Share Pedestrian Crossing and Footpath Works - Corner of Magellan and Keen Street on Facebook
Share Pedestrian Crossing and Footpath Works - Corner of Magellan and Keen Street on Linkedin
Email Pedestrian Crossing and Footpath Works - Corner of Magellan and Keen Street link
Council wishes to advise that pedestrian safety works for a section of Magellan and Keen Streets, are scheduled to start Wednesday, 12 April 2023 for a period of six (6) weeks, subject to contractor availability and fine weather conditions. Should the works be delayed, you will be notified.
This work will take place under the CBD Footpath Replacement Project, which aims to further revitalise the Lismore CBD, benefiting the local economy and community.
What do the works involve?
- Installation of a wombat pedestrian crossing on Magellan Street, including signage
- Concreting works to complete the footpath on the corner of Magellan and Keen Streets (damaged due to the 2022 flooding event)
- Upgrading of existing garden beds (including garden edging)
- Installation of new garden and edging.
What are the traffic and pedestrian adjustments?
Pedestrian thoroughfare and access to shopfronts will be maintained. The existing crossing point on the corner of Magellan and Keen Streets will be closed to pedestrians and a temporary crossing will be in place whilst we work to install the wombat crossing.
We aim for these works to have minimal disruption to business owners. However, we will contact you directly should access to your property be disrupted.
What do I need to do?
Please adhere to the safety fencing in place for pedestrian thoroughfare and obey traffic control instructions.
Who should I contact with questions/ concerns?
We apologise in advance for disruptions you may experience while we carry out these works. We would appreciate your cooperation with controls and workplace protection measures to help keep everyone safe. If you have any concerns, please call our Coordinator Roads Maintenance, Rod Thistleton on 02 6625 0500 or email council@lismore.nsw.gov.au and include the title ‘Keen & Magellan Streets – Pedestrian Crossing’.
Share Project Update - Sunday 5 March 2023 on Facebook
Share Project Update - Sunday 5 March 2023 on Linkedin
Email Project Update - Sunday 5 March 2023 link
Keen Street Revitalisation works update:
Works next week:
- Replacement of barriers with temporary street furniture (progressive)
- Surface finish final clean and sealing
- Ongoing joint sealing (partial footpath closures to allow sufficient drying)
- Satay Hut Blister planting
Within the month:
- Linemarking (13th March – Nightshift)
- Signage finalisation (ongoing)
- Bollard Placement in Central Parking (intermittent closures over 2 days)
March-April:
- Bespoke Street Furniture will start to arrive. (Quatro Pots and seats 27th March)
- Planting of Seats, planter boxes (WS 27th March)
- Keen Magellan Corner rectification works (Mid-March)
- Wheel Stop installation Central Parking bays (intermittent closures over 1 days)
May-June
- Keen Magellan Corner revitalisation works.
- Electrical and communication cabling
- Finalisation of street furniture
We greatly appreciate the patience showed by all Keen St businesses during this project.
Share Project Update - Friday 24 February 2023 on Facebook
Share Project Update - Friday 24 February 2023 on Linkedin
Email Project Update - Friday 24 February 2023 link
Keen Street Revitalisation works update:
Works next week:
- Replacement of barriers with temporary street furniture (ongoing)
- Concrete removal Satay Hut (Sunday 28th – cutting)
- Surface finish final clean and sealing
- Cutting (Noise work to be conducted Sunday 26th)
- Ongoing joint sealing (partial footpath closures to allow sufficient drying)
- Removal and replacement of partial central crossing
- Cutting Sunday 26th Feb
- Remove and repour Tuesday 28th Feb.
Within next month:
- Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
- Linemarking (13th March – Nightshift)
- Signage finalisation (ongoing)
- Bollard Placement in Central Parking (intermittent closures over 2 days)
March-April:
- Bespoke Street Furniture will start to arrive. (Quatro Pots and seats 27th March)
- Planting of Seats, planter boxes (WS 27th March)
- Keen Magellan Corner rectification works (Mid-March)
- Wheel Stop installation Central Parking bays (intermittent closures over 1 days)
May-June
- Keen Magellan Corner revitalisation works.
- Electrical and communication cabling
- Finalisation of street furniture
We greatly appreciate the patience showed by all Keen St businesses during this project.
Share Project Update - Friday 17 February 2023 on Facebook
Share Project Update - Friday 17 February 2023 on Linkedin
Email Project Update - Friday 17 February 2023 link
Please see the below project update for activities.
Keen Street Revitalisation works update:
Works next week:
- Replacement of barriers with temporary street furniture
- Concrete removal (Satay hut – 1 day)
- Surface finish final clean and sealing
- Noise work to be conducted late afternoons/weekends
- Ongoing joint sealing (partial footpath closures to allow sufficient drying)
Within the month:
- Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
- Linemarking (tentative 2-MAR
- Signage finalisation (ongoing)
- Bollard Placement in Central Parking (intermittent closures over 2 days)
March-April:
- Bespoke Street Furniture will start to arrive. (Quatro Pots and seats)
- Planting of Seats, planter boxes
- Keen Magellan Corner rectification works.
- Wheel Stop installation Central Parking bays (intermittent closures over 1 days)
May-June
- Keen Magellan Corner revitalisation works.
- Electrical and communication cabling
- Finalisation of street furniture
We greatly appreciate the patience showed by all keen St businesses during this project.
Share Project Update - Monday 13 February 2023 on Facebook
Share Project Update - Monday 13 February 2023 on Linkedin
Email Project Update - Monday 13 February 2023 link
Please see the below project update for activities.
Keen Street Revitilisation works update:
We have only minor works planned for the next week and will conduct these outside of business hours to minimise any disturbance where possible.
Below are indicative timelines for remaining activities.
Works next week:
- There will be minor concreting works in Larkin Lane to take place over the weekend to enable future Asphalt paving.
- These works have been rescheduled to Thursday this week to take advantage of contractor availability. (1/2 day closure, with Traffic Control – if any deliveries are scheduled please let us know we can assist with delivery planning)
- Replacement of barriers with temporary street furniture
- Landscape Rock placement
- These works have been rescheduled to Thursday this week to take advantage of contractor availability. (1/4 day intermittent road delays during placement on Keen Street)
- Surface finish final clean and seal
- Noise work to be conducted late afternoons/weekends
- Ongoing joint sealing (partial footpath closures)
Within the month:
- Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Milling Sunday 26th February, Placement Monday 27thFebruary (Road Closed during placement – traffic Control on Keen/Woodlark Roundabout)
- Linemarking (TBC)
- Signage finalisation (ongoing)
March-April:
- Bespoke Street Furniture will start to arrive.
- Planting of Seats, planter boxes
- Keen Magellan Corner rectification works.
May-June
- Electrical and communication cabling
- Finalisation of street furniture and planting
We greatly appreciate the patience showed by all keen St businesses during this project.
Share Project Update - Tuesday 7 February 2023 on Facebook
Share Project Update - Tuesday 7 February 2023 on Linkedin
Email Project Update - Tuesday 7 February 2023 link
The revitalisation works for Keen Street are emerging from the holiday period hiatus and we are fast locking in the remaining finishes to the project.
We have only minor works planned for the next week and will conduct these outside of business hours to minimise any disturbance where possible.
Below are indicative timelines for remaining activities.
Works next week:
- There will be minor concreting works in Larkin Lane to take place over the weekend to enable future Asphalt paving.
- Garden bed mulching and planting preparation
- Replacement of barriers with temporary street furniture
Next Fortnight:
- Placement of landscaping materials and planting in Blister Areas
- Surface finish final clean and seal
Within the month:
- Asphalt works in Larkin Lane and Keen/Woodlark Street Roundabout (Date to be confirmed)
- Linemarking (the following asphalt)
- Signage finalisation
March-April:
- Bespoke Street Furniture will start to arrive.
- Planting of Seats, planter boxes
- Keen Magellan Corner rectification works.
May-June
- Electrical and communication cabling
- Finalisation of street furniture and planting
We greatly appreciate the patience showed by all Keen Street businesses during this project.
Share Project Update - Saturday 26th November on Facebook
Share Project Update - Saturday 26th November on Linkedin
Email Project Update - Saturday 26th November link
Despite some slight issues this week with concrete supply the project team have progressed the footpath pours to the final traffic blister at the Northern end of the street. (Woodlark end)
These pours will allow the asphalt subcontractor to mobilise to site from Monday to Wednesday next week to pave the new parking and driving lanes.
These final works are weather sensitive however we are still looking confident for vehicle access to shops at the end of the month.
This week the project team also installed the new underground power and communications conduit from the Gallery via underbore drilling.
Priorities for the project team over the next week are as follows:
- Kerb pours at the Woodlark end Roundabout crossing
- Asphalt profiling (milling) and paving of the parking and traffic lanes.
- Existing Pit repairs under Woodlark Street
- Footpath pours at the Woodlark end Roundabout crossing
Share Project Update - Friday 18th November 2022 on Facebook
Share Project Update - Friday 18th November 2022 on Linkedin
Email Project Update - Friday 18th November 2022 link
This week the project team focused on finishing all stormwater and drainage works as well as the new road pavement layers at Larkin Lane.
We also progressed with lean mix (1st layer of footpath) and exposed aggregate finish (top layer of footpath) for the bottom section of the footpath.
With a big week next week focusing on footpath pours, the project team is looking forward to finishing the bulk of construction and reopening the road at the end of the month.
Priorities for the project team over the next week are as follows:
- Continuing lean mix (subbase) pours early in the week
- Continuation of lower section of the footpath.
- Continuation of Gollan Traffic Blister pits and drainage.
Share Project Update - Friday 11 November 2022 on Facebook
Share Project Update - Friday 11 November 2022 on Linkedin
Email Project Update - Friday 11 November 2022 link
This week the project team focused on kerb, channel drain and the civil works in preparation for the new road and footpath pavement.
The progression of this work allows large volume footpath pours next week.
Priorities for the project team over the next week are as follows:
- Continuing lean mix (subbase) pours early in the week
- Continuation of lower section of the footpath.
- Gollan Traffic Blister pits and drainage.
Share Project Update Friday, 4th November 2022 on Facebook
Share Project Update Friday, 4th November 2022 on Linkedin
Email Project Update Friday, 4th November 2022 link
This week the project team focused on progressing the channel drain and underground drainage and electrical networks.
Although it doesn’t appear as though the project advances much during these types of activities, it does allow us to progress into concrete and finishing works ensuring Keen Street is opened in the most timely manner possible.
A small number of footpath pours were also completed this week at the centre traffic blister.
Priorities for the project team over the next week are as follows:
- Lean mix (trench pours to protect the stormwater pipes)
- Larkin Lane Lean Mix and pavement works.
- Pour Channel drain encasement and kerb
- Continuation of lower section of the footpath.
There will be no further shop closures in relation to the Keen Street construction works. Once again we would like to thank the businesses for their understanding around these closures in order to accelerate the works.
Currently the project team are available onsite Mondays 3pm and Wednesdays 11am for discussions around construction staging and business interactions.