contemporary themes and ideas that will now form the basis of the track experiences. From artwork, to park furniture and to interpretive signage. These themes and ideas include accessibility functions, security requirements, use of Traditional Owner language, appropriate access to natural areas and landscape views, interpretation of the traditional owners and Nimbin before and after Aquarius, natural area improvements and artworks of all sorts. Thank you everyone that contributed.

    These themes and ideas are being collated by a working group which have the task of sorting them into the priority projects including Artwork, Interpretive Signage and Park Furniture. The structural parts of the track will be advertised for construction in the coming months of March/April. It is anticipated construction wont start any time before July at this stage, depending upon wet weather and the availability of contractors. Completion of the full project is anticipated to be September/October this year.

Page last updated: 03 Oct 2024, 02:24 PM