Current Road Project Updates - June 21 2022
Wallace Road - Geotechnical drilling will be continuing this week, to remedy the landslip 1.3km from Tuntable Creek Road.
Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.
Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin north of Rose Road.
Keerrong Road - The bridge piling has been completed. Bridge construction works are now underway.
Repentance Creek Road - No further road closures are planned. The road is currently a gravel surface, while asphalt contractor scheduled works are confirmed. Speed has been reduced to 60KM due to loose gravel. Please drive with care.
Dunoon Road – The road is open, with caution to traffic. Pavement has been placed, with the final stages being the seal to go ahead this week.
Duncan Road - Funding has been approved to heavy patch stabilise damaged sections, and work has begun.
The Channon Road- Geotechnical investigations are now complete. Reconstruction will be dependent on design of proposed embankment.
The Channon Road (Robertson Bridge)- Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.
Pinchin Road (embankment failure)- Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.
Works planned for Ross Road (culvert has been cleared) and Black Road (washed out causeway) have now been completed.