Rock Valley Road Repairs

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

14 May 2021 Update

The closed section of Rock Valley Road, about 500m south of Boggumbil Road, re-opened today after reconstruction of this section of road due to an earlier collapse of the road’s embankment.
Major reconstruction work was needed to fix the 300m section, including removing the existing road surface and embankment, and significant earthwork to replace the road with new gravel and a bitumen seal, as well as reconstructing the embankment. Check out photos of the roadworks here.
The road was closed between Rosehill Road and Boggumbil Road during the reconstruction works.
We thank the community, and in particular local residents, for your patience during this major reconstruction project.


Background

Lismore City Council is repairing a section of Rock Valley Road, approximately 500m south of Boggumbil Road, where the embankment has failed.

This project will require a section of Rock Valley Road to be closed to traffic for at least eight weeks. A detour will be established for commuters.

Residents whose properties are located within the closed section of Rock Valley Road will continue to have local access to their properties during this time.

What are the works?

The roadworks comprise reconstruction of a 300m section of failed embankment. This includes the following:

  • Clearing of vegetation and trees adjacent to the embankment failure
  • Excavation and removal of the existing road surface and embankment material
  • Reconstruction of the embankment
  • Road surface construction – gravel placement
  • Road surface construction – bitumen seal
  • Signage and line marking

When are the works taking place?

Works are expected to begin in late February and take eight weeks to complete, subject to weather conditions.

Work hours will be as follows:

  • 6am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays (when required).
  • No work Sundays or public holidays.

If there is a requirement to change these hours, residents will be notified.

What are the traffic adjustments?

During construction, Rock Valley Road will be closed between Rosehill Road and Boggumbil Road for the duration of the works. Local traffic access will be retained for residents that live between Rosehill Road and Boggumbil Road.

All other traffic will be detoured around the site via Rosehill Road, Nimbin Road, Jiggi Road and Boggumbil Road (see detour map).

Please commute through the detour at low speed, obey adjusted speed limits and directions from any traffic controllers, and drive carefully. We will ensure all driveways and farm gates that intersect the road match any changes to the road profile and are safe for property owners/residents.

At times the roadworks may create dust, which will be managed by a water cart during work hours.

More information

For more information or if you have questions about the project, please use our online Q&A function below, phone Project Manager Ricky Singh from Civil Consult on 0429 102 241 or email ricky@civilconsult.com.

Thank you for your patience while we complete these essential works.


14 May 2021 Update

The closed section of Rock Valley Road, about 500m south of Boggumbil Road, re-opened today after reconstruction of this section of road due to an earlier collapse of the road’s embankment.
Major reconstruction work was needed to fix the 300m section, including removing the existing road surface and embankment, and significant earthwork to replace the road with new gravel and a bitumen seal, as well as reconstructing the embankment. Check out photos of the roadworks here.
The road was closed between Rosehill Road and Boggumbil Road during the reconstruction works.
We thank the community, and in particular local residents, for your patience during this major reconstruction project.


Background

Lismore City Council is repairing a section of Rock Valley Road, approximately 500m south of Boggumbil Road, where the embankment has failed.

This project will require a section of Rock Valley Road to be closed to traffic for at least eight weeks. A detour will be established for commuters.

Residents whose properties are located within the closed section of Rock Valley Road will continue to have local access to their properties during this time.

What are the works?

The roadworks comprise reconstruction of a 300m section of failed embankment. This includes the following:

  • Clearing of vegetation and trees adjacent to the embankment failure
  • Excavation and removal of the existing road surface and embankment material
  • Reconstruction of the embankment
  • Road surface construction – gravel placement
  • Road surface construction – bitumen seal
  • Signage and line marking

When are the works taking place?

Works are expected to begin in late February and take eight weeks to complete, subject to weather conditions.

Work hours will be as follows:

  • 6am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays (when required).
  • No work Sundays or public holidays.

If there is a requirement to change these hours, residents will be notified.

What are the traffic adjustments?

During construction, Rock Valley Road will be closed between Rosehill Road and Boggumbil Road for the duration of the works. Local traffic access will be retained for residents that live between Rosehill Road and Boggumbil Road.

All other traffic will be detoured around the site via Rosehill Road, Nimbin Road, Jiggi Road and Boggumbil Road (see detour map).

Please commute through the detour at low speed, obey adjusted speed limits and directions from any traffic controllers, and drive carefully. We will ensure all driveways and farm gates that intersect the road match any changes to the road profile and are safe for property owners/residents.

At times the roadworks may create dust, which will be managed by a water cart during work hours.

More information

For more information or if you have questions about the project, please use our online Q&A function below, phone Project Manager Ricky Singh from Civil Consult on 0429 102 241 or email ricky@civilconsult.com.

Thank you for your patience while we complete these essential works.


Consultation has concluded

Ask us a question about this roadworks project and our staff will respond as soon as possible. Thank you.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    When will Missingham Road, Dunoon be graded and the gutters cleared out to stop water running down the bank and further gouging out the road?

    Robyn Davies asked almost 3 years ago

    Hi Robyn, I have forwarded your question on to one of our engineers and will make sure I get you a response.

    I have now received a response!

    "Missingham Rd is scheduled for grading works mid June under the Natural Disaster Funding.  Works will include cleaning of drains where required.  Timing of works may change pending weather conditions."

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Hi, Do you have an updated date for the completion of these road works?

    Glen asked almost 3 years ago

    Hi Glen

    Thanks for your question and sorry for the delay in replying. Hopefully you will have seen the update on this page below and will be aware that Rock Valley Road opened on 14 May

    14 May 2021 Update

    The closed section of Rock Valley Road, about 500m south of Boggumbil Road, re-opened today after reconstruction of this section of road due to an earlier collapse of the road’s embankment.
    Major reconstruction work was needed to fix the 300m section, including removing the existing road surface and embankment, and significant earthwork to replace the road with new gravel and a bitumen seal, as well as reconstructing the embankment. Check out photos of the roadworks here.
    The road was closed between Rosehill Road and Boggumbil Road during the reconstruction works.
    We thank the community, and in particular local residents, for your patience during this major reconstruction project.

     

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    When will the rock Valley road reopen

    Carin Moss asked almost 3 years ago

    Hi Carin,

    Ricki Singh, project manager for the Rock Valley Road repairs has conformed that we are still on track for an early May opening, which will take us to just over 8 weeks from the date that this work started. We are posting updates in the News Feed at the bottom of this project page on a regular basis and will be keeping in close contact with the project manager as we get towards the end of April.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Hi. Wondering if Boggumbil Rd will be graded and kept graded and watered during these roadworks.

    Marty asked about 3 years ago

    Hi Marty, we are planning to undertake grading works and keep the road graded as needed throughout the project. There will be higher traffic volumes so we are aware maintenance will be required. We will also use the water cart to keep dust down as the project progresses.