Category Wyrallah Road   Show all

  • Flood Restoration - Roads & Bridges Update (May 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.


    COMPLETED WORKS

    Wallace Road

    Council recently completed temporary pavement patching works around the slip area on Wallace Road to improve road surface conditions. The works are a temporary measure, until permanent pavement rehabilitation works are scheduled.


    Mackie Road

    Following the AGRN943 2020 natural disaster the Mackie Road causeway at Johnston Creek suffered extensive damage. Funding was awarded to replace the damaged structure with a bridge to reduce impediments to fish passage. The Mackie Road culvert to bridge replacement at Johnston Creek works are now completed with the road opening at the end of May 2023. Work at site began in March and during May the bridge concrete pours, guardrail installation and bridge approaches were completed, with the final stage of works involving bitumen sealing and batter protection. Council would like to thank residents and road users for their patience during the road closure.


    CURRENT WORKS

    Tuntable Creek Road

    Recently, council staff were forced to close Tuntable Creek Road for two days due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes. As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence. In the event of rainfall exceeding our trigger level or other significant changes, the temporary track will be closed again at short notice. Please contact floodrecoveryroadsbridges@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.


    Nimbin Road

    Council commenced roadworks on two landslip sites on Nimbin Road during May. The first major construction works involve tree felling for both sites, with site one having larger trees which will land on the road. The works are expected to occur over 9 months from mid-May 2023 subject to weather, contractor, and material availability. This will involve piling and retaining wall construction works to allow repair of the landslips, reconstruction of pavement, reinstatement of road and guardrail barriers along with installing signs, guideposts, and line marking. Traffic control lights remain in place and existing single lane traffic control will remain in place during the works period. Road users are advised to follow VMS boards and signage, with delays expected as these works commence.


    Town Road

    Funding was awarded by the NSW Government through its Fixing Country Bridges program to replace the damaged structure at Town Road, Terania Creek with a new steel superstructure bridge. The innovative steel structure has been constructed in France and will be launched into place in one piece. Unique for the area, this type of structure will be the first in the region. Works have recommenced at the site in April 2023, where a temporary track has now been constructed in preparation for bridges piling. A planned completion date is scheduled for September 2023, subject to weather, contractor, and material availability.


    Wyrallah Road & Wyrallah Ferry Road

    During May, the rock bridging layer and subbase layer were completed for Wyrallah Ferry Road intersection, with works starting at the end of May on drainage. Pipes were also laid through the park at Wyrallah Ferry Road Intersection. During June, all drainage works are scheduled to be completed followed by site clean-up and project completion.


    Cawongla Road

    Drainage works on Cawongla Road are continuing with two new sections recently completed. It is anticipated work crews will reach the halfway mark next week. Council would like thank residents for their positive feedback and continued patience as the works progress.


    FUTURE WORKS

    Branch Creek Crossing, Terania Creek Road

    Following the 2022 natural disaster Terania Creek Road suffered extensive damage. Due to the nature and high number of damages incurred, works are being finalised on how best to provide timely improvements for the community and road users. The current structure at Branch Creek Crossing has received funding from disaster recovery funding arrangement (DRFA) for replacement of the flood damaged asset. An alternative structure is necessary to increase resilience of the network. Works will include replacing the current box culvert structure with a 16m bridge and extending erosion protection to the edge of the road. Additional works required and subsequent funding for other damages on Terania Creek Road are being assessed. Survey and design work is commencing in June 2023.



  • Flood Restoration - Roads & Bridges Update (Mar 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please email floodrestoration@lismore.nsw.gov.au with subject ‘Add Road Name - Notification list’ to register your contact details to receive updates.


    COMPLETED WORKS

    Tuntable Falls Road
    Temporary sealed patching works were recently completed for Tuntable Falls Road. These works involved placing overlay, stabilise, trim and sealing the road surface height to repair damages from the 2022 flooding event.


    Tuntable Creek Road
    After establishing a baseline for the monitoring process and developing a management plan, the temporary track opened on Tuesday, the 14th of March. Due to the volatile nature of the landslip and risks of further damages occurring a detailed risk assessment was undertaken to control access until a permanent solution is implemented. The risk assessment requires weekly visual monitoring, survey monitoring of fixed control points and monthly inspections by a geotechnical engineer. Restrictions will be placed on the temporary access road during large rain events to mitigate risks to public. Should the road be closed due to adverse weather, VMS boards placed at The Channon and Nimbin will identify the road closure. Facebook updates will also communicate the closure to the wider community. Please report hazards or changes to Lismore City Council using reference LCC92.


    CURRENT WORKS

    Mackie Road

    The Mackie Road culvert to bridge replacement at Johnston Creek, works are currently underway after starting on Monday the 13th of March. The project works will operate for approximately three months with a planned completion in late June 2023, subject to fine weather. Due to the nature of the works a full 24-hour hard road closure is required during the March – June 2023 works period around the site location. For further details and to view a map of the works, please visit the Mackie Road bridge update link below:
    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/mackie-road-bridge-feb-2023


    Crofton Road
    All drainage and pipe work is scheduled to be completed by Thursday the 6th of April. These works include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.


    Wyrallah Road
    Pavement rehabilitation works started at the end of January to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. The site closed on the 24th of March, with recommencement expected mid-April to allow for required drainage re-design and survey prior to finalising the section and switching traffic and commencing the Northbound Lane. For further details please visit the Wyrallah Road update link below:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/wyrallah-road-jan-2023


    Quilty Road
    The remaining drainage works are scheduled to commence after Easter for Quilty Road.


    FUTURE WORKS

    Town Road
    Funding through the Fixing Country Bridges program has been awarded to replace the damaged structure with a new bridge on Town Road. The bridge superstructure is currently being constructed in France with an innovative steel beam that will be launched into place in one piece. A unique type of structure, this bridge will be the first in the region. A general plan of the works is provided below. The Town Road bridge superstructure will be delivered at the end of May 2023. Civil works are scheduled to begin in April 2023 with a planned completion in late July 2023, subject to fine weather. Further updates will be provided towards the end of March 2023.

  • Flood Restoration - Roads & Bridges Update (Feb 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please email floodrestoration@lismore.nsw.gov.au with subject ‘Add Road Name - Notification list’ to register your contact details to receive updates.


    COMPLETED WORKS

    Tuntable Creek Road

    Tuntable Creek Road experienced significant damage during the February 2022 natural disaster with 11 notable landslips recorded and a major landslip closing the road north of intersection with Rose Road. A temporary solution was designed to open the road and establish connectivity between Nimbin and The Channon while the permanent solution is designed. The temporary construction consists of stabilising the embankment below the road and excavating into the slope above the road to make a single trafficable lane. The stabilisation will use up to 160 8m long soil nails and over 400m2 of sprayed concrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control. The works are expected to be complete in March with the road opened to local access only and restricted during weather events. For further details please visit the Tuntable Creek Road update:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/tuntable-creek-road-jan-2023


    Cawongla Road

    The Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods.


    Gwynne Road

    Temporary repair of damaged pavement was recently completed for Gwynne Road. During these works, the crews also performed scour repair and mulching vegetation along with cleaning drains and pipes to improve the roads condition.


    Unsealed Roads

    Overlay works to repair damages from the October flood event were recently completed for Lagoon Grass Road, Howards Grass Road, Cusack Road, Booerie Creek Road, Hewitt Road, Swan Bay Road, and Sheehan Road.


    Johnston Road

    Temporary patching works across slip single lane were recently completed for Johnston Road.


    CURRENT WORKS

    Crofton Road & Rock Valley Road
    Drainage works are continuing for Crofton Road and Rock Valley Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.


    Wyrallah Road

    Pavement rehabilitation works started at the end of January to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/wyrallah-road-jan-2023


    FUTURE WORKS

    Town Road

    Funding through the Fixing Country Bridges program has been awarded to replace the damaged structure with a new bridge. The bridge superstructure is currently being constructed in France with an innovative steel beam that will be launched into place in one piece. A unique type of structure, this bridge will be the first in the region. A general plan of the works is provided below. The Town Road bridge superstructure will be delivered at the end of May 2023. Civil works are scheduled to begin in April 2023 with a planned completion in late July 2023, subject to fine weather. Further updates will be provided towards the end of March 2023.


    Mackie Road

    Following the 2020 natural disaster the Mackie Road causeway at Johnston Creek suffered extensive damage. Funding has been awarded to replace the damaged structure with a bridge to reduce impediments to fish passage. The Mackie Road culvert to bridge replacement at Johnston Creek, works will begin on the 13th of March for approximately three months with a planned completion in late June 2023, subject to fine weather. Due to the nature of the works a full 24-hour hard road closure is required during the March – June 2023 works period around the location detailed on the map below. For further details please visit the Mackie Road bridge update link below:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/mackie-road-bridge-feb-2023

  • Flood Restoration - Roads & Bridges Update (Jan 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au


    COMPLETED WORKS

    Cawongla Road

    Excitingly, the Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. We would like to thank all the residents of Larnook and the surrounding region for their patience and cooperation during these repairs. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods. Further details can be found on the latest Cawongla Road update on the following link:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/cawongla-road-jan-2022


    Sheehan Road

    Works have been completed on Sheehan Road to address issues caused from the February and March 2022 floods. This has involved overlay and drainage works to repair flood damages.


    Mountain Top Road, Standing Street, Nimbin Street & Wallace Road

    Overlay works have been completed on Mountain Top Road, Standing Street, Nimbin Street and Wallace Road, to address issues caused from the February and March 2022 floods.


    Blue Knob Road

    Works are completed for Blue Knob Road, these included removing and replacing the existing material from the road surface, along with grading and rolling the road with a temporary seal over the new surface. A planned return to complete permanent works will be scheduled during 2023.


    CURRENT WORKS

    Tuntable Creek Road

    The works crew remobilised to the site at the beginning of January, this stage of construction consists of excavating into the slope above the road and installing 49 soil nails and 100m2 shotcrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control and opening one lane. The works are expected to be complete in February with additional updates to be provided as the works commence on the upper slope. For further details please visit the Tuntable Creek Road update link below:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/tuntable-creek-road-jan-2023


    Wyrallah Road

    Pavement rehabilitation works are commencing shortly to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/wyrallah-road-jan-2023


    Swan Bay Road

    Overlay and drainage works are currently underway to repair damages from the October flood event for Swan Bay Road.


    Crofton Road & Rock Valley/Cawongla Road
    Drainage works are continuing for Crofton Road and Rock Valley/Cawongla Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.


    FUTURE WORKS

    Munro Wharf Road

    Overlay and drainage works to repair damages from the October flood event will commence shortly for Munro Wharf Road.

  • Wyrallah Road - Pavement Works (Jan 2023)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Following the 2022 natural disaster, Wyrallah Road suffered extensive damage. Works will begin from the end of January for pavement rehabilitation, please refer to the map provided for an overview of the location.


    All works will be completed under single lane traffic control, this will be implemented from January 30th 2023 for 4 months with a planned completion in late May 2023, subject to fine weather, between the hours of 7am and 5pm. This planned single lane road closure will allow Council to preform reconstruction work on Wyrallah Road preforming numerus tasks mentioned within this letter throughout the 500m stretch of the road.


    Funding has been secured through Transport for NSW. This funding is allocated to repair damage sustained during the February 2022 natural disaster only. Additional works required and subsequent funding for Wyrallah Road are being reviewed.


    We apologise in advance for access disruptions you may experience during these construction activities, and we thank you in anticipation of your cooperation and patience during these essential works.

    Map outlining approximate location of the Wyrallah Road single lane closure

    What are the works?


    The works will reconstruct and rehabilitate approximately 500m of Wyrallah Road. These works include removing approximately 400mm of shoulder material and replacing this section with roadbase through the first 100m of the project from Lismore. Then, approximately 100mm of the existing surface will be overlaid and stabilised. Throughout the remaining 250m length of the road, crews will remove unsuitable material to an approximate depth of 600mm below existing heights and replace it with 500mm of rock, and 350mm of roadbase. This will result in an increased road height of approximately 250mm from the existing height to the finish surface height. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed.


    When are the works taking place?

    Works are scheduled to start from January 30th and are expected to take about four months to complete, subject to fine weather conditions. Daily work hours will mostly be between 7am and 5pm weekdays, although there may be some weekend work.


    What will be the traffic controls/detours?

    Due to the intensive nature of roadworks and associated traffic controls, there will unfortunately be some traffic disruptions. These traffic controls will include single land road closure. This will ensure the roadworks are completed in a timely manner, with safety as a predominant factor, by eliminating traffic through a single lane of this road throughout the construction footprint. Throughout the construction period there may be periods where 24/7 portable traffic lights will be needed to keep a travel lane closed overnight.

    Local access to residences will be maintained by actively managing residents’ needs within the construction footprint to allow access to homes, however, please be aware of delays. Electronic billboard signage will notify motorists of detours via Lismore and Tregeagle Road. Updates will also be available via Live Traffic NSW and Your Say (page details below). Road users are advised to seek alternate routes, as single lane closures are likely to cause heavy traffic delays.

    Please commute through the job sites at low speed, obey traffic control instructions and drive carefully.


    Further Information

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Wyrallah Road – Pavement Works.’

  • Wyrallah Road - Landslip, Bridge Repairs and Pavement Rehabilitation

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Following the February and March 2022 natural disaster, Wyrallah Road suffered extensive damage. Funding has now been secured to complete restoration works.

    The works will include repairs to the bridge approach and guardrail on the western abutment of Wyrallah Ferry Road Bridge, and pavement rehabilitation from Bridge Street south on Wyrallah Road. Please see map of proposed work sites below.

    All works will be completed under single lane traffic control. Properties within this area are accessible, however please be aware of delays. Electronic billboard signage will notify motorists of detours via Lismore and Tregeagle Road. Updates will also be available via Live Traffic NSW and Your Say (page details below). Road users are advised to seek alternate routes, as single lane closures are likely to cause heavy traffic delays.

    Council wishes to advise that we will be using an area within the road reserve, at the intersection of Coraki Road and Wyrallah Ferry Road for the storage of gravel for these and other works.

    Additional segments of Wyrallah Road have also been identified for heavy patching works to repair flood damage to road surface. Scheduling of these works will be advised at a later date.

    The geotechnical investigations have taken place at the landslip north of Bridge Street. The proposed remediation works are complex, requiring specialist contractors and designers and unfortunately will not be completed concurrent with these works. This remediation will take place in 2023.

    Further information and updates will be posted on this page.

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Wyrallah Road Works’ in your correspondence.



  • WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    OUR WEEKLY POTHOLE REPAIR SCHEDULE


    It looks like it’s going to be another glorious week in paradise, with little to no rain predicted.
    What is not so glorious are the potholes in our roads.

    Our road crews are working their way through the list of roads that require temporary pothole repair, as we also continue with other road works to repair the significant damage caused by the February natural disaster.

    It is a massive job, and we thank you for your patience.


    This week our pothole repair team will focus on:
    Rock Valley Road
    Nimbin Road
    Dunoon Road
    Blue Knob Road
    Wyrallah Road
    Kyogle Street
  • Current Road Project Updates 5 August 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Gravel Roads (Flood Repair Works) – approximately 50% of LCC Gravel Roads have been repaired now since the Feb/March 2022 events.

    Caniaba Road – Drainage and shoulder widening works progressing well. Project is currently running to plan with minimal delays.

    Richmond Hill Road – the landslip has been repaired and pavement rehabilitation works are progressing.

    Nimbin Road near Goolmangar School – urgent maintenance works were carried out last week, the damaged sealed pavement was returned to gravel. This section of road will be overlaid with new gravel and stabilised this month

    Keerrong Road Bridge – the new concrete bridge is now complete and earthworks progressing on the approaches

    Henson Bridge – Piling is now complete, works progressing well on preparing the bridge abutments (form/reo/poor)

    Keerong Road – Landslip and drainage remediation works are commencing, leading to a road closure from August 10th - adjacent to 1265 Kerrong Road. Motorists are advised via roadside signage. Pavement strengthening works are also progressing on approximately a 1km section. Further pavement works are scheduled.

    Bruxner Highway at Northcott Road – pavement rehabilitation works are progressing which have included stabilisation of the existing material and overlay with new gravel.

    Gungas Road – shoulder widening and pavement works are progressing.

    Cowlong Road – pavement strengthening works are progressing south of McKenzie Road.

    Jiggi Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    Pinchin Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    One section of Jiggi Road, preconstruction on 04/08/22

    Wyrallah Road - Geotechnical drilling to determine scope of works.

    Drilling at Wyrallah Road 27/07/22

    Dunoon Road (near the Macadamia Factory) - Temporary patching on a section of road adjacent Macadamia factory on Dunoon Road. This section of road is due for full pavement reconstruction in October this year.

    a section of Dunoon Road before temporary patching 02/08/22

  • Current Road Project Updates July 22 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Fernside Bridge

    The side-track is still on schedule to be open to traffic by 29th July, pending weather. Additional pipes for higher creek flows have been installed as an added precaution.

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 25th – 29th July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation. (Updated and postponed due to illness in the specialist contracting team)

    Koonorigan Road

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Regional Roads - Damaged Sealed Roads

    Approval has been received for the proposed scope of work to heavy patch six sections of Nimbin Road. Heavy patching consists of cutting off high shoulders, box out soft spots, overlay gravel where required, stabilise (nominal 1.5% slag/lime), compact, trim and seal. The procurement of a specialist stabilising subcontractor is underway. Scope has also been approved for Blue Knob Road, Dunoon Road, Kyogle Road and Wyrallah Road (excluding the Wyrallah Village). Wyrallah Village will be the subject to a reconstruction as it is not suitable for heavy patching.

    Precinct 1 - Damaged Sealed Roads

    Heavy patching has been approved for Graham Road, Gundurimba Road, River Bank Road, Rous Road, Skyline Road and Tuckurimba Road.

    Wyrallah Road Landslips

    Geotechnical drilling will take place under traffic control lane closures at 257 Wyrallah Road and 896 Wyrallah Road at the end of July.

    Johnston Road (Clunes)

    Geotechnical works will take place on the week of the 1st of August. This road, currently accessible to locals, will be fully closed during the works.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week (subject to weather)

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is still underway.

    Mountain Top Road

    Geotechnical drilling is still underway.

  • Flood Recovery Heavy Patching Program

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Flood Recovery Heavy Patching Program –

    Restoration of road surface, possible change in road level.

    Segments of the following have been identified for heavy patching works to repair flood damage to road surface.

    Precinct 1

    Graham Road

    Gundarimba Road

    River Bank Road

    Rous Road

    Skyline Road

    Tregeagle Road

    Tuckurimba Road

    Tucki Road

    Wybelena Road

    Precinct 2

    Bagotville Road

    Broadwater Road

    Kilgin Road

    Mathieson Lane

    Precinct 3

    Tatham Road

    Precinct 4

    Nimoola Road

    Pelican Creek Road

    Precinct 6

    Back Creek Road

    Precinct 7

    Axford Road

    Martin Road

    McGuinness Road

    Rock Valley Road

    Precinct 8

    Boggumbil Road

    Davis Road

    Jacobson Road

    Jiggi Road

    Potessu Road

    Rosehill Road

    Precinct 9

    Anderson Road

    Basil Road

    Cecil Street

    Crofton Road

    Gungas Road

    Lillian Rock Road

    Moffitt Road

    Sibley Street

    Symonds Road

    Thorburn Street

    Precinct 10

    Booerie Creek Road

    Boyle Road

    Keerrong Road

    Precinct 11

    Koonorigan Road

    Pinchin Road

    Terania Creek Road

    The Channon Road

    Tuntable Creek Road

    Precinct 12

    Dorroughby Road

    Duncan Road

    James Street (Dunoon)

    Middleton Way

    Nightcap Range Road

    Rocky Creek Dam Road

    Precinct 13

    Corndale Road

    Hunters Hill Road

    Grace Road

    James Gibson Road

    Precinct 14

    Boatharbour Road

    Eltham Road

    Humpty Back Road

    Regional Roads

    Blue Knob Road

    Coraki Road

    Dunoon Road

    Nimbin Road

    Wyrallah Road

    Bridge Street (Wyrallah)

    Kyogle Road


    These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.


    Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.


    How will the works affect traffic?

    Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.


    What do the works involve?

    These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.


    The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.

    This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.


    All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.

    What happens now?

    If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:

    • Via the ‘Submissions’ tab of this article HERE.
    • Email to council@lismore.nsw.gov.au
    • Call to Council (02) 6625 0500
    • In writing to Lismore City Council, PO Box 23A, Lismore 2480