  • Flood Restoration - Roads & Bridges Update (July 2024)

    Share Flood Restoration - Roads & Bridges Update (July 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (July 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (July 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (July 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    CURRENT WORKS

    Blue Knob Road

    Progress on the Blue Knob Road landslip project is progressing well. The drilling and soil nail installation at the first site are complete, and testing is scheduled for early August. Meanwhile, drilling has begun at the second site, and clearing and excavation work are underway at the third and fourth sites.


    Eureka Road

    During this busy month at the construction site, significant advancement has been made. The installation of the side track, driven steel piles, bridge abutments, and rock scour protection is now complete. Towards the end of July, crews completed the bridge deck pour with concrete curing now underway. Following these tasks, the bridge approach works are scheduled to commence in early August.


    Graham Road

    Construction activities for culvert replacement are currently in progress at the site. During the past month, the installation of the side track, piling, and steel driving piles were completed. This allowed crews are to commence installation of bridge components, abutment blinding layer and concrete pour of abutments, all of which are now accomplished. The bridge pour is scheduled for early August with backfilling of abutments to follow prior to bridge opening to motorists.


    Haywood Lane

    Works crews have been busy at site completing the installation of a side track, driven steel piles and bridge abutments. Towards the end of the month placement of rock scour protection, abutment backfilling and bridge deck installation was also accomplished. This made way for the steel works to be finalised with a deck concrete pour completed on July 23. Approach works will commence following completion of Eureka Road works.


    Leycester Road

    Pavement rehabilitation is progressing well with approximately 250m of open drains completed and two culvert replacements installed. Over the next 4-5 weeks, open drainage and culvert works will continue with granular overlay to follow. Bice and Yeager Roads grading will be delayed due to these works.


    Newton Drive

    Repairs are continuing for installation of a new culvert after the previous culvert failed. The road has been slightly diverted as works take place.


    Gravel Roads – Multiple Sites

    Works continue for grading over 150 kms of unsealed gravel roads, which suffered substantial damage due to declared natural disasters in December 2023 and April 2024. The most severely affected roads receive highest priority to expedite critical route restoration. This ambitious project, one of the largest of its kind, involves Council deploying six distinct work crews, strategically clustered geographically to optimise efficiency and resource allocation. Recently completed roads include Gungas Road, Upper Coopers Creek Road, Minyon Falls Road, Wallace Road and Pinchin Road.


    Rogerson Road

    With weather remaining on our side this month at Rogerson Road, construction works were able to continue. The works included four separate concrete pours to produce two custom-sized concrete headwalls, these two headwalls alone saw a total volume of almost 100 cubic metres of concrete.


    Terania Creek Road

    Excitingly, works are now completed for Bridge 3. Crews have completed the concrete approaches at Bridge 2, with installation of structure restraining brackets and concrete footings for guardrail completed. The temporary side track was also removed, and installation of the guardrail is scheduled in the coming weeks. Bridge 1 has works commenced on the concrete approaches following successful installation of a side track.


    FUTURE WORKS

    Repentance Creek Road

    Works will commence 19 August 2024 on Repentance Creek Road. The works will occur for approximately 8 weeks, subject to weather conditions. The road will remain open with works completed under stop/go traffic control to have minimal impact on residents, delays are expected. Funding has been secured for minor pavement rehabilitation and open drainage works. View further details: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/works-notice-repentance-creek-road-jul-2024

  • Repentance creek Road - Pavement & Drainage Works (Jul 2024)

    Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Facebook Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Twitter Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Linkedin Email Repentance creek Road - Pavement & Drainage Works (Jul 2024) link

    Council wishes to advise of upcoming works on Repentance Creek Road. The works will occur for approximately 8 weeks, from 19 August to 14 October 2024, subject to weather conditions.

    The road will remain open with works completed under stop/go traffic control to have minimal impact on residents, delays are expected. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.

    We apologise in advance for any disruptions you may experience while we carry out this essential work.

    What are the works?
    Following the February 2022 natural disaster, Repentance Creek Road suffered extensive damage. Funding has been secured for minor pavement rehabilitation and open drainage works identified on the map below.

    Further Information
    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Repentance Creek Road – July 2024 Update.’

  • Current Road Project Updates July 22 2022

    Share Current Road Project Updates July 22 2022 on Facebook Share Current Road Project Updates July 22 2022 on Twitter Share Current Road Project Updates July 22 2022 on Linkedin Email Current Road Project Updates July 22 2022 link

    Fernside Bridge

    The side-track is still on schedule to be open to traffic by 29th July, pending weather. Additional pipes for higher creek flows have been installed as an added precaution.

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 25th – 29th July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation. (Updated and postponed due to illness in the specialist contracting team)

    Koonorigan Road

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Regional Roads - Damaged Sealed Roads

    Approval has been received for the proposed scope of work to heavy patch six sections of Nimbin Road. Heavy patching consists of cutting off high shoulders, box out soft spots, overlay gravel where required, stabilise (nominal 1.5% slag/lime), compact, trim and seal. The procurement of a specialist stabilising subcontractor is underway. Scope has also been approved for Blue Knob Road, Dunoon Road, Kyogle Road and Wyrallah Road (excluding the Wyrallah Village). Wyrallah Village will be the subject to a reconstruction as it is not suitable for heavy patching.

    Precinct 1 - Damaged Sealed Roads

    Heavy patching has been approved for Graham Road, Gundurimba Road, River Bank Road, Rous Road, Skyline Road and Tuckurimba Road.

    Wyrallah Road Landslips

    Geotechnical drilling will take place under traffic control lane closures at 257 Wyrallah Road and 896 Wyrallah Road at the end of July.

    Johnston Road (Clunes)

    Geotechnical works will take place on the week of the 1st of August. This road, currently accessible to locals, will be fully closed during the works.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week (subject to weather)

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is still underway.

    Mountain Top Road

    Geotechnical drilling is still underway.

  • Current Road Project Updates July 14 2022

    Share Current Road Project Updates July 14 2022 on Facebook Share Current Road Project Updates July 14 2022 on Twitter Share Current Road Project Updates July 14 2022 on Linkedin Email Current Road Project Updates July 14 2022 link

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 18th – 22nd July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation.

    Koonorigan Road

    Investigations are underway to make a safe passage over the slip, while design is undertaken for a permanent solution. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Woodlawn Road

    Opened up to one lane. Geotechnical investigations are scheduled for the end of July.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is underway.

    Mountain Top Road

    Geotechnical drilling is underway.

    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Current Road Project Updates - June 21 2022

    Share Current Road Project Updates - June 21 2022 on Facebook Share Current Road Project Updates - June 21 2022 on Twitter Share Current Road Project Updates - June 21 2022 on Linkedin Email Current Road Project Updates - June 21 2022 link

    Wallace Road - Geotechnical drilling will be continuing this week, to remedy the landslip 1.3km from Tuntable Creek Road.

    Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.

    Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin north of Rose Road.

    Keerrong Road - The bridge piling has been completed. Bridge construction works are now underway.

    Repentance Creek Road - No further road closures are planned. The road is currently a gravel surface, while asphalt contractor scheduled works are confirmed. Speed has been reduced to 60KM due to loose gravel. Please drive with care.

    Dunoon Road – The road is open, with caution to traffic. Pavement has been placed, with the final stages being the seal to go ahead this week.

    Duncan Road - Funding has been approved to heavy patch stabilise damaged sections, and work has begun.

    The Channon Road- Geotechnical investigations are now complete. Reconstruction will be dependent on design of proposed embankment.

    The Channon Road (Robertson Bridge)- Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.

    Pinchin Road (embankment failure)- Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.

    Works planned for Ross Road (culvert has been cleared) and Black Road (washed out causeway) have now been completed.

  • Repentance Creek Road Closure

    Share Repentance Creek Road Closure on Facebook Share Repentance Creek Road Closure on Twitter Share Repentance Creek Road Closure on Linkedin Email Repentance Creek Road Closure link

    Lismore City Council is continuing works to repair roads following significant flood and consequent landslide damage. Urgent work is required to reconstruct an embankment and replace a pipe on Repentance Creek Road at Turkey Creek adjacent 171 Repentance Creek Road. Unfortunately, due to safety for road users, the road must be fully closed during a portion of the works period.

    What do the works involve?

    • Remove old damaged concrete pipe and replace with larger capacity pipes and headwalls.
    • Reconstruct embankment with rock fill
    • Construct drainage chute to discharge water away from embankment

    When will the works start?

    • 25/05/2022 – Stop/Go traffic control between 6:30am – 6:00pm Monday to Sunday
    • 30/05/2022 – Expect full 24-hour road closure until 13/06/2022 (please monitor electronic signage onsite, and Community Updates tab below for most up to date information)
    • 13/06/2022 – Stop/Go traffic control between 6:30am – 6:00pm Monday to Sunday
    • All closures will allow for pedestrian access through the work site

    These works may be subject to delays due to weather events. If there is a requirement to change these hours, updates will be listed below in 'Community Updates'.

    What are the traffic adjustments?

    A detour will be available through Federal for motorists to remain on the sealed road network. A VMS board will be stationed at the junction of Eureka Road and Repentance Creek Road, and at Dunoon Road to notify road users of the detour. Information will be listed on northernrivers.myroadinfo.com.

    Please allow additional travel time.

    Where can I find more information?

    Community updates and Q&A are listed in the below article.

    https://yoursay.lismore.nsw.gov.au/repentance-creek-road-closure

  • Dunoon Road Closure - Emergency Works

    Share Dunoon Road Closure - Emergency Works on Facebook Share Dunoon Road Closure - Emergency Works on Twitter Share Dunoon Road Closure - Emergency Works on Linkedin Email Dunoon Road Closure - Emergency Works link

    ***Updates for this project, plus Q+A are posted on the main article HERE

    Due to significant flood damage, Lismore City Council will close both sides of Dunoon Road between Dorroughby Road and Repentance Creek Road starting on Monday, 4 April, 2022.

    The road is expected to be closed in a phased approach to accommodate the Easter long weekend where it will open up again with traffic lights for both directions. After Easter from Tuesday, 19 April the section of Dunoon Road will close again until 26 April, 2022.

    What do the works involve?

    • Excavation of existing road surface down to access base of embankment.
    • Reconstruct embankment using rock and select fill.
    • Reconstruct pavement and seal.
    • Damage to the sealed pavement on the approaches will be repaired also.

    When will the works start and what are the hours of work?

    Works will start in the week commencing 4 April 2022. We expect the project will take about 6 weeks to complete, subject to weather conditions.

    Work hours:

    • 4th to 14th April, 2022 24-hour closure (working hours 6:30am to 6:00 pm Monday to Saturday)
    • 15th to 25th April, 2022 Single Lane track open under automated traffic lights
    • 26th April to 22nd May, 2022 24-hour closure (working hours 6:30am to 6:00 pm Monday to Saturday)
    • No work Sundays or public holidays.

    If there is a requirement to change these hours, you will be notified.

    What are the traffic adjustments?

    During the road closure period, traffic will be detoured via Repentance Creek Road (turns into Rosebank Road) and Dorroughby Road.

    Electronic billboards will be displaying alerts for detours. Further details will be available on MyRoadInfo website.

    What do I need to do?

    Please obey the temporary traffic conditions in place and allow additional time for travel.

    We apologise in advance for disruptions you may experience whilst we complete these works. We would appreciate your cooperation with all temporary traffic control and workplace protection measures onsite to help keep everyone safe.

    Who should I contact for further information?

    If you have any questions or concerns, please post in the Q&A on the main article HERE. Our team will provide updates to share with the community.