Rock Valley Road Repairs

Share Rock Valley Road Repairs on Facebook Share Rock Valley Road Repairs on Twitter Share Rock Valley Road Repairs on Linkedin Email Rock Valley Road Repairs link

Consultation has concluded

14 May 2021 Update

The closed section of Rock Valley Road, about 500m south of Boggumbil Road, re-opened today after reconstruction of this section of road due to an earlier collapse of the road’s embankment.
Major reconstruction work was needed to fix the 300m section, including removing the existing road surface and embankment, and significant earthwork to replace the road with new gravel and a bitumen seal, as well as reconstructing the embankment. Check out photos of the roadworks here.
The road was closed between Rosehill Road and Boggumbil Road during the reconstruction works.
We thank the community, and in particular local residents, for your patience during this major reconstruction project.


Background

Lismore City Council is repairing a section of Rock Valley Road, approximately 500m south of Boggumbil Road, where the embankment has failed.

This project will require a section of Rock Valley Road to be closed to traffic for at least eight weeks. A detour will be established for commuters.

Residents whose properties are located within the closed section of Rock Valley Road will continue to have local access to their properties during this time.

What are the works?

The roadworks comprise reconstruction of a 300m section of failed embankment. This includes the following:

  • Clearing of vegetation and trees adjacent to the embankment failure
  • Excavation and removal of the existing road surface and embankment material
  • Reconstruction of the embankment
  • Road surface construction – gravel placement
  • Road surface construction – bitumen seal
  • Signage and line marking

When are the works taking place?

Works are expected to begin in late February and take eight weeks to complete, subject to weather conditions.

Work hours will be as follows:

  • 6am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays (when required).
  • No work Sundays or public holidays.

If there is a requirement to change these hours, residents will be notified.

What are the traffic adjustments?

During construction, Rock Valley Road will be closed between Rosehill Road and Boggumbil Road for the duration of the works. Local traffic access will be retained for residents that live between Rosehill Road and Boggumbil Road.

All other traffic will be detoured around the site via Rosehill Road, Nimbin Road, Jiggi Road and Boggumbil Road (see detour map).

Please commute through the detour at low speed, obey adjusted speed limits and directions from any traffic controllers, and drive carefully. We will ensure all driveways and farm gates that intersect the road match any changes to the road profile and are safe for property owners/residents.

At times the roadworks may create dust, which will be managed by a water cart during work hours.

More information

For more information or if you have questions about the project, please use our online Q&A function below, phone Project Manager Ricky Singh from Civil Consult on 0429 102 241 or email ricky@civilconsult.com.

Thank you for your patience while we complete these essential works.


14 May 2021 Update

The closed section of Rock Valley Road, about 500m south of Boggumbil Road, re-opened today after reconstruction of this section of road due to an earlier collapse of the road’s embankment.
Major reconstruction work was needed to fix the 300m section, including removing the existing road surface and embankment, and significant earthwork to replace the road with new gravel and a bitumen seal, as well as reconstructing the embankment. Check out photos of the roadworks here.
The road was closed between Rosehill Road and Boggumbil Road during the reconstruction works.
We thank the community, and in particular local residents, for your patience during this major reconstruction project.


Background

Lismore City Council is repairing a section of Rock Valley Road, approximately 500m south of Boggumbil Road, where the embankment has failed.

This project will require a section of Rock Valley Road to be closed to traffic for at least eight weeks. A detour will be established for commuters.

Residents whose properties are located within the closed section of Rock Valley Road will continue to have local access to their properties during this time.

What are the works?

The roadworks comprise reconstruction of a 300m section of failed embankment. This includes the following:

  • Clearing of vegetation and trees adjacent to the embankment failure
  • Excavation and removal of the existing road surface and embankment material
  • Reconstruction of the embankment
  • Road surface construction – gravel placement
  • Road surface construction – bitumen seal
  • Signage and line marking

When are the works taking place?

Works are expected to begin in late February and take eight weeks to complete, subject to weather conditions.

Work hours will be as follows:

  • 6am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays (when required).
  • No work Sundays or public holidays.

If there is a requirement to change these hours, residents will be notified.

What are the traffic adjustments?

During construction, Rock Valley Road will be closed between Rosehill Road and Boggumbil Road for the duration of the works. Local traffic access will be retained for residents that live between Rosehill Road and Boggumbil Road.

All other traffic will be detoured around the site via Rosehill Road, Nimbin Road, Jiggi Road and Boggumbil Road (see detour map).

Please commute through the detour at low speed, obey adjusted speed limits and directions from any traffic controllers, and drive carefully. We will ensure all driveways and farm gates that intersect the road match any changes to the road profile and are safe for property owners/residents.

At times the roadworks may create dust, which will be managed by a water cart during work hours.

More information

For more information or if you have questions about the project, please use our online Q&A function below, phone Project Manager Ricky Singh from Civil Consult on 0429 102 241 or email ricky@civilconsult.com.

Thank you for your patience while we complete these essential works.


Consultation has concluded
  • Update on progress: 10 May

    Share Update on progress: 10 May on Facebook Share Update on progress: 10 May on Twitter Share Update on progress: 10 May on Linkedin Email Update on progress: 10 May link

    Ricky Singh, Project Manager for the Rock Valley Road Repairs, has advised that the road will be open at the end of this week - Friday 14 May

  • Update on progress: 22 April

    Share Update on progress: 22 April on Facebook Share Update on progress: 22 April on Twitter Share Update on progress: 22 April on Linkedin Email Update on progress: 22 April link

    Ricki Singh, project manager for the Rock Valley Road repairs has conformed that we are still on track for an early May opening, which will take us to just over 8 weeks from the date that this work started

  • Update on progress: 24 March

    Share Update on progress: 24 March on Facebook Share Update on progress: 24 March on Twitter Share Update on progress: 24 March on Linkedin Email Update on progress: 24 March link
    supporting image

    Despite the wet weather, we are making progress on the installation of the new culvert on the Rock Valley project. Work actually started on 8 March and we are still on track to complete the necessary work within 8 weeks. Please use caution on the current detour and adhere to the sign posted speed limit.