Share Completion of work delayed until February on Facebook
Share Completion of work delayed until February on Linkedin
Email Completion of work delayed until February link
Oakey
Creek Landslip Repairs – completion of work delayed
We are incredibly sorry to have to inform residents
that work on the Oakey Creek Road landslip will take another two to three weeks
to complete.
We had hoped to have the road open by mid-January and
apologise for this additional inconvenience after such a lengthy project. Contractors
have informed us that the recent rain, while very welcome indeed, has delayed
the final completion date.
Good stretches of dry weather are required to complete
the remaining works including finalisation of the road, bitumen sealing and guard rail
installation.
We now expect the road to be open by 21 February 2020
– but again, this is dependent on rain.
Our sincere and heartfelt apologies for this further
delay. We are very conscious that people are frustrated and just want the job
finished. Our contractors are working as fast as they can to complete the
project.
Mountain Top Road Culvert
Replacement – start of work delayed
Construction of a temporary side track around the Mountain
Top Road culvert was scheduled to commence in mid-January but this work has
been delayed.
We now expect the side track to be complete by the end
of March. Once it is in place, work on constructing a new bridge will commence.
We expect the new bridge to be open by June 2020.
Share Landslip repairs almost complete: 17 December on Facebook
Share Landslip repairs almost complete: 17 December on Linkedin
Email Landslip repairs almost complete: 17 December link
Works are now almost complete on the Oakey Creek Road landslip repairs. Final work on reconstructing the road will be completed by mid-January and the road will be reopened to traffic.
Share Update on roadworks: 26 November 2019 on Facebook
Share Update on roadworks: 26 November 2019 on Linkedin
Email Update on roadworks: 26 November 2019 link
Oakey Creek Landslip Repairs
Council has been notified by the contractors managing the Oakey Creek Road landslip repairs that the expected completion date for this project is now December 2019. We had planned to finish in January 2020 but contractors are working hard to complete the project sooner and be finished by Christmas.
This has been a very complex and lengthy project and we would like to sincerely thank residents for your patience while these repairs have taken place.
Mountain Top Road Culvert Replacement
Planning for the Mountain Top Road culvert replacement is now complete. We encountered some unexpected geotechnical issues, and decided to do more investigation work to reduce the possibility of the project encountering delays during construction.
Construction of a temporary side track around the culvert will commence in mid-January and this will provide ongoing access to motorists until a new bridge is constructed.
Once the side track is complete, construction of the new bridge will commence. It is expected to be complete by June 2020.
Share Further Update on Mountain Top Road - 27 August on Facebook
Share Further Update on Mountain Top Road - 27 August on Linkedin
Email Further Update on Mountain Top Road - 27 August link
For those of you that like a little more detail, the latest developments on the Mountain Top Road project are that geotechnical investigations have been done for the construction of the piling platform that is needed on site and also for the temporary traffic diversion track.
Designs have also been completed for the piling platform and the engineers are currently reviewing these designs.
So, overall things are progressing and it should not be too long before you see activity on site.
Share Mountain Top Road - Update - 27 August on Facebook
Share Mountain Top Road - Update - 27 August on Linkedin
Email Mountain Top Road - Update - 27 August link
We told you that works on Mountain Top Road culvert replacement would start in early August. Whilst you will not have seen activity on site yet, there is plenty going on in the background. Discussions are underway with piling contractors and geotechnical engineers to decide on the best approach to this complex project.
A more detailed update from our engineers will be posted before the end of this week. In the meantime, if you have specific questions or concerns you can ask your question via the "Q and A" section above or phone our Community Engagement Officer. Her contact details are on this project page under the 'Who's Listening' section.
Share Oakey Creek Road - Earthworks progressing on Facebook
Share Oakey Creek Road - Earthworks progressing on Linkedin
Email Oakey Creek Road - Earthworks progressing link
Trucks are currently hauling on Jiggi and Gwynne Rd so please be careful! These trucks are bringing in rock that will be placed and compacted as part of the ongoing earthworks. This is in preparation for up and coming piling works. A date for these piling works will be advised in the next update.
Share Members of Community Ignoring Signage and driving through Oakey Creek Work Site on Facebook
Share Members of Community Ignoring Signage and driving through Oakey Creek Work Site on Linkedin
Email Members of Community Ignoring Signage and driving through Oakey Creek Work Site link
In the last few days, a person on a motor bike and someone driving a car have ignored the signage on Oakey Creek Road and driven onto the work site, whilst contractors were operating heavy machinery.
We are concerned to ensure that all residents stay safe while we complete the essential work on Oakey Creek landslip.
People ignoring signage and driving onto the site could also cause considerable delay to the project.