• Current Project Updates Tuesday, 11 October 2022

    Share Current Project Updates Tuesday, 11 October 2022 on Facebook Share Current Project Updates Tuesday, 11 October 2022 on Twitter Share Current Project Updates Tuesday, 11 October 2022 on Linkedin Email Current Project Updates Tuesday, 11 October 2022 link

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au

    Caniaba Road - Shoulder widening and kerb and gutter installation completed, awaiting pavement backfill against kerb.

    Caniaba Road

    Blue Knob Road - Drainage and preparation work started this week, with further stabilisation works scheduled on various sections for next week - subject to weather, contractor and material availability. The landslip is being monitored as scope of works is determined.

    Gravel road repairs - Young Road, Noble Road, Robb Road, Milgate Road, Beardow Road, Browning Road, Fairfull Road, Gibson Lane have all undergone maintenance. Upcoming maintenance is scheduled for Webber Road, Cook Road, Tulk Road, Fraser Road, Rose Road, Wybelena Road and Gray Road.

    Gundurimba Road - Drainage works are scheduled for completion on various sections.

    Gungas Road - Emergency culvert repair on Gungas Road, following damage sustained after recent heavy rainfall.

    Gungas Road - emergency repairs

    James Gibson Road - Temporary patching is scheduled, while scope of works for remediation is finalised.

    Jiggi Road - First section has been completed, with an additional five to be completed. There have some delays due to weather, with scope of works reviewed to ensure damages due to heavy rainfall are remediated. Proposed works include pavement rehabilitation and drainage works.

    Keerrong Road - Final stages of works, with a tidy up to be completed. Additional sections are scheduled for maintenance in December.

    Nimbin Road - Drainage and Stabilisation are being completed on Nimbin Road with four patches completed out for the six scoped for repair. Guide posting and line marking works still to be completed. Stabilisation works are also scheduled for Nimbin Road (near Shipway Drive and Swift Road) in the coming weeks - subject to weather, contractor and material availability.

    Pinchin Road - Final stages of completion on the sections of heavy patching works.

    Pinchin Road - heavy patching completed

    Sexton Bridge - Bridge deck pour and earthworks are currently being completed.

  • MAJOR WATER BREAK ACROSS KELLAS STREET

    Share MAJOR WATER BREAK ACROSS KELLAS STREET on Facebook Share MAJOR WATER BREAK ACROSS KELLAS STREET on Twitter Share MAJOR WATER BREAK ACROSS KELLAS STREET on Linkedin Email MAJOR WATER BREAK ACROSS KELLAS STREET link
    A major water break has occurred across Kellas Street, in Lismore Heights.


    The road has sustained major damage and is in need of significant repairs. The section of road impacted by the water break will need to be rebuilt.
    Due to the extent of the repairs, the road will be closed until Friday, 14 October 2022.


    Bus companies and emergency services have been notified. Detours have been setup for access to the University and other services within this area.
    Travelling East, detours are in place via Dibbs Street, Dalley Street and Military Road.
    Travelling West, detours are in place via William Blair Drive and Parkwalk Drive to University Road.
  • WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE

    Share WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE on Facebook Share WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE on Twitter Share WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE on Linkedin Email WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE link

    WEEKLY TEMPORARY POTHOLE REPAIR SCHEDULE

    We hope everyone enjoyed their long weekend.

    The good weather to start off the week has allowed our pothole repair teams to get out and about. They are focusing on:

    ๐Ÿ‘‰ Pinchin Road

    ๐Ÿ‘‰ Tuntable Falls Road

    ๐Ÿ‘‰ Kyogle Road

    ๐Ÿ‘‰ Urban Roads

    While progress is being made to repair potholes across our road network, it remains a massive job which is made worse every time it rains. We thank the community for their on-going patience.

    To report a pothole in need of repair, go to https://ecouncil.lismore.nsw.gov.au/eservice/crm/selectCategory.do?key_num=478&nodeNum=148596&nodeNum//=148596

  • Mountain Top Road - Flood Recovery

    Share Mountain Top Road - Flood Recovery on Facebook Share Mountain Top Road - Flood Recovery on Twitter Share Mountain Top Road - Flood Recovery on Linkedin Email Mountain Top Road - Flood Recovery link

    Geotechnical drilling is required to investigate sub surface conditions at landslips which have occurred on Mountain Top Road, starting from approximately 500mtrs north of the Jacobson Road intersection. To ensure safety for motorists, a full road 24-hour road closure is required at the work zone for approximately three weeks, starting Monday, 10th October. Road closure has been in place since March, due to the nature of the slips.

    A road closure with traffic detour is required, as the drill rig being used will block the entire road during operation. Please consider if access to your property is best via Jiggi Road or Stony Chute Road to avoid unnecessary delays.

    <165 Mountain Top Road โ€“ Access via Jiggi Road

    221> Mountain Top Road โ€“ Access via Stony Chute Road

    ***UPDATE - Jiggi Road - First section has been completed, with an additional five to be completed. There have some delays due to weather, with scope of works reviewed to ensure damages due to heavy rainfall are remediated.***

    The construction schedule to remediate the landslip will be determined based on the scope of works and availability of subsequent contractors. Construction is expected to occur in 2023, residents will be notified at each stage of the works. Temporary measures including gravel fill, to improve driving conditions of Mountain Top Road will be completed shortly while permanent landslip remediation works are reviewed.

    Further updates will be shared via the Maintaining Our Roads and Bridges Your Say article: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference โ€˜Mountain Top Road Closureโ€™ in your correspondence.

  • Dunoon Road - Pavement Rehabilitation Works

    Share Dunoon Road - Pavement Rehabilitation Works on Facebook Share Dunoon Road - Pavement Rehabilitation Works on Twitter Share Dunoon Road - Pavement Rehabilitation Works on Linkedin Email Dunoon Road - Pavement Rehabilitation Works link

    Single lane traffic control will be in place as Council completes pavement rehabilitation works to Dunoon Road. The works will apply to one section across the length of Dunoon Road, to be completed throughout five months starting late October 2022 subject to weather, contractor, and material availability.

    Funding has now been secured through the Safer Roads Program and Black Spot Program to complete these works, which will improve road conditions and associated safety for road users. Additional works for Dunoon Road will continue to be assessed and reviewed.

    Works will include:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 250mm.
    • Signs and line marking: Line marking and guideposts.
    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.
    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    Road users are advised to follow signage and expect delays as these works are completed.

    Further Information

    Updates for these works will be posted on our Your Say dedicated Maintaining Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges

    Should you wish to contact us directly with any questions or comments, or register your details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title โ€˜Dunoon Road โ€“ Pavement Rehabilitation.โ€™

  • The Channon Road - Pavement Rehabilitation Works

    Share The Channon Road - Pavement Rehabilitation Works on Facebook Share The Channon Road - Pavement Rehabilitation Works on Twitter Share The Channon Road - Pavement Rehabilitation Works on Linkedin Email The Channon Road - Pavement Rehabilitation Works link

    Single lane traffic control will be in place as Council completes pavement rehabilitation works to The Channon Road. The works will apply to one section across the length of The Channon Road, to be completed through within approximately 3 months starting October 2022 subject to weather, contractor, and material availability.

    Funding has now been secured through the Fixing Local Roads Program, to complete these works which will improve road conditions and associated safety for road users. Additional works for The Channon Road will continue to be assessed and reviewed.

    Works will include:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 100mm.
    • Signs and line marking: Line marking and guideposts.
    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.
    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    Road users are advised to follow signage and expect delays as these works are completed.

    Further Information

    Updates for these works will be posted on our Your Say dedicated Maintaining Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges

    Should you wish to contact us directly with any questions or comments, or register your details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title โ€˜The Channon Road โ€“ Pavement Rehabilitation.โ€™

  • Gundurimba Road - Pavement Rehabilitation Works

    Share Gundurimba Road - Pavement Rehabilitation Works on Facebook Share Gundurimba Road - Pavement Rehabilitation Works on Twitter Share Gundurimba Road - Pavement Rehabilitation Works on Linkedin Email Gundurimba Road - Pavement Rehabilitation Works link

    Single lane traffic control will be in place as Council completes pavement rehabilitation works to Gundurimba Road. The works will apply to three sections across the length of Gundurimba Road, to be completed through October 2022 subject to weather, contractor, and material availability.

    Funding has now been secured from TfNSW to complete these works which will improve road conditions and associated safety for road users. Additional works for Gundurimba Road will continue to be assessed and reviewed.

    Works will include:

    • Road surface: Improve the surface of the road in places. Road to be raised approximately 150mm.
    • Signs and line marking: Line marking and guideposts.
    • Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.
    • Drainage maintenance: Re-excavate open drains and remove flood sediment as required.
    • Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    Road users are advised to follow signage and expect delays as these works are completed.

    Further Information

    Updates for these works will be posted on our Your Say dedicated Maintaining Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges

    Should you wish to contact us directly with any questions or comments, or register your details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title โ€˜Gundurimba Road โ€“ Pavement Rehabilitation.'

  • Blue Knob Road - Pavement Rehabilitation Works

    Share Blue Knob Road - Pavement Rehabilitation Works on Facebook Share Blue Knob Road - Pavement Rehabilitation Works on Twitter Share Blue Knob Road - Pavement Rehabilitation Works on Linkedin Email Blue Knob Road - Pavement Rehabilitation Works link

    Single lane traffic control will be in place as Council completes pavement rehabilitation works to Blue Knob Road. The works will apply to three sections across the length of Blue Knob Road, to be completed through October 2022 subject to weather, contractor, and material availability.

    Funding has now been secured from TfNSW to complete these works which will improve road conditions and associated safety for road users. Additional works for Blue Knob Road will continue to be assessed and reviewed

    Works in the three sections will include:

    Road surface: Improve the surface of the road in places. Road to be raised approximately 150mm.

    Signs and line marking: Line marking and guideposts.

    Vegetation management: Manage roadside vegetation to remove obstacles, improve sight distances, and clearances for signage.

    Drainage maintenance: Re-excavate open drains and remove flood sediment as required.

    Driveway adjustment: Adjust access to driveways affected by the wider road footprint as required.

    Road users are advised to follow signage and expect delays as these works are completed.

    Further Information

    Updates for these works will be posted on our Your Say dedicated Maintaining Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges

    Should you wish to contact us directly with any questions or comments, or register your details to receive updates, please call (02) 6625 0500 or email council@lismore.nsw.gov.au and include the title โ€˜Blue Knob Road โ€“ Pavement Rehabilitation.

  • WEEKLY POTHOLE REPAIR SCHEDULE

    Share WEEKLY POTHOLE REPAIR SCHEDULE on Facebook Share WEEKLY POTHOLE REPAIR SCHEDULE on Twitter Share WEEKLY POTHOLE REPAIR SCHEDULE on Linkedin Email WEEKLY POTHOLE REPAIR SCHEDULE link
    We hope everyone enjoyed the sunshine over the weekend. It was certainly helpful in starting to dry out our roads after the last few days of last week.
    As the good weather continues, our pothole repair teams will be out and about focusing on:


    Koonorigan Road
    Tuntable Falls Road
    Aphadale Road
    Kyogle Road
    Rosehill Road
    Urban roads


    While progress is being made to repair potholes across our road network, it remains a massive job which is made worse every time it rains. We thank the community for their on-going patience.
  • Current Road Project Updates 26 September 2022

    Share Current Road Project Updates 26 September 2022 on Facebook Share Current Road Project Updates 26 September 2022 on Twitter Share Current Road Project Updates 26 September 2022 on Linkedin Email Current Road Project Updates 26 September 2022 link

    Please note, there are several road and bridge projects progressing concurrently. Below are updates of some projects progressing this week.

    Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like to secure specific updates on, please utilise the Q+A function of this page, or email council@lismore.nsw.gov.au

    Canaiba Road - Shoulder widening and kerb gutter installation completed. Awaiting pavement backfill against the kerb.

    Cowlong Road - Final stage of construction has been completed. Drainage currently undergoing review.

    Crofton Road - Damages have been scoped, and will be submitted this week.

    Dunoon Road - Approved for heavy patch stabilising in flood damaged sections. Schedule of works to be confirmed shortly.

    Fernside Road - Fernside Bridge side-track bitumen sealing and culvert shotcrete application completed.

    Gravel road repairs - Numulgi Creek Road, Beddoes Road, Borton Road will be undergoing repairs this week. Gravel road maintenance continues for Precinct 12 (Corndale, Dunoon and Rosebank). Gravel Roads in Precinct 11 (The Channon, Terania Creek and Tuntable Creek) scheduled for October.

    Gray Road - Works are progressing, with drainage still to be completed. Vegetation management is currently being reviewed.

    Gungas Road - Erosion protection works to commence shortly.

    Jiggi Road - Some sections have been completed, with additional pavement repair works still to be scheduled. These works will continue as subsequent projects are completed in the area, to ensure efficiency.

    Keerrong Road - Culvert replacement between Keerrong Bridge Road and Nimbin Road. Single lane road closure will be in place as works are completed. Please adhere to road signage and drive with caution.

    Koonorigan Road - The landslip area has been assessed, and safe for motorists. Please drive to the conditions. This will continue to be monitored and is under review for works. Heavy patch stabilising has been approved, and received funding. Emergency patching adjacent to the hall is scheduled to commence shortly.

    Nimbin Road - A total of six heavy patching sections to be repaired. All drainage works have been completed on first three patches, with drainage works on the final three to be completed by end of next week. Approximately 1km of the first patch has been sealed, with seal on the other half of this section still to be completed.

    Northcott Road - Final stage of Northcott Road has been completed.

    Pinchin Road - Five heavy patching sections have been completed. One additional section remaining; only final trim and seal left to be completed. All drainage works and embankment failure/slip remediation completed (gabion wall constructed, damaged pipe replaced, road surface and pavement reinstated).

    Richmond Hill Road - Damaged section of pavement adjacent to Richmond Hill landslip resealed. Further shoulder work, guide posting, and line marking still to be completed.

    Sexton Bridge - Abutment works underway. Installation of both abutmentsโ€™ formwork on Wednesday 14th September with concrete poured Thursday 15th September. Bridge beams have now been landed, with skirting and abutment concrete pouring scheduled for the coming week (weather permitting).

    Tuckurimba Road - Temporary pothole repairs have been completed on a number of major potholes. Due to the low lying nature of the road, a flood study is required prior to permanent heavy patching works. These heavy patching works may change the road level, further details will be shared following assessments.