• Pinchin Road - Pavement Stabilisation Repair commencing 29th August 2022

    Share Pinchin Road - Pavement Stabilisation Repair commencing 29th August 2022 on Facebook Share Pinchin Road - Pavement Stabilisation Repair commencing 29th August 2022 on Twitter Share Pinchin Road - Pavement Stabilisation Repair commencing 29th August 2022 on Linkedin Email Pinchin Road - Pavement Stabilisation Repair commencing 29th August 2022 link

    Pinchin Road is scheduled to undergo pavement repairs on some sections of severely damaged areas from Monday 29th August 2022.

    Initially the works will start with drainage remediation to allow water to drain from the pavement. Following these works there will be a pavement stabilisation crew mobilising to site to stabilise the existing pavement. As well as adding an additional 100mm of new road base material to improve the pavements strength.

    This work is a large roads maintenance activity and will take approximately 5 weeks to complete (weather permitting).

    A single lane traffic closure will allow traffic to travel through the worksite. Signage will be in place to notify road users, and updates available on Live Traffic NSW. Works on Keerrong Road will be postponed from September 1st, to allow additional traffic flow while Pinchin Road works are completed.

  • Johnston Road - Landslip Closure

    Share Johnston Road - Landslip Closure on Facebook Share Johnston Road - Landslip Closure on Twitter Share Johnston Road - Landslip Closure on Linkedin Email Johnston Road - Landslip Closure link

    Following the February 28 and March 2022 flooding events, a road embankment landslip and tension cracking have occurred on Johnston Road, approximately 1km from Bangalow Road.

    There is currently an interim road closure in place, allowing local access only. Geotechnical borehole drilling and the installation of inclinometers and piezometers will commence from Monday 22nd of August for one week (subject to weather and ground conditions). For the safety of motorists, a full road closure at the slip location will be in place for the duration of these works , with access granted to the properties located within the road closure only. To ensure your travels are not delayed, please review the road closure location to determine whether accessing from Eltham Road or Bangalow Road is most appropriate for your property.

    Minor surface grade repairs, shoulder works and signposting for longer term traffic arrangements will also take place during this time. On completion of these works, the road will be reopened to one lane of traffic under a give-way arrangement at the slip locations. This arrangement will remain in place for several months until full remediation work commences.

    A detailed site survey will be needed to get a full understanding of the landslips impact to the surrounding area, and to undertake the detailed design of the restoration. The survey will take approximately 2 days and will be completed after the geotechnical investigations, dates TBC. The survey will involve a combination of traditional (on foot) and drone survey, as per the extent in the following image. During the survey you may see surveyors working on the side of the road, or a drone flying overhead.

    On-going monitoring of the inclinometers and piezometers will be required for a few months following the installation (timeframe will be confirmed from the data recorded). This on-going monitoring will ensure the slips behaviour / displacement is fully understood and the design of the remediation is robust and fit-for purpose. The on-going monitoring will involve a geotechnical engineer re-visiting the instruments once per week and taking readings by hand for approximately 30 minutes at each location. The instruments will be located within the shoulders of the road to enable the readings to take place with no impact to traffic. The approximate locations of the instruments are shown below.

    The geotechnical investigations and survey will determine the detailed design and cost of the repair, which will be included in an application for funding to complete this work. Approval for funding is anticipated to be received by the end of August. Construction is planned to be commenced by the end of 2022, subject to approvals, contractor availability and weather.

    Further updates will be shared via this page as works continue.

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Johnston Road’ in your correspondence.

  • Skyline Road - Geotechnical Drilling

    Share Skyline Road - Geotechnical Drilling on Facebook Share Skyline Road - Geotechnical Drilling on Twitter Share Skyline Road - Geotechnical Drilling on Linkedin Email Skyline Road - Geotechnical Drilling link

    ***Update Thursday 1 September, 2022***

    South Skyline Road closure will be extended until Wednesday 7/9/2022 next week due to difficult drilling conditions. We are aiming to have the rig off the road, and the road opened up over the weekend.***



    Following the February 28 and March 2022 events, Skyline Road has suffered damage due to a landslip, adjacent to 353 Skyline Road. Funding has now been secured to complete remediation works.

    To undertake remediation, geotechnical drilling under engineer supervision is required. Instruments to monitor further ground movement and water table will be installed for monitoring, to assist designers and determine the scope of works.

    Drilling is expected to commence this week. Motorists will be advised via roadside signage. A track is available each way allowing access past the slip. Please use caution and drive carefully.

    Further updates, including commencement of construction for remediation at a later date will be shared via the News Feed tab of this page.

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Skyline Road Landslip’ in your correspondence.

  • WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022

    Share WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022 on Facebook Share WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022 on Twitter Share WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022 on Linkedin Email WEEKLY POTHOLE SCHEDULE - 8TH AUGUST 2022 link
    OUR WEEKLY POTHOLE REPAIR SCHEDULE


    It looks like it’s going to be another glorious week in paradise, with little to no rain predicted.
    What is not so glorious are the potholes in our roads.

    Our road crews are working their way through the list of roads that require temporary pothole repair, as we also continue with other road works to repair the significant damage caused by the February natural disaster.

    It is a massive job, and we thank you for your patience.


    This week our pothole repair team will focus on:
    Rock Valley Road
    Nimbin Road
    Dunoon Road
    Blue Knob Road
    Wyrallah Road
    Kyogle Street
  • Temporary Closure - Gundurimba Road Sexton Bridge Replacement Project

    Share Temporary Closure - Gundurimba Road Sexton Bridge Replacement Project on Facebook Share Temporary Closure - Gundurimba Road Sexton Bridge Replacement Project on Twitter Share Temporary Closure - Gundurimba Road Sexton Bridge Replacement Project on Linkedin Email Temporary Closure - Gundurimba Road Sexton Bridge Replacement Project link

    Council wishes to advise that bridge replacement works will start shortly on Sexton Bridge, located on Gundurimba Road, Monaltrie. These works are due to get underway during the week commencing 15 August 2022. The location of works is shown below.

    What do the works involve?

    The works will involve the temporary road closure of Gundurimba Road to enable the construction of a new concrete bridge.

    Bridge construction works will include the following:

    • Temporary closure of Gundurimba Road at the site (access to property available via detours, see below)
    • Demolition of the existing timber bridge structure
    • Initial earthworks in preparation for foundation works
    • Installation of driven reinforced concrete piles
    • Installation of concrete bridge abutments and beams
    • Reinstatement of road pavement
    • Signage and line marking.

    When will the works start and what are the hours of work?

    Works will start in the week commencing 15 August 2022. We expect the project will take about 12 weeks to complete, subject to suitable weather conditions and contractor availability.

    Work hours:

    • 7am to 6pm Monday to Friday
    • 8am to 1pm on Saturdays
    • No work Sundays or public holidays.

    If there is a requirement to change these hours, updates will be available via the '

    What are the traffic adjustments?

    During this bridge replacement, traffic will be detoured as a result of the temporary road closure of Gundurimba Road. Traffic will be detoured via the following routes:

    Northbound traffic:

    • Via Monaltrie Road, Wyrallah Road and Bruxner Highway

    Southbound traffic:

    • Via Bruxner Highway, Wyrallah Road and Monaltrie Road

    What do I need to do?

    Please obey the temporary traffic conditions in place and allow additional time for travel.

    We apologise in advance for disruptions you may experience whilst we replace Sexton Bridge. We would appreciate your cooperation with all temporary traffic control and workplace protection measures onsite to help keep everyone safe.

    If you have further questions or concerns, please do not hesitate to contact Lismore City Council via council@lismore.nsw.gov.au, or call (02) 6625 0500

  • Current Road Project Updates 5 August 2022

    Share Current Road Project Updates 5 August 2022 on Facebook Share Current Road Project Updates 5 August 2022 on Twitter Share Current Road Project Updates 5 August 2022 on Linkedin Email Current Road Project Updates 5 August 2022 link

    Gravel Roads (Flood Repair Works) – approximately 50% of LCC Gravel Roads have been repaired now since the Feb/March 2022 events.

    Caniaba Road – Drainage and shoulder widening works progressing well. Project is currently running to plan with minimal delays.

    Richmond Hill Road – the landslip has been repaired and pavement rehabilitation works are progressing.

    Nimbin Road near Goolmangar School – urgent maintenance works were carried out last week, the damaged sealed pavement was returned to gravel. This section of road will be overlaid with new gravel and stabilised this month

    Keerrong Road Bridge – the new concrete bridge is now complete and earthworks progressing on the approaches

    Henson Bridge – Piling is now complete, works progressing well on preparing the bridge abutments (form/reo/poor)

    Keerong Road – Landslip and drainage remediation works are commencing, leading to a road closure from August 10th - adjacent to 1265 Kerrong Road. Motorists are advised via roadside signage. Pavement strengthening works are also progressing on approximately a 1km section. Further pavement works are scheduled.

    Bruxner Highway at Northcott Road – pavement rehabilitation works are progressing which have included stabilisation of the existing material and overlay with new gravel.

    Gungas Road – shoulder widening and pavement works are progressing.

    Cowlong Road – pavement strengthening works are progressing south of McKenzie Road.

    Jiggi Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    Pinchin Road - flood restoration works to commence shortly, to improve overall road conditions. Further information has been mailed to local residents, and is available in 'Community Updates' tab.

    One section of Jiggi Road, preconstruction on 04/08/22

    Wyrallah Road - Geotechnical drilling to determine scope of works.

    Drilling at Wyrallah Road 27/07/22

    Dunoon Road (near the Macadamia Factory) - Temporary patching on a section of road adjacent Macadamia factory on Dunoon Road. This section of road is due for full pavement reconstruction in October this year.

    a section of Dunoon Road before temporary patching 02/08/22

  • SOLAR PROJECT AND REPAIRS AT CLYDE CAMPBELL CARPARK

    Share SOLAR PROJECT AND REPAIRS AT CLYDE CAMPBELL CARPARK on Facebook Share SOLAR PROJECT AND REPAIRS AT CLYDE CAMPBELL CARPARK on Twitter Share SOLAR PROJECT AND REPAIRS AT CLYDE CAMPBELL CARPARK on Linkedin Email SOLAR PROJECT AND REPAIRS AT CLYDE CAMPBELL CARPARK link
    supporting image
    We are continuing to update the community on the extensive repair work Council is undertaking across our road network and any updates on our planned projects.


    Among many other roads, our crews are working on two projects at the Clyde Campbell Carpark.


    Construction of the Clyde Campbell Solar Carpark and EV Charging Station officially commenced in early July. Electrical work for the 75kW DC fast Electric Vehicle (EV) charger, capable of charging two cars at one, has been installed.


    Today crews resurfaced the area of the Solar Carpark with asphalt and prepared the landscaping sections.


    The next phase of this project will be constructing a 100kW solar array, which doubles as a shade structure – Engineered to withstand floods.


    At the same time today, the carpark was repaired in sections from damage due to the 28 February natural disaster. Crews prepared the surface of the carpark and resurfaced it with asphalt.


    We will keep our community up to date on the solar project and repair work of the carpark.


    For the latest updates on our road works, please visit the dedicated Maintaining our Roads update page on Your Say website at https://yoursay.lismore.nsw.gov.au/maintaining-our-roads..., where you can ask questions about this road closure or any other current road works occurring in the Q+A section of the page.


  • Planned Flood Restoration Maintenance Works - Pinchin Road

    Share Planned Flood Restoration Maintenance Works - Pinchin Road on Facebook Share Planned Flood Restoration Maintenance Works - Pinchin Road on Twitter Share Planned Flood Restoration Maintenance Works - Pinchin Road on Linkedin Email Planned Flood Restoration Maintenance Works - Pinchin Road link

    Council plans to undertake roadworks on sections of Pinchin Road.

    This planned work is proudly funded by both the New South Wales (NSW) and the Australian Governments.

    Where are the roadworks?

    The roadworks will apply to numerous designated sections across the full length of Pinchin Road.

    Why do the roadworks?

    The roadwork will improve road conditions and associated safety, and funding has been allocated due to the 28 February 2022 and March 2022 flooding events.

    What do the roadworks involve?

    The roadwork is to improve road safety through the following:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 150mm.

    • Signs and line marking: Line marking and guideposts.

    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.

    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.

    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    These works will be completed under single lane traffic control.

    When do the roadworks start?

    Works will be undertaken between August 2022 and October 2022. Once works commence, they should take approximately 4-6 weeks to complete (weather permitting).

    What do you need to do now?

    You do not need to do anything as this notification is just to let you know in advance of the roadworks. If you have any questions or local knowledge of issues for Council to consider in your area, you are welcome to contact our Civil Works Engineer.

  • Planned Flood Restoration Maintenance Works – Jiggi Road

    Share Planned Flood Restoration Maintenance Works – Jiggi Road on Facebook Share Planned Flood Restoration Maintenance Works – Jiggi Road on Twitter Share Planned Flood Restoration Maintenance Works – Jiggi Road on Linkedin Email Planned Flood Restoration Maintenance Works – Jiggi Road link

    Council plans to undertake roadworks on sections of Jiggi Road.

    This planned work is proudly funded by both the New South Wales (NSW) and the Australian Governments.

    Where are the roadworks?

    The roadworks will apply to numerous sections on Jiggi Road between Nimbin Road and Mountain Top Road.

    Why do the roadworks?

    The roadwork will improve road conditions and associated safety, and funding has been allocated due to the February and March 2022 flooding events.

    What do the roadworks involve?

    The roadwork is to improve road safety through the following:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 150mm.

    • Signs and line marking: Line marking and guideposts.

    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.

    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.

    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    These works will be completed under single lane traffic control.

    When do the roadworks start?

    Works will be undertaken between August 2022 and February 2023. Once works commence, they should take approximately 5-6 months to complete (weather permitting).

  • WEEKLY POTHOLE SCHEDULE-2 August 2022

    Share WEEKLY POTHOLE SCHEDULE-2 August 2022 on Facebook Share WEEKLY POTHOLE SCHEDULE-2 August 2022 on Twitter Share WEEKLY POTHOLE SCHEDULE-2 August 2022 on Linkedin Email WEEKLY POTHOLE SCHEDULE-2 August 2022 link
    Our pothole repair teams are fixing as many potholes as possible, especially with this fine winter weather.


    We understand that there are many potholes to be repaired and ask for the community’s patience as we undertake this work.


    This week we have three Hotmix Teams and two Autopatches repairing damaged roads.


    This week our pothole repair teams are focusing on:


    Eltham Road
    Diadem Street
    Rosehill Road
    Nimbin Rd
    Blue Knob Road
    Cawonlga Road


    Preparations will also begin for Night Work starting on Monday, 8 August to conduct heavy patching on Wyrallah Rd and Dalley St (north end of roundabout approach).


    Take care on the roads, and please always drive to the conditions as we fix our roads.