Dunoon Road
Dunoon Road works at Boomerang Creek were completed on June 28th. Additional pothole repair works for Dunoon Road will be completed over the coming weeks.
The Channon Road
Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.
The Channon Road (Robertson Bridge)
Remediation works of the abutments is planned for week starting July 4th. Traffic control will be present, and motorists are advised to drive carefully.
Pinchin Road Embankment failure
Embankment reconstruction works are substantially complete. Pavement repair to the road surface will commence shortly.
Wallace Road
Geotechnical drilling has been completed. Inclinometers have been installed to monitor ground movement over the next month before design to build back better commences.
Keerrong Road
Bridge construction works are now underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August
Tuntable Creek Road
Investigation works north of rose road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.
Duncan Road- Corndale Road
Works have started to heavy patch and stabilise damaged sections.
Nimbin Road (slip north of Stoney Chute)
80% design drawings received and under review. Procurement of contractor proposed for this month.
Stoney Chute Road
Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.
Cawongla Road
Geotechnical drilling is underway.
Share Black Road reopen on Facebook
Share Black Road reopen on Linkedin
Email Black Road reopen link
Black Road is a short gravel road off Terania Creek, north of The Channon. The original creek crossing of Terania Creek consists of four concrete pipes and a concrete causeway. During the February 28th flooding event, the causeway was swept away in the torrential flow.
Funding has been approved by TfNSW and Resilience NSW for engineering and survey works to be undertaken to design a new crossing to current standards. The temporary crossing currently in place is constructed of nylon rock bags with infill rock and gravel running surface. The temporary crossing will be maintained for the next 12 months until the permanent structure is complete.
The residents have shown extraordinary resilience and fortitude during this time and their patience is appreciated.
Share 21 June 2022 on Facebook
Share 21 June 2022 on Linkedin
Email 21 June 2022 link
Wallace Road - Geotechnical drilling will be continuing this week.
Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.
Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin. Please see attached photo.
Works planned for Ross Road and Black Road have now been completed.
We thank the community for their ongoing patience.
Share 9 June 2022 on Facebook
Share 9 June 2022 on Linkedin
Email 9 June 2022 link
Terania Creek Road -
Geotechnical works are now completed on Terania Creek Road. Instruments have been installed to monitor the slip plane. With this information, design works to build back better will commence in a month.
Wallace Road -
Road remains open under traffic control as geotechnical drilling rig is mobilised. There will likely be traffic delays, we appreciate the ongoing patience.
Black Road -
Temporary crossing is now in place.
Ross Road -
Culvert has been cleared.
The Channon Road-
Geotechnical investigations are now complete. Reconstruction will be dependant on design of proposed embankment.
The Channon Road (Robertson Bridge) -
Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.
Pinchin Road (embankment) -
Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.
Tuntable Creek Road -
Local access to Nimbin is being investigated. Works north of Rose Road are underway to establish the feasibility of a side-track to facilitate this access. Geotechnical investigations are complete for all reported slips. Instrument monitoring continues to determine the remediation of the site.
Keerrong Road -
Bridge piling is underway. More information for this project can be found at: https://yoursay.lismore.nsw.gov.au/keerrong-road-works
As always, we thank the community for their ongoing patience. If you have any questions we ask to please utilise the Q&A function of this page to ensure we can share with the community.
Share 31 May 2022 on Facebook
Share 31 May 2022 on Linkedin
Email 31 May 2022 link
Geotechnical works are progressing on Terania Creek Road. Unforeseen geological conditions means drilling to a greater depth than planned, as such will be working on this site until early next week. A full closure is no longer in place, the road is open for light vehicle access only to ensure safety for motorists.
Works on Wallace Road (due to delays on Terania Creek Road) will commence early next week. There will be light vehicle access past works on Wallace Road, however closed to heavy vehicles to ensure safety for motorists.
A temporary crossing will be in place for Black Rd by the end of next week.
The culvert on Ross Road will be cleaned out after completion of Black Road works.
We thank you for your ongoing patience as we work through unforeseen delays. Shall you have any further concerns, please consider posting in the Q&A so we may answer and share updates with the community.
Share 27th May 2022 on Facebook
Share 27th May 2022 on Linkedin
Email 27th May 2022 link
Geotechnical Engineers will return on Monday 30th May to continue drilling on Terania Creek Road. To date, weather and unforeseen ground conditions has caused delays to the program. Once Terania Creek Road is complete we will move to Wallace Road. 24 hour notice will be provided for any full road closure.
We apologise for the inconvenience, and appreciate your ongoing patience.
Share 24th May 2022 on Facebook
Share 24th May 2022 on Linkedin
Email 24th May 2022 link
Planned works have now been pushed back to start next week 30th May.
Ongoing wet weather continues to delay geotechnical investigations, and the ability to repair road surface.
We apologise for the inconvenience, and thank this community for their ongoing patience.
Share 23rd of May 2022 on Facebook
Share 23rd of May 2022 on Linkedin
Email 23rd of May 2022 link
Due to ongoing wet weather, drilling works on Terania Creek Road have been delayed until 25th May at the earliest.
Council is committed to ensuring safety for road users. Temporary works are still in place, and road users are encouraged to drive cautiously.
We apologise for the inconvenience and thank the community for their ongoing patience.