Diadem Street Roadworks

Share on Facebook Share on Twitter Share on Linkedin Email this link

This project has now been completed. Thank you for your patience while we completed these works.

A photo of Diadem Street roadworks with a road closed and detour sign.


Roadworks will be taking place in Diadem Street between Leycester Street and Laurel Avenue from early February 2020.

Eire Constructions Pty Ltd is the contractor undertaking works on behalf of Lismore City Council. This work is likely to take around six weeks and includes the following:

  • Replacing the ageing water main.
  • Reconstruction of the road, including widening 2.5m on both sides.
  • Drain maintenance and improvement of stormwater drainage.
  • Footpath reconstruction on the western side from Orion Street to Leycester Street.

There will be traffic disruptions and parking will be restricted however access arrangements will be in place for residents and businesses. There will be periods of dust, noise and water supply disruptions.

Hours of work:

  • 7am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays.
  • No work will take place on Sundays and public holidays.

People affected by the work will be kept up to date with detailed Community Updates posted to residents and updated below. A plan of the works can be viewed in the Document Library to your right.

You can ask a question using the Q&A tab below or you can contact Project Manager Aaron Hoffman on 1300 87 83 87 or email aaron.hoffman@lismore.nsw.gov.au. All Council staff are available through the above number using the National Relay Service.



Roadworks will be taking place in Diadem Street between Leycester Street and Laurel Avenue from early February 2020.

Eire Constructions Pty Ltd is the contractor undertaking works on behalf of Lismore City Council. This work is likely to take around six weeks and includes the following:

  • Replacing the ageing water main.
  • Reconstruction of the road, including widening 2.5m on both sides.
  • Drain maintenance and improvement of stormwater drainage.
  • Footpath reconstruction on the western side from Orion Street to Leycester Street.

There will be traffic disruptions and parking will be restricted however access arrangements will be in place for residents and businesses. There will be periods of dust, noise and water supply disruptions.

Hours of work:

  • 7am to 6pm Monday to Friday.
  • 8am to 1pm on Saturdays.
  • No work will take place on Sundays and public holidays.

People affected by the work will be kept up to date with detailed Community Updates posted to residents and updated below. A plan of the works can be viewed in the Document Library to your right.

You can ask a question using the Q&A tab below or you can contact Project Manager Aaron Hoffman on 1300 87 83 87 or email aaron.hoffman@lismore.nsw.gov.au. All Council staff are available through the above number using the National Relay Service.


This project has now been completed. Thank you for your patience while we completed these works.

  • Roadworks delayed by wet weather: 27 February

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Unfortunately ongoing wet weather is affecting the works taking place in Diadem Street.

    Council’s contractor Eire Constructions will delay major roadworks until such time as they can confidently forecast at least five consecutive days with no rain. At present, the forecast is not looking good.

    This timeframe is essential to facilitate the uninterrupted reconstruction of the road, which includes:

    • Ripping up the existing road.
    • ‘Stabilising’ the natural ground beneath with lime – this improves its strength and requires two days of ‘curing time’ before the subsequent gravel layer can be placed.
    • Re-spreading, cement stabilising and compacting the new road base (gravel layer).

    If we get caught be weather mid-way through this process, it will create safety issues and result in delays, rework and disruptions to property access.

    At present, the BOM is showing ongoing rain and the possibility of another east coast low in early March.

    While we wait for dry weather, the contractor will complete what work they can, including the installation of sub-soil drains, which will help if rain continues.

    We are very sorry for this ongoing wet weather delay. We hope residents can understand that it is better to wait and do the works efficiently once it is dry rather than go ahead while the weather is not good.

    Thank you for your understanding and patience – once we have the all-clear to go ahead, we will be in touch.

  • Latest News: 17 January 2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Thank you to everyone who attended our Community Coffee Cart information session on 16 January in Diadem Street – it was great to speak face-to-face with residents about the project.

    For those who couldn’t make it, some of the key talking points were as follows:

    Eire Constructions Pty Ltd has been appointed as the contractor undertaking roadworks.

    The extent of work is constrained to repairing the existing road and widening the road by about 2.5m on each side to facilitate on-street, parallel parking.

    • Eire anticipate starting in early February. Work will take approximately six weeks.
    • Sections of the road will be closed to through traffic at times, but the contractor will work with residents to ensure access to properties where possible.
    • The contractor will also arrange for bin collections as required. Residents should place their bins outside their house on their normal collection day and the contractor will move them to a central location and return. A number may be temporarily drawn on the bins with chalk to differentiate.
    • Some residents we spoke to had specific requests regarding personal driveway access. The scope of works does not extend to driveways however residents with any specific requests are welcome to get in contact with the Project Manager, Aaron Hoffman to discuss options. If considered appropriate, Council may be able to provide a quote for the additional work to be completed as part of the project.

    Key contacts throughout construction are:

    Tom Rayner, Eire Constructions –Construction Manager
    0428 771 811 or tom.rayner@eirecon.com.au

    Nathan Pendlebury, Eire Constructions – Site Engineer
    0438 784 235 or nathan.pendlebury@eirecon.com.au

    Aaron Hoffman, Lismore City Council – Project Manager
    0427 559 513 or aaron.hoffman@lismore.nsw.gov.au


    We will continue to send Community Updates as work progresses.

  • Dilapidation Surveys and Free Community Coffee Cart

    Share on Facebook Share on Twitter Share on Linkedin Email this link


    Dilapidation Surveys: 13 to 28 January

    Pre-construction dilapidation surveys are required to be undertaken. This work will be conducted by East Coast Building Consultants from Monday, 13 January to Tuesday, 28 January.

    Please contact them using the details below at your earliest convenience to arrange the best time for an inspection of your residence.

    The dilapidation surveys are an important step of the construction process and involve a visual inspection of the internal and external of your building/s by a qualified consultant with photos and notes taken and complied into a report. An identical exercise will also occur post-construction so that in the unlikely event of damage occurring during construction, comparisons can be made, and any issues can be rectified. Copies of the report will be made available to property owners on request.

    Residents are encouraged to work with the consultant to improve the level of detail in the report for their property. If internal access is not granted, the resident is not at home on the survey day, or the Consultant hasn’t been contacted, only an external survey will be conducted.


    Dilapidation Survey Contact Details:

    Brett Crawford – Building Certifier
    Mobile: 0438 646 097
    Email: brett@ecbuildingconsultants.com.au


    Free Community Coffee Cart: 16 January

    Lismore City Council and Eire Constructions are hosting a Community Coffee Cart information session on Thursday, 16 January so local residents can ask questions about the project.

    Topics we aim to cover include:

    1. Overview of the design – what are we planning to build?

    2. Construction methodology – how are we planning to build it? What impacts will this have on me?

    3. Construction timeframes – how long will I be affected?

    4. Traffic management & disruptions.

    5. Key contacts during the works.

    Come and enjoy a free morning coffee between 7.30am and 9am and bring along your questions. If you can’t make it, please don’t worry – we will continue to send detailed Community Updates to all residents throughout the project.