Road Restoration Works - The Channon
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
***Unfortunately due to ongoing wet weather, the below schedule is being pushed back. Please see Community Updates tab for further details***
Due to significant flood damage, Lismore City Council will be continuing works to repair roads. The following are proposed to take place throughout May and June 2022.
Location | Reason | Traffic Plan | Duration | Dates |
Terania Creek Road Landslip north of Lawler Road | Geotechnical investigations using drilling rig, to understand subsurface conditions. | Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated. | 5 days | 25th May to 30th May |
Wallace Road Landslip 1.3km from Tuntable Creek Road | Geotechnical investigations using drilling rig to understand subsurface conditions | Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated. | 3 days | 30th May to 3rd June |
Black Road Causeway washed out | Core drilling rock to determine strength for future rock anchors | Road currently closed. | 1 day | Depending on productivity of the full road closures |
Terania Creek Road Landslip between Izzard and Town Road | Geotechnical investigations using drilling rig to understand subsurface conditions | One lane traffic control during daylight hours. | 3 days | Depending on productivity of the full road closures |
The Channon Road Landslip behind guardrail | Geotechnical investigations using drilling rig to understand subsurface conditions | One lane traffic control during daylight hours. | 2 days | Depending on productivity of the full road closures |
*All closures will allow for pedestrian access.
A VMS board is placed at Town Road, updating motorists and allowing turnaround time for those travelling along the roads on these specified dates.
***Unfortunately due to ongoing wet weather, the below schedule is being pushed back. Please see Community Updates tab for further details***
Due to significant flood damage, Lismore City Council will be continuing works to repair roads. The following are proposed to take place throughout May and June 2022.
Location | Reason | Traffic Plan | Duration | Dates |
Terania Creek Road Landslip north of Lawler Road | Geotechnical investigations using drilling rig, to understand subsurface conditions. | Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated. | 5 days | 25th May to 30th May |
Wallace Road Landslip 1.3km from Tuntable Creek Road | Geotechnical investigations using drilling rig to understand subsurface conditions | Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated. | 3 days | 30th May to 3rd June |
Black Road Causeway washed out | Core drilling rock to determine strength for future rock anchors | Road currently closed. | 1 day | Depending on productivity of the full road closures |
Terania Creek Road Landslip between Izzard and Town Road | Geotechnical investigations using drilling rig to understand subsurface conditions | One lane traffic control during daylight hours. | 3 days | Depending on productivity of the full road closures |
The Channon Road Landslip behind guardrail | Geotechnical investigations using drilling rig to understand subsurface conditions | One lane traffic control during daylight hours. | 2 days | Depending on productivity of the full road closures |
*All closures will allow for pedestrian access.
A VMS board is placed at Town Road, updating motorists and allowing turnaround time for those travelling along the roads on these specified dates.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
July 6 2022
Share July 6 2022 on Facebook Share July 6 2022 on Twitter Share July 6 2022 on Linkedin Email July 6 2022 linkDunoon Road
Dunoon Road works at Boomerang Creek were completed on June 28th. Additional pothole repair works for Dunoon Road will be completed over the coming weeks.
The Channon Road
Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.
The Channon Road (Robertson Bridge)
Remediation works of the abutments is planned for week starting July 4th. Traffic control will be present, and motorists are advised to drive carefully.
Pinchin Road Embankment failure
Embankment reconstruction works are substantially complete. Pavement repair to the road surface will commence shortly.
Wallace Road
Geotechnical drilling has been completed. Inclinometers have been installed to monitor ground movement over the next month before design to build back better commences.
Keerrong Road
Bridge construction works are now underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August
Tuntable Creek Road
Investigation works north of rose road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.
Duncan Road- Corndale Road
Works have started to heavy patch and stabilise damaged sections.
Nimbin Road (slip north of Stoney Chute)
80% design drawings received and under review. Procurement of contractor proposed for this month.
Stoney Chute Road
Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.
Cawongla Road
Geotechnical drilling is underway.
Dunoon Road
Dunoon Road works at Boomerang Creek were completed on June 28th. Additional pothole repair works for Dunoon Road will be completed over the coming weeks.
The Channon Road
Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.
The Channon Road (Robertson Bridge)
Remediation works of the abutments is planned for week starting July 4th. Traffic control will be present, and motorists are advised to drive carefully.
Pinchin Road Embankment failure
Embankment reconstruction works are substantially complete. Pavement repair to the road surface will commence shortly.
Wallace Road
Geotechnical drilling has been completed. Inclinometers have been installed to monitor ground movement over the next month before design to build back better commences.
Keerrong Road
Bridge construction works are now underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August
Tuntable Creek Road
Investigation works north of rose road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.
Duncan Road- Corndale Road
Works have started to heavy patch and stabilise damaged sections.
Nimbin Road (slip north of Stoney Chute)
80% design drawings received and under review. Procurement of contractor proposed for this month.
Stoney Chute Road
Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.
Cawongla Road
Geotechnical drilling is underway.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
Black Road reopen
Share Black Road reopen on Facebook Share Black Road reopen on Twitter Share Black Road reopen on Linkedin Email Black Road reopen linkBlack Road is a short gravel road off Terania Creek, north of The Channon. The original creek crossing of Terania Creek consists of four concrete pipes and a concrete causeway. During the February 28th flooding event, the causeway was swept away in the torrential flow.
Funding has been approved by TfNSW and Resilience NSW for engineering and survey works to be undertaken to design a new crossing to current standards. The temporary crossing currently in place is constructed of nylon rock bags with infill rock and gravel running surface. The temporary crossing will be maintained for the next 12 months until the permanent structure is complete.
The residents have shown extraordinary resilience and fortitude during this time and their patience is appreciated.
Black Road is a short gravel road off Terania Creek, north of The Channon. The original creek crossing of Terania Creek consists of four concrete pipes and a concrete causeway. During the February 28th flooding event, the causeway was swept away in the torrential flow.
Funding has been approved by TfNSW and Resilience NSW for engineering and survey works to be undertaken to design a new crossing to current standards. The temporary crossing currently in place is constructed of nylon rock bags with infill rock and gravel running surface. The temporary crossing will be maintained for the next 12 months until the permanent structure is complete.
The residents have shown extraordinary resilience and fortitude during this time and their patience is appreciated.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
21 June 2022
Share 21 June 2022 on Facebook Share 21 June 2022 on Twitter Share 21 June 2022 on Linkedin Email 21 June 2022 link
Wallace Road - Geotechnical drilling will be continuing this week.
Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.
Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin. Please see attached photo.
Works planned for Ross Road and Black Road have now been completed.
We thank the community for their ongoing patience.
Wallace Road - Geotechnical drilling will be continuing this week.
Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.
Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin. Please see attached photo.
Works planned for Ross Road and Black Road have now been completed.
We thank the community for their ongoing patience.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
9 June 2022
Share 9 June 2022 on Facebook Share 9 June 2022 on Twitter Share 9 June 2022 on Linkedin Email 9 June 2022 linkTerania Creek Road -
Geotechnical works are now completed on Terania Creek Road. Instruments have been installed to monitor the slip plane. With this information, design works to build back better will commence in a month.
Wallace Road -
Road remains open under traffic control as geotechnical drilling rig is mobilised. There will likely be traffic delays, we appreciate the ongoing patience.
Black Road -
Temporary crossing is now in place.
Ross Road -
Culvert has been cleared.
The Channon Road-
Geotechnical investigations are now complete. Reconstruction will be dependant on design of proposed embankment.
The Channon Road (Robertson Bridge) -
Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.
Pinchin Road (embankment) -
Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.
Tuntable Creek Road -
Local access to Nimbin is being investigated. Works north of Rose Road are underway to establish the feasibility of a side-track to facilitate this access. Geotechnical investigations are complete for all reported slips. Instrument monitoring continues to determine the remediation of the site.
Keerrong Road -
Bridge piling is underway. More information for this project can be found at: https://yoursay.lismore.nsw.gov.au/keerrong-road-works
As always, we thank the community for their ongoing patience. If you have any questions we ask to please utilise the Q&A function of this page to ensure we can share with the community.
Terania Creek Road -
Geotechnical works are now completed on Terania Creek Road. Instruments have been installed to monitor the slip plane. With this information, design works to build back better will commence in a month.
Wallace Road -
Road remains open under traffic control as geotechnical drilling rig is mobilised. There will likely be traffic delays, we appreciate the ongoing patience.
Black Road -
Temporary crossing is now in place.
Ross Road -
Culvert has been cleared.
The Channon Road-
Geotechnical investigations are now complete. Reconstruction will be dependant on design of proposed embankment.
The Channon Road (Robertson Bridge) -
Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.
Pinchin Road (embankment) -
Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.
Tuntable Creek Road -
Local access to Nimbin is being investigated. Works north of Rose Road are underway to establish the feasibility of a side-track to facilitate this access. Geotechnical investigations are complete for all reported slips. Instrument monitoring continues to determine the remediation of the site.
Keerrong Road -
Bridge piling is underway. More information for this project can be found at: https://yoursay.lismore.nsw.gov.au/keerrong-road-works
As always, we thank the community for their ongoing patience. If you have any questions we ask to please utilise the Q&A function of this page to ensure we can share with the community.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
31 May 2022
Share 31 May 2022 on Facebook Share 31 May 2022 on Twitter Share 31 May 2022 on Linkedin Email 31 May 2022 linkGeotechnical works are progressing on Terania Creek Road. Unforeseen geological conditions means drilling to a greater depth than planned, as such will be working on this site until early next week. A full closure is no longer in place, the road is open for light vehicle access only to ensure safety for motorists.
Works on Wallace Road (due to delays on Terania Creek Road) will commence early next week. There will be light vehicle access past works on Wallace Road, however closed to heavy vehicles to ensure safety for motorists.
A temporary crossing will be in place for Black Rd by the end of next week.
The culvert on Ross Road will be cleaned out after completion of Black Road works.
We thank you for your ongoing patience as we work through unforeseen delays. Shall you have any further concerns, please consider posting in the Q&A so we may answer and share updates with the community.
Geotechnical works are progressing on Terania Creek Road. Unforeseen geological conditions means drilling to a greater depth than planned, as such will be working on this site until early next week. A full closure is no longer in place, the road is open for light vehicle access only to ensure safety for motorists.
Works on Wallace Road (due to delays on Terania Creek Road) will commence early next week. There will be light vehicle access past works on Wallace Road, however closed to heavy vehicles to ensure safety for motorists.
A temporary crossing will be in place for Black Rd by the end of next week.
The culvert on Ross Road will be cleaned out after completion of Black Road works.
We thank you for your ongoing patience as we work through unforeseen delays. Shall you have any further concerns, please consider posting in the Q&A so we may answer and share updates with the community.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
27th May 2022
Share 27th May 2022 on Facebook Share 27th May 2022 on Twitter Share 27th May 2022 on Linkedin Email 27th May 2022 linkGeotechnical Engineers will return on Monday 30th May to continue drilling on Terania Creek Road. To date, weather and unforeseen ground conditions has caused delays to the program. Once Terania Creek Road is complete we will move to Wallace Road. 24 hour notice will be provided for any full road closure.
We apologise for the inconvenience, and appreciate your ongoing patience.
Geotechnical Engineers will return on Monday 30th May to continue drilling on Terania Creek Road. To date, weather and unforeseen ground conditions has caused delays to the program. Once Terania Creek Road is complete we will move to Wallace Road. 24 hour notice will be provided for any full road closure.
We apologise for the inconvenience, and appreciate your ongoing patience.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
24th May 2022
Share 24th May 2022 on Facebook Share 24th May 2022 on Twitter Share 24th May 2022 on Linkedin Email 24th May 2022 linkPlanned works have now been pushed back to start next week 30th May.
Ongoing wet weather continues to delay geotechnical investigations, and the ability to repair road surface.
We apologise for the inconvenience, and thank this community for their ongoing patience.
Planned works have now been pushed back to start next week 30th May.
Ongoing wet weather continues to delay geotechnical investigations, and the ability to repair road surface.
We apologise for the inconvenience, and thank this community for their ongoing patience.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.
-
23rd of May 2022
Share 23rd of May 2022 on Facebook Share 23rd of May 2022 on Twitter Share 23rd of May 2022 on Linkedin Email 23rd of May 2022 linkDue to ongoing wet weather, drilling works on Terania Creek Road have been delayed until 25th May at the earliest.
Council is committed to ensuring safety for road users. Temporary works are still in place, and road users are encouraged to drive cautiously.
We apologise for the inconvenience and thank the community for their ongoing patience.
Due to ongoing wet weather, drilling works on Terania Creek Road have been delayed until 25th May at the earliest.
Council is committed to ensuring safety for road users. Temporary works are still in place, and road users are encouraged to drive cautiously.
We apologise for the inconvenience and thank the community for their ongoing patience.
All road repairs related to the 2022 disaster are being shared on the Flood Restoration - Roads & Bridges page.