  • Flood Restoration - Roads & Bridges Update (Mar 2024)

    Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Mar 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS
    Black Road
    Temporary repair works were completed on Black Road to restore access to properties for residents. This involved importing some additional rock, stabilising the current structure with no fines concrete, and adding some additional surface material to ensure the crossing remains trafficable while the design for a new structure is under way.


    Dorroughby Road
    The Dorroughby Road landslip restoration project is now completed with motorists excitingly driving the stretch over road in mid-March. The works involved stabilising the landslip embankment, installing drainage, and constructing a new road pavement. We would like to thank the community for their patience during the construction and the positive feedback we have received from road users who are enjoying this new section of the road.

    Industry Drive
    During March work crews constructed a gabion wall to improve drainage prevent future erosion on Industry Drive. The works were completed under the watchful eye of nearby preschool children, who demonstrated great anticipation at the fence each day as they watched eagerly what the machinery would do next. A highlight for our crews as they witnessed the children’s smiling faces observing the works. Thank you to the local community for your support during these works.

    Johnston Road
    Works are now complete on a storm water outlet on Johnston Road. These works included reinstating the rock erosion protection and the concrete around the top of the precast headwall.

    Road Maintenance Works - Gwynne Road, Stony Chute Road & Tuntable Falls Road
    A busy month for our maintenance crews with staff inspecting and providing maintenance on many roads throughout the region. After listening to community concerns Gwynne Road, Stony Chute Road and Tuntable Falls Road were added as priority maintenance works. To improve road conditions, crews provided pothole repairs on Stony Chute Road and Tuntable Falls Road along with light grading and filling potholes for the sealed section of Gwynne Road.


    CURRENT WORKS
    Crofton Road
    Road pavement restoration works have commenced on Crofton Road for the locations identified below. The works will occur for approximately two to three months, subject to weather conditions. The road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.


    Newton Drive
    Works have commenced on several minor upslope landslips and a single pipe culvert. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.

    Nimbin Road
    Works are progressing on Nimbin Road at the site near Shipway Road. During the past month, on the southbound lane, work crews have removed the asphalt and base material along with reshaping and installing drainage. The road pavement was also constructed, compacted, and rolled along the full width of the road. Following this, the steel barriers on top of the retaining wall were installed, allowing the traffic to shift back to the northbound lane. Next month, works are scheduled to construction drainage along the retaining wall and complete placement of the road base layers along the full width of the road. This will be followed by sealing and asphalting along the full width of the road, installing guardrails and construction of the gabion basket wall extension ready for the anticipated opening on the road in May.


    Milgate Road
    Works have commenced on Milgate Road involving road surface and drainage repairs.


    Rogerson Road
    The team are continuing to implement the appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We will provide further update when available. Thank you to the community for your patience and understanding.

    Rosebank Road
    Landslip restorations are underway at Rosebank Road. The works involve reinstating the property access track and restoring the batter and table drain along the road edge.


    Terania Creek – Bridge Updates
    The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.

    Tuntable Creek Road
    During March, maintenance works were completed on Tuntable Creek Road from Young Road heading back down the hill approximately 500m. These works involved reshaping of table drains, slashing and minor landslip remediation.


    Upper Tuntable Falls Road
    Works are underway on two landslip sites on Upper Tuntable Falls Road located near the Tuntable Falls Primary School. During the past month, a site office was established and works commenced to reinstate the existing open drains. Temporary ramps were also constructed to allow trucks entry to the slip area. The works are expected to take 6-8 weeks weather permitting.


    Zouch Road
    Priority works have commenced for Zouch Road. This will involve with a light grade and repairs to the road surface.


    FUTURE WORKS
    Gwynne Road
    Gwynne Road is currently out to design; the design will take approximately one month. After this, the project will go to tender with work will be starting on the road in approximately 8 weeks.

    Magellan Street
    New guardrails will be installed on Magellan Street in the location identified on the map below during April. The road will remain open with works completed under single lane traffic control to have minimal impact on road users.

  • Flood Restoration - Roads & Bridges Update (Sept 2023)

    Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Sept 2023) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Bungabbee Road

    Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Dudgeon Road Bridge

    Works were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.


    Major Flood Recovery Works Map

    Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.


    CURRENT WORKS

    Nimbin Road

    Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.


    Keerrong Road

    Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.


    Geotechnical Investigations

    The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.

    Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.

    Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.


    Cawongla Road

    Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.

  • Geotechnical Investigations & Survey (Aug 2023)

    Share Geotechnical Investigations & Survey (Aug 2023) on Facebook Share Geotechnical Investigations & Survey (Aug 2023) on Twitter Share Geotechnical Investigations & Survey (Aug 2023) on Linkedin Email Geotechnical Investigations & Survey (Aug 2023) link

    Interim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.


    Commencing - 4th of September
    Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.


    Commencing - 18th of September

    Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.


    Commencing - 16th of October

    Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road


    There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’

  • Current Road Project Updates 25 August 2022

    Share Current Road Project Updates 25 August 2022 on Facebook Share Current Road Project Updates 25 August 2022 on Twitter Share Current Road Project Updates 25 August 2022 on Linkedin Email Current Road Project Updates 25 August 2022 link

    There are a number of road projects currently being completed. The below are updates for some of the projects which are progressing this week.

    If the road or project of interest isn't included below, please click the road name to the right (for desktop) of this page, or by scrolling to the bottom of the page (for mobile) for updates.

    Additionally, please utilise the Q+A function of this page to request specific updates.


    Black Road - Design is underway for a replacement structure. A temporary crossing is in place.

    Caniaba Road - Drainage works complete, shoulder widening works including a rock foundation is ongoing.

    Cowlong Road - Works are progressing near Lavis Road. Construction works planned for completion late September.

    Cawongla Road - Community consultation is underway in preparation for the road closure to replace four damaged culverts.

    Gravel Roads Program - Flood repair works are progressing. Approximately 60% of the LGA has now been complete with four road grading crews working full time on these works. Grading of gravel roads in Precinct 11 (including The Channon and surrounds) is due to commence in September. Please take care around the mobile plant. View the Precinct map and completion dates HERE

    Gungas Road - Pavement works well underway. Works expected to be complete by October.

    Hensen Bridge - Concrete abutments have been poured. Concrete bridge beams to be placed September in preparation of the deck pour.

    Johnston Road, Clunes - Geotechnical investigations finalised this week, with instruments installed to monitor the slip. Road reopened Monday 29th August under stop go traffic control until investigation works are complete.

    Keerrong Bridge - Concrete bridge complete including bridge approaches. Bridge will be opened under traffic control early September.

    Keerrong Road - Repairs to a 1.8km section on Keerrong Road is progressing well which will be complete by early September.

    Oakey Creek Road - Community consultation is underway in preparation for geotechnical investigations to determine the scope of work required for landslip remediation.

    Pinchin Road - Pavement stabilisation repair on several sections of Pinchin Road will commence August 29th. Single lane traffic control in place for the duration of works (5 weeks, weather permitting). Works on Keerrong Road will be postponed from September 1st, to allow additional traffic flow while Pinchin Road works are completed.

    Sexton Bridge, Gundurimba Road – Piling works commenced with abutment works planned for the next 3 weeks.

    Terania Creek Road - Segments have been identified to be included in the Flood Recovery Heavy Patching Program, which will provide improvements to the structural integrity of the road and driving conditions for road users. Geotechnical monitoring of the slip site is underway, as is procurement of specialist contractors and designers. Once works are complete at the slip, bridge approaches will be repaired and the road graded.

    Town Road - Bridge structure has been procured and works are expected to commence in late 2022.

    Tuntable Creek Road - Drilling has been undertaken on the slips, with geotechnical instrumentation installed to monitor movement to best inform the required structural design. Unfortunately, there is a shortage of suitably qualified geotechnical engineers at present. Council has started the procurement process to engage a designer and contractor to undertake restoration works. Additionally, funding has been received to undertake pavement repairs on damaged sealed-sections of Tuntable Creek Road, which is scheduled for October.

     Keerrong Road - repairs to a 1.8km sectionKeerrong Road - repairs to a 1.8km section

    Sexton Bridge piling works commenced

    Cowlong Road, near Lavis Road


  • Black Road reopen

    Share Black Road reopen on Facebook Share Black Road reopen on Twitter Share Black Road reopen on Linkedin Email Black Road reopen link
    supporting image

    Black Road is a short gravel road off Terania Creek, north of The Channon. The original creek crossing of Terania Creek consists of four concrete pipes and a concrete causeway. During the February 28th flooding event, the causeway was swept away in the torrential flow.

    Funding has been approved by TfNSW and Resilience NSW for engineering and survey works to be undertaken to design a new crossing to current standards. The temporary crossing currently in place is constructed of nylon rock bags with infill rock and gravel running surface. The temporary crossing will be maintained for the next 12 months until the permanent structure is complete.

    The residents have shown extraordinary resilience and fortitude during this time and their patience is appreciated.


    For more information on this project, and other road projects in The Channon and surrounding areas, please visit: https://yoursay.lismore.nsw.gov.au/road-restoration-works-the-channon

    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Current Road Project Updates - June 21 2022

    Share Current Road Project Updates - June 21 2022 on Facebook Share Current Road Project Updates - June 21 2022 on Twitter Share Current Road Project Updates - June 21 2022 on Linkedin Email Current Road Project Updates - June 21 2022 link

    Wallace Road - Geotechnical drilling will be continuing this week, to remedy the landslip 1.3km from Tuntable Creek Road.

    Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.

    Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin north of Rose Road.

    Keerrong Road - The bridge piling has been completed. Bridge construction works are now underway.

    Repentance Creek Road - No further road closures are planned. The road is currently a gravel surface, while asphalt contractor scheduled works are confirmed. Speed has been reduced to 60KM due to loose gravel. Please drive with care.

    Dunoon Road – The road is open, with caution to traffic. Pavement has been placed, with the final stages being the seal to go ahead this week.

    Duncan Road - Funding has been approved to heavy patch stabilise damaged sections, and work has begun.

    The Channon Road- Geotechnical investigations are now complete. Reconstruction will be dependent on design of proposed embankment.

    The Channon Road (Robertson Bridge)- Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.

    Pinchin Road (embankment failure)- Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.

    Works planned for Ross Road (culvert has been cleared) and Black Road (washed out causeway) have now been completed.

  • Road Restoration Works - The Channon

    Share Road Restoration Works - The Channon on Facebook Share Road Restoration Works - The Channon on Twitter Share Road Restoration Works - The Channon on Linkedin Email Road Restoration Works - The Channon link

    ***Unfortunately due to ongoing wet weather, the below schedule is being pushed back. Please see Community Updates on the main article HERE for further details***

    Due to significant flood damage, Lismore City Council will be continuing works to repair roads. The following are proposed to take place throughout May and June 2022.

    Location

    Reason

    Traffic Plan

    Duration

    Dates

    Terania Creek Road

    Landslip north of Lawler Road

    Geotechnical investigations using drilling rig, to understand subsurface conditions.

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    5 days

    25th May to 30th May

    Wallace Road

    Landslip 1.3km from Tuntable Creek Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    3 days

    30th May to 3rd June

    Black Road

    Causeway washed out

    Core drilling rock to determine strength for future rock anchors

    Road currently closed.

    1 day

    Depending on productivity of the full road closures

    Terania Creek Road

    Landslip between Izzard and Town Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    3 days

    Depending on productivity of the full road closures

    The Channon Road

    Landslip behind guardrail

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    2 days

    Depending on productivity of the full road closures

    *All closures will allow for pedestrian access.