Flood Restoration - Roads & Bridges Update (Jan 2023)
ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
COMPLETED WORKS
Cawongla Road
Excitingly, the Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. We would like to thank all the residents of Larnook and the surrounding region for their patience and cooperation during these repairs. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods. Further details can be found on the latest Cawongla Road update on the following link:
Sheehan Road
Works have been completed on Sheehan Road to address issues caused from the February and March 2022 floods. This has involved overlay and drainage works to repair flood damages.
Mountain Top Road, Standing Street, Nimbin Street & Wallace Road
Overlay works have been completed on Mountain Top Road, Standing Street, Nimbin Street and Wallace Road, to address issues caused from the February and March 2022 floods.
Blue Knob Road
Works are completed for Blue Knob Road, these included removing and replacing the existing material from the road surface, along with grading and rolling the road with a temporary seal over the new surface. A planned return to complete permanent works will be scheduled during 2023.
Tuntable Creek Road
The works crew remobilised to the site at the beginning of January, this stage of construction consists of excavating into the slope above the road and installing 49 soil nails and 100m2 shotcrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control and opening one lane. The works are expected to be complete in February with additional updates to be provided as the works commence on the upper slope. For further details please visit the Tuntable Creek Road update link below:
Wyrallah Road
Pavement rehabilitation works are commencing shortly to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:
Swan Bay Road
Overlay and drainage works are currently underway to repair damages from the October flood event for Swan Bay Road.
Crofton Road & Rock Valley/Cawongla Road
Drainage works are continuing for Crofton Road and Rock Valley/Cawongla Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.
Munro Wharf Road
Overlay and drainage works to repair damages from the October flood event will commence shortly for Munro Wharf Road.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends