Category Cawongla Road Show all
-
Rock Valley / Cawongla Road - Technical Investigations (Aug 2024)
Share Rock Valley / Cawongla Road - Technical Investigations (Aug 2024) on Facebook Share Rock Valley / Cawongla Road - Technical Investigations (Aug 2024) on Twitter Share Rock Valley / Cawongla Road - Technical Investigations (Aug 2024) on Linkedin Email Rock Valley / Cawongla Road - Technical Investigations (Aug 2024) linkCouncil wishes to advise of continuing investigation works along Rock Valley Road and Cawongla Road. The works will occur for approximately three weeks, from 19 August to 6 September 2024, subject to weather conditions. The road will remain open with no impact to motorists or emergency services vehicles. We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Funding has now been secured for technical investigations scheduled along Rock Valley and Cawongla Roads identified on the below map. These examinations help inform the design for road restoration works required for these roads following the 2022 natural disaster. This information will inform the design for road pavement remediation and restoration works, due for delivery around mid-February 2025.
What to Expect?- Surveyors undertaking surveying activity in the area
- Mulching of grass verge.
- Potential drone activity in the area to assess local topography.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Rock Valley / Cawongla Road – August 2024 Update.’ -
Flood Restoration - Roads & Bridges Update (May 2024)
Share Flood Restoration - Roads & Bridges Update (May 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (May 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (May 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (May 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
Environmental Rescue at Rogerson Road
What happens when a handful of bats put a major flood restoration project on hold? When it came time to replace three large steel storm water drainage pipes with reinforced concrete pipes ones on Rogerson Road, McKees Hill, project coordinators discovered at least half a dozen micro bats had made a hole in one pipe, their home.Myotis Macropus: One of Australia’s most fascinating species because they’re the only bats in Australia to capture fish for food. They have large feet which they use to trawl for food near the water’s surface. Work crews had to play a waiting game until two juvenile bats were old enough to fly. But then the challenge was - how to catch the youngsters and offer them an alternative roosting venue. Eventually patience and thermal imaging cameras confirmed the two young bats took to the skies for the first time, just after sunset on 1st May.
That night the hole was sealed, and a timber bat box installed as an alternative roost. Four bats settled into their new home but the remaining two had to be caught and housed in the box. Once the culvert work is complete it’s hoped all the bats, and their box will be relocated into the new concrete pipes.
COMPLETED WORKS
Crofton Road
Road pavement restoration works on Crofton Road are on track to be completed by the end of May. Until then the road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.
Gungas Road
Works commenced at the end of April on Gungas Road to desilt the creek crossing at Black Sheep. This involved the removal of debris to allow the creek to flow across the full width and reduce the chance of overtopping the crossing in the future.
Nimbin Road
Wet weather continued to cause delays to the completion of works on Nimbin Road at the site near Shipway Road. By mid-May the road was open to two-way traffic with the final clean up completed by 24 May 2024. During the past month, works were completed for the construction drainage along the retaining wall and placement of road base layers along the full width of the road. The road has now been sealed with asphalt and guardrails installed.
Oakey Creek Road
In May, temporary works were completed at a landslip site along Oakey Creek Road that was identified as a safety hazard.
CURRENT WORKS
Multiple Road Works
The works involve grading over 120km on 53 unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events in December 2023 and April 2024. Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work. For further information visit https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/upcoming-works-grading-for-multiple-unsealed-gravel-roads
Blue Knob Road
Works began in late May to rectify the first of two landslip sites on Blue Knob Road. These works will occur for approximately 12 months which will include an additional two sites along Blue Knob Road. The road will remain open under stop go traffic control to have minimal impact on residents.
Eureka Road, Graham Road & Haywood Lane
Works have commenced to replace culverts with bridges and all side tracks are in place with existing culverts removed. Future piling work is scheduled to commence in mid-June.
Newton Drive
Works on several minor upslope landslips and a single pipe culvert were heavily impacted this month due to weather conditions. Crews are hoping for favourable weather in June to progress the pending works which will to be completed under traffic control and will have minimal impact on the residents in this area.
Rogerson Road
Through successful collaboration with environmental professionals the juvenile micro bats were temporary relocated during April. This will allow works to commence replacing the steel drainage pipes with cement ones. Thank you to the community for your understanding and patience while the works continue.
Stony Chute Road
Following the February 2022 natural disaster, Stony Chute Road suffered extensive damage. With funding secured restoration works are now underway. The works will continue for approximately three to four weeks from 15 May 2024, subject to weather conditions.
Terania Creek Road – Bridge Updates
Concrete approaches, scour protection, and guard rail installation are complete for Bridge 3. Final work is due to be complete late May. For Bridges 1 and 2 side track installation is nearing completion with work to recommence in June.
Upper Tuntable Falls Road
Landslip remediation works will be complete at the Upper Tuntable Falls slip site this week. Some minor grading and drainage works will continue into June on Upper Tuntable Falls Road, with completion expected mid June.
FUTURE WORKS
Gwynne Road
The design for 1.2 kilometres of new pavement is nearing completion and once finalised the work will be put out to tender with works predicted to begin in approximately 6 weeks. -
Flood Restoration - Roads & Bridges Update (April 2024)
Share Flood Restoration - Roads & Bridges Update (April 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (April 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (April 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (April 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
‘Thirst for Legacy’ – CMC Community Spirit in Nimbin
In a heart warming display of community spirit, the CMC team involved in the Nimbin Road project recently rallied together to support the Nimbin Bowling Club. Their initiative involved recycling cans and bottles collected from their work site, with the proceeds earmarked for a noble cause: funding the installation of a BBQ area at the club. CMC head office joined in on the idea, matching the money the team raised. The Nimbin Bowlo is a non-for-profit establishment, mostly managed by dedicated volunteers, so they were very appreciative of the kind gesture. Last month the dedicated team volunteered to lay down the concrete slab. Soon other organisations came to the party with Holcim Concrete Lismore providing a discount on the concrete to fit into the budget and Nimbin Hardware donating two sheets of mesh. Additionally, several locals donated their time along with the CMC staff to place and finish the slab. CMC donated labour and supervision, as you can see from the photos many locals also provided supervision of their own. This act of gratitude was CMC’s way of expressing appreciation to the local community for their unwavering support during the team’s time in our region. Their commitment to both the project and the community exemplifies the positive impact that collaborative efforts can have. LCC would like to thank the project team for their generosity and community-minded approach!
Black Road
The causeway has been resurfaced following recent deterioration by high water flows. The road is now repaired and new guideposts installed.
Coraki Road
Geotechnical works are completed on Coraki Road they will enable engineers to design and construct remediation works to deliver roads that are safer and more durable. The design phase is now in progress.
Guardrails Projects
The Flood Recovery Guardrail replacement multisite works are now complete. A recent project included the installation of guardrails at Kyogle Street and Oakey Creek Bridge. Thanks to all motorists for their patience during the works.
Road Maintenance Works - Gwynne Road, Stony Chute Road & Tuntable Falls Road
Maintenance crews were busy inspecting and providing maintenance on many roads throughout the region. To improve road conditions, crews continued to provide pothole repairs on Tuntable Falls Road and Stony Chute Road along with grading and pothole repairs on Gwynne and Yeager roads. Priority works have also commenced for Zouch Road involving a light grade and repairs to the road surface.
Rosebank Road
Landslip restorations are complete at Rosebank Road. The works involved reinstating the property access track and restoring the batter and table drain along the road edge.CURRENT WORKS
Crofton Road
Road pavement restoration works are well on the way on Crofton Road. The works will be ongoing for approximately two to three months, subject to weather conditions. The road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.Eureka Road, Graham Road & Haywood Lane
Works have commenced on the culvert to bridge structure replacement project at Haywood Lane. Construction has begun on installation of side tracks with piling to follow next month.
Gungas Road
Works commenced at the end of April on Gungas Road to desilt the creek crossing at Black Sheep. This will involve the removal of debris to allow for further rectification works.
Newton Drive
Works have commenced on several minor upslope landslips and a single pipe culvert. However, these works were heavily impacted this month due to weather conditions. During May, work crews are hoping for favourable weather to assist with making good progress at the sites. Works will continue to be completed under traffic control and will have minimal impact on the residents in this area.
Nimbin Road
Works are nearing completion on Nimbin Road at the site near Shipway Road. During the past month, works were completed for the construction drainage along the retaining wall and placement of road base layers along the full width of the road. The road has now been sealed with asphalt and guardrails installed. Remaining work includes line marking and the installation of guideposts. The road is due to be officially opened on 11 May.
Rogerson Road
Through successful collaboration with environmental professionals the juvenile micro bats were temporary relocated during April. Works were able to commence April 29, to start on the culvert replacement project. Thank you to the community for your understanding and patience while we relocated this projected species.
Terania Creek – Bridge Updates
Project is underway for bridge 1, 2 and 3. Bridge 3 has new concrete bridge approaches and scour protection completed with guardrail installation scheduled during early May. After this, installation of lateral restrains brackets will follow. Approximately 50% of bridge 2 and 1 have side track installations complete. These will continue during May, subject to weather conditions. Once completed, installation of concrete approaches and guard rail for bridges 2 and 1 will follow.
Upper Tuntable Falls Road
Works are underway on Landslip DM01184 near the Tuntable Falls Co-Op. However recent rain delayed the excavation process on site, weather permitting, the works are expected to take an extra three weeks. Once completed, works will commence on Landslip DM01183, located approximately 500m North of DM01184.FUTURE WORKS
Blue Knob Road
Works will commence in May on two landslip sites identified on the below map. These works will occur for approximately 12 months. The road will remain open under stop go traffic control to have minimal impact on residents.
Branch Creek Road
Works are progressing for the design phase of the Branch Creek culvert replacement project. IFC drawings have been issued with procurement of pre-cast components and piling underway. Construction is expected to commence in Sept.
Cawongla Road
Weather pending, pipe scour protection will be undertaken in May under single lane traffic control.
Milgate Road
During last month grading work was completed on Milgate Road. The design for the culvert is underway and a notice will be provided on these works in the next few months.
Oakey Creek Road
In May, works will commence for temporary landslip repair works identified on the below map for approximately two to four weeks. The road will remain open under stop go traffic control to have minimal impact on residents.
Patterson Road
Work is progressing for the design phase of the Paterson Road culvert replacement project with the RFQ issued for design of culvert replacement with a new bridge structure. -
Flood Restoration - Roads & Bridges Update (Nov 2023)
Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Nov 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Nov 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Cawongla Road
Recently work crews made the road wider on Cawongla Road around the landslip area. You can locate the exact region through viewing our IntraMaps and selecting ‘Major Flood Recovery Works’ these works are found at damage No. DM00666.Geotechnical Investigations
During the month our contractors closed Wallace Road and Oakey Creek Road to perform geotechnical investigations. This involved using a drilling rig to understand subsurface conditions. We would like to thank residents for your patience and resilience during this time.
Koonorigan Road
Road maintenance works were recently completed for Koonorigan Road with a new seal laid to improve the road condition and impact on residents. Geotechnical investigations were also performed during this period, and we would like to thank the community for their continuing patience.CURRENT WORKS
Carabeen Place
Carabeen Place is progressing on schedule with asphalt now completed at the site. Work crews are finalising works to prepare for a reopening of the site. Thank you to the residents for your patience during the works period.
Nimbin Road
The works are progressing on schedule for Nimbin Road with Site Km1.0 is on track to open before the end of the year. The total extension of the remediation works for the site is 120m with 239 piles now installed with the total length of 3,226 linear meters. Additionally, 150m3 of concrete have been used for the construction of the pile cap with 611 blocks placed on top of the pile cap to allow the reconstruction of the road.
FUTURE WORKSZouch Road
Following the February 2022 natural disaster, Zouch Road suffered extensive damage. Funding has now been secured to complete geotechnical investigations using a drilling rig to understand subsurface conditions. The full road closure will no longer be in place as work crews have been able to contract a smaller drilling rig for the works. A smaller rig allows the team to establish a temporary track for resident cars to drive through the work zone to access their properties during the works period. As a result of this change, the works will change to occur from 7am to 5pm between the 6th to 15th of December. The works are located approximately between the intersection with Stoney Chute Road and to the west along Zouch Road approximately 400m. Motorists will be notified of further information via roadside signage and updated through www.livetraffic.com. Emergency services vehicles will be accommodated during these works. Please adhere to all road closed signs and directions from any traffic controllers and expect delays. We apologise for any inconvenience. Further information can be sourced on the original works post: -
Flood Restoration - Roads & Bridges Update (Sept 2023)
Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Sept 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Bungabbee Road
Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.
Dudgeon Road BridgeWorks were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.
Major Flood Recovery Works Map
Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.
CURRENT WORKS
Nimbin Road
Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.
Keerrong Road
Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.
Geotechnical Investigations
The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.
Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.
Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.
Cawongla Road
Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.
-
Geotechnical Investigations & Survey (Aug 2023)
Share Geotechnical Investigations & Survey (Aug 2023) on Facebook Share Geotechnical Investigations & Survey (Aug 2023) on Twitter Share Geotechnical Investigations & Survey (Aug 2023) on Linkedin Email Geotechnical Investigations & Survey (Aug 2023) linkInterim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.
Commencing - 4th of September
Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.Commencing - 18th of September
Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.
Commencing - 16th of October
Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road
There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’
-
Flood Restoration - Roads & Bridges Update (July 2023)
Share Flood Restoration - Roads & Bridges Update (July 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (July 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (July 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (July 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Pavement Investigations
During July, Council completed pavement investigations involving drilling operations on the following roads:
- Rock Valley / Cawongla Road
- Crofton Road
Cawongla Road
During July, flood remediation drainage works were completed on Cawongla Road.
CURRENT WORKS
Nimbin Road
Roadworks have commenced on two landslip sites on Nimbin Road that have been identified as significantly impacted by the February 2022 natural disaster. Funding was secured through the Disaster Recovery Funding Arrangement (DRFA). This funding is allocated to repair damage sustained during the February 2022 natural disaster only.
Works have already commenced at both sites, with Site 1 is approximately 1 km from Nimbin and Site 2 is approximately 4 kms from Nimbin. The works are currently on program at Site 1 with bulk earthworks now completed and 80 piles out of 240 are now installed. In the following weeks, concrete works are due to commence. At Site 2, there is an approximately 2 weeks delay due to the requirement to construct additional erosion protection to stop the soil washing away in heavy rain. The gabion erosion protection will be completed this week and pile installation will commence in 2 weeks’ time.
The works are expected to occur over 9 months from mid-May 2023 subject to weather, contractor, and material availability. This will involve piling and retaining wall construction works to allow repair of the landslips, reconstruction of pavement, reinstatement of road and guardrail barriers along with installing signs, guideposts, and line marking. Traffic control lights remain in place and existing single lane traffic control will remain in place during the works period. Council would like to thank the residents of the region for their patience during this time.Pavement Investigations
Council staff are continuing to perform pavement investigations involving drilling operations on the following roads:
- Blue Knob Road
- Jiggi Road
- Gwynne Road
- Nimbin Road
-
Flood Restoration - Roads & Bridges Update (May 2023)
Share Flood Restoration - Roads & Bridges Update (May 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (May 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (May 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (May 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Wallace Road
Council recently completed temporary pavement patching works around the slip area on Wallace Road to improve road surface conditions. The works are a temporary measure, until permanent pavement rehabilitation works are scheduled.
Mackie Road
Following the AGRN943 2020 natural disaster the Mackie Road causeway at Johnston Creek suffered extensive damage. Funding was awarded to replace the damaged structure with a bridge to reduce impediments to fish passage. The Mackie Road culvert to bridge replacement at Johnston Creek works are now completed with the road opening at the end of May 2023. Work at site began in March and during May the bridge concrete pours, guardrail installation and bridge approaches were completed, with the final stage of works involving bitumen sealing and batter protection. Council would like to thank residents and road users for their patience during the road closure.
CURRENT WORKS
Tuntable Creek Road
Recently, council staff were forced to close Tuntable Creek Road for two days due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes. As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence. In the event of rainfall exceeding our trigger level or other significant changes, the temporary track will be closed again at short notice. Please contact floodrecoveryroadsbridges@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
Nimbin Road
Council commenced roadworks on two landslip sites on Nimbin Road during May. The first major construction works involve tree felling for both sites, with site one having larger trees which will land on the road. The works are expected to occur over 9 months from mid-May 2023 subject to weather, contractor, and material availability. This will involve piling and retaining wall construction works to allow repair of the landslips, reconstruction of pavement, reinstatement of road and guardrail barriers along with installing signs, guideposts, and line marking. Traffic control lights remain in place and existing single lane traffic control will remain in place during the works period. Road users are advised to follow VMS boards and signage, with delays expected as these works commence.
Town Road
Funding was awarded by the NSW Government through its Fixing Country Bridges program to replace the damaged structure at Town Road, Terania Creek with a new steel superstructure bridge. The innovative steel structure has been constructed in France and will be launched into place in one piece. Unique for the area, this type of structure will be the first in the region. Works have recommenced at the site in April 2023, where a temporary track has now been constructed in preparation for bridges piling. A planned completion date is scheduled for September 2023, subject to weather, contractor, and material availability.
Wyrallah Road & Wyrallah Ferry Road
During May, the rock bridging layer and subbase layer were completed for Wyrallah Ferry Road intersection, with works starting at the end of May on drainage. Pipes were also laid through the park at Wyrallah Ferry Road Intersection. During June, all drainage works are scheduled to be completed followed by site clean-up and project completion.
Cawongla Road
Drainage works on Cawongla Road are continuing with two new sections recently completed. It is anticipated work crews will reach the halfway mark next week. Council would like thank residents for their positive feedback and continued patience as the works progress.
FUTURE WORKS
Branch Creek Crossing, Terania Creek Road
Following the 2022 natural disaster Terania Creek Road suffered extensive damage. Due to the nature and high number of damages incurred, works are being finalised on how best to provide timely improvements for the community and road users. The current structure at Branch Creek Crossing has received funding from disaster recovery funding arrangement (DRFA) for replacement of the flood damaged asset. An alternative structure is necessary to increase resilience of the network. Works will include replacing the current box culvert structure with a 16m bridge and extending erosion protection to the edge of the road. Additional works required and subsequent funding for other damages on Terania Creek Road are being assessed. Survey and design work is commencing in June 2023.
-
Flood Restoration - Roads & Bridges Update (Feb 2023)
Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Feb 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Feb 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please email floodrestoration@lismore.nsw.gov.au with subject ‘Add Road Name - Notification list’ to register your contact details to receive updates.
COMPLETED WORKS
Tuntable Creek Road
Tuntable Creek Road experienced significant damage during the February 2022 natural disaster with 11 notable landslips recorded and a major landslip closing the road north of intersection with Rose Road. A temporary solution was designed to open the road and establish connectivity between Nimbin and The Channon while the permanent solution is designed. The temporary construction consists of stabilising the embankment below the road and excavating into the slope above the road to make a single trafficable lane. The stabilisation will use up to 160 8m long soil nails and over 400m2 of sprayed concrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control. The works are expected to be complete in March with the road opened to local access only and restricted during weather events. For further details please visit the Tuntable Creek Road update:
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/tuntable-creek-road-jan-2023
Cawongla Road
The Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods.
Gwynne Road
Temporary repair of damaged pavement was recently completed for Gwynne Road. During these works, the crews also performed scour repair and mulching vegetation along with cleaning drains and pipes to improve the roads condition.
Unsealed Roads
Overlay works to repair damages from the October flood event were recently completed for Lagoon Grass Road, Howards Grass Road, Cusack Road, Booerie Creek Road, Hewitt Road, Swan Bay Road, and Sheehan Road.
Johnston Road
Temporary patching works across slip single lane were recently completed for Johnston Road.
CURRENT WORKS
Crofton Road & Rock Valley Road
Drainage works are continuing for Crofton Road and Rock Valley Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.Wyrallah Road
Pavement rehabilitation works started at the end of January to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:
FUTURE WORKS
Town Road
Funding through the Fixing Country Bridges program has been awarded to replace the damaged structure with a new bridge. The bridge superstructure is currently being constructed in France with an innovative steel beam that will be launched into place in one piece. A unique type of structure, this bridge will be the first in the region. A general plan of the works is provided below. The Town Road bridge superstructure will be delivered at the end of May 2023. Civil works are scheduled to begin in April 2023 with a planned completion in late July 2023, subject to fine weather. Further updates will be provided towards the end of March 2023.
Mackie Road
Following the 2020 natural disaster the Mackie Road causeway at Johnston Creek suffered extensive damage. Funding has been awarded to replace the damaged structure with a bridge to reduce impediments to fish passage. The Mackie Road culvert to bridge replacement at Johnston Creek, works will begin on the 13th of March for approximately three months with a planned completion in late June 2023, subject to fine weather. Due to the nature of the works a full 24-hour hard road closure is required during the March – June 2023 works period around the location detailed on the map below. For further details please visit the Mackie Road bridge update link below:
-
Flood Restoration - Roads & Bridges Update (Jan 2023)
Share Flood Restoration - Roads & Bridges Update (Jan 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Jan 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Jan 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Jan 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au
COMPLETED WORKS
Cawongla Road
Excitingly, the Cawongla Road pipes’ replacement project was ahead of schedule and the road opened at the end of January before school started. We would like to thank all the residents of Larnook and the surrounding region for their patience and cooperation during these repairs. The works consisted of replacing two culverts that suffered significant damage during the 2022 floods. Further details can be found on the latest Cawongla Road update on the following link:
Sheehan Road
Works have been completed on Sheehan Road to address issues caused from the February and March 2022 floods. This has involved overlay and drainage works to repair flood damages.
Mountain Top Road, Standing Street, Nimbin Street & Wallace Road
Overlay works have been completed on Mountain Top Road, Standing Street, Nimbin Street and Wallace Road, to address issues caused from the February and March 2022 floods.
Blue Knob Road
Works are completed for Blue Knob Road, these included removing and replacing the existing material from the road surface, along with grading and rolling the road with a temporary seal over the new surface. A planned return to complete permanent works will be scheduled during 2023.
CURRENT WORKSTuntable Creek Road
The works crew remobilised to the site at the beginning of January, this stage of construction consists of excavating into the slope above the road and installing 49 soil nails and 100m2 shotcrete. Additionally, crews are also reconstructing pavement through the slip zone and installing light traffic control and opening one lane. The works are expected to be complete in February with additional updates to be provided as the works commence on the upper slope. For further details please visit the Tuntable Creek Road update link below:
Wyrallah Road
Pavement rehabilitation works are commencing shortly to reconstruct and rehabilitate approximately 500m of Wyrallah Road. Throughout this construction process drainage works, kerb installation and subsoil installation will also be completed. For further details please visit the Wyrallah Road update link below:
Swan Bay Road
Overlay and drainage works are currently underway to repair damages from the October flood event for Swan Bay Road.
Crofton Road & Rock Valley/Cawongla Road
Drainage works are continuing for Crofton Road and Rock Valley/Cawongla Road these include desilt and reshape table drainage, installing headwalls and pipe extensions as required to ensure water runoff from the road, to prevent future road damages from occurring.FUTURE WORKSMunro Wharf Road
Overlay and drainage works to repair damages from the October flood event will commence shortly for Munro Wharf Road.