• Road Restoration Works - The Channon

    Share Road Restoration Works - The Channon on Facebook Share Road Restoration Works - The Channon on Twitter Share Road Restoration Works - The Channon on Linkedin Email Road Restoration Works - The Channon link

    ***Unfortunately due to ongoing wet weather, the below schedule is being pushed back. Please see Community Updates on the main article HERE for further details***

    Due to significant flood damage, Lismore City Council will be continuing works to repair roads. The following are proposed to take place throughout May and June 2022.

    Location

    Reason

    Traffic Plan

    Duration

    Dates

    Terania Creek Road

    Landslip north of Lawler Road

    Geotechnical investigations using drilling rig, to understand subsurface conditions.

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    5 days

    25th May to 30th May

    Wallace Road

    Landslip 1.3km from Tuntable Creek Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    3 days

    30th May to 3rd June

    Black Road

    Causeway washed out

    Core drilling rock to determine strength for future rock anchors

    Road currently closed.

    1 day

    Depending on productivity of the full road closures

    Terania Creek Road

    Landslip between Izzard and Town Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    3 days

    Depending on productivity of the full road closures

    The Channon Road

    Landslip behind guardrail

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    2 days

    Depending on productivity of the full road closures

    *All closures will allow for pedestrian access.

  • Dunoon Road Closure - Emergency Works

    Share Dunoon Road Closure - Emergency Works on Facebook Share Dunoon Road Closure - Emergency Works on Twitter Share Dunoon Road Closure - Emergency Works on Linkedin Email Dunoon Road Closure - Emergency Works link

    ***Updates for this project, plus Q+A are posted on the main article HERE

    Due to significant flood damage, Lismore City Council will close both sides of Dunoon Road between Dorroughby Road and Repentance Creek Road starting on Monday, 4 April, 2022.

    The road is expected to be closed in a phased approach to accommodate the Easter long weekend where it will open up again with traffic lights for both directions. After Easter from Tuesday, 19 April the section of Dunoon Road will close again until 26 April, 2022.

    What do the works involve?

    • Excavation of existing road surface down to access base of embankment.
    • Reconstruct embankment using rock and select fill.
    • Reconstruct pavement and seal.
    • Damage to the sealed pavement on the approaches will be repaired also.

    When will the works start and what are the hours of work?

    Works will start in the week commencing 4 April 2022. We expect the project will take about 6 weeks to complete, subject to weather conditions.

    Work hours:

    • 4th to 14th April, 2022 24-hour closure (working hours 6:30am to 6:00 pm Monday to Saturday)
    • 15th to 25th April, 2022 Single Lane track open under automated traffic lights
    • 26th April to 22nd May, 2022 24-hour closure (working hours 6:30am to 6:00 pm Monday to Saturday)
    • No work Sundays or public holidays.

    If there is a requirement to change these hours, you will be notified.

    What are the traffic adjustments?

    During the road closure period, traffic will be detoured via Repentance Creek Road (turns into Rosebank Road) and Dorroughby Road.

    Electronic billboards will be displaying alerts for detours. Further details will be available on MyRoadInfo website.

    What do I need to do?

    Please obey the temporary traffic conditions in place and allow additional time for travel.

    We apologise in advance for disruptions you may experience whilst we complete these works. We would appreciate your cooperation with all temporary traffic control and workplace protection measures onsite to help keep everyone safe.

    Who should I contact for further information?

    If you have any questions or concerns, please post in the Q&A on the main article HERE. Our team will provide updates to share with the community.