Flood Restoration - Roads & Bridges

Share Flood Restoration - Roads & Bridges on Facebook Share Flood Restoration - Roads & Bridges on Twitter Share Flood Restoration - Roads & Bridges on Linkedin Email Flood Restoration - Roads & Bridges link

You will find all the latest repair works for Flood Recovery - Roads and Bridges. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list

You will find all the latest repair works for Flood Recovery - Roads and Bridges. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list
  • Repentance creek Road - Pavement & Drainage Works (Jul 2024)

    Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Facebook Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Twitter Share Repentance creek Road - Pavement & Drainage Works (Jul 2024) on Linkedin Email Repentance creek Road - Pavement & Drainage Works (Jul 2024) link

    Council wishes to advise of upcoming works on Repentance Creek Road. The works will occur for approximately 8 weeks, from 19 August to 14 October 2024, subject to weather conditions.

    The road will remain open with works completed under stop/go traffic control to have minimal impact on residents, delays are expected. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.

    We apologise in advance for any disruptions you may experience while we carry out this essential work.

    What are the works?
    Following the February 2022 natural disaster, Repentance Creek Road suffered extensive damage. Funding has been secured for minor pavement rehabilitation and open drainage works identified on the map below.

    Further Information
    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Repentance Creek Road – July 2024 Update.’

  • Record-Setting Restoration of Rural Gravel Roads

    Share Record-Setting Restoration of Rural Gravel Roads on Facebook Share Record-Setting Restoration of Rural Gravel Roads on Twitter Share Record-Setting Restoration of Rural Gravel Roads on Linkedin Email Record-Setting Restoration of Rural Gravel Roads link

    Lismore City Council has commenced an historic effort to restore over 120km of unsealed gravel roads damaged by natural disasters. Over the next three months, Council will deploy six dedicated local crews to grade and repair the most severely affected areas.

    This extensive project, one of the largest of its kind ever undertaken in Lismore’s rural areas, represents a multi-million-dollar investment into improving Lismore’s key transport corridors for safer and faster commute times.

    Lismore City Council’s Chief Operating Officer, Brendan Logan, said rural roads are lifelines for many in our community, providing essential access for locals, visitors, emergency services and local businesses.

    “This record-setting grading project demonstrates our commitment to restoring these vital routes to their optimal condition as quickly as possible,” he said.

    “This blitz on over 120km of unsealed roads is a welcome investment for our teams who are responsible annually for maintaining 1,215km of sealed and unsealed roads across the local government area.”

    The undertaking not only addresses the critical need for road restoration post flood, but also injects significant financial benefit into Lismore’s local economy with local contractors intentionally engaged to deliver the works.

    "This initiative is more than just road repairs, it's an incredible ‘shop local’ initiative. By engaging local contractors, we're ensuring that the investment benefits our community directly, creating jobs and keeping this money in our community,” he said.

    The project is expected to take approximately three months to complete, weather permitting, with the most severely damaged roads prioritised to be restored first.

    The assessment process is continuing with the possibility that additional roads may be included in the scope of the recovery works.

    To access the complete list of roads undergoing restoration and to stay updated on the progress of recovery efforts for roads and bridges, visit the Council’s dedicated Flood Recovery – Roads and Bridges Your Say page at yoursay.lismore.nsw.gov.au.

    The funding for this project is granted by Transport for NSW (TfNSW) under the Disaster Recovery Funding Arrangements (DRFA) guidelines to reconstruct eligible assets to pre-disaster function.

  • Tuntable Creek Road - Reopened (3 July 2024)

    Share Tuntable Creek Road - Reopened (3 July 2024) on Facebook Share Tuntable Creek Road - Reopened (3 July 2024) on Twitter Share Tuntable Creek Road - Reopened (3 July 2024) on Linkedin Email Tuntable Creek Road - Reopened (3 July 2024) link

    Tuntable Creek Road – Road Open (3 July 2024)

    Tuntable Creek Road has reopened at 1:30pm today, 3 July, after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.

    As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.

    In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.

    Please contact floodrecoveryroadsbridges@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.

    We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.

    To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form.

  • Tuntable Creek Road - Road Closure (2 July 2024)

    Share Tuntable Creek Road - Road Closure (2 July 2024) on Facebook Share Tuntable Creek Road - Road Closure (2 July 2024) on Twitter Share Tuntable Creek Road - Road Closure (2 July 2024) on Linkedin Email Tuntable Creek Road - Road Closure (2 July 2024) link

    Tuntable Creek Road - Road Closure (2 July 2024)

    Tuntable Creek Road between Rose Road and Beardow Road will be closed at 10 am today until further notice due to significant rainfall.

    We apologise for the short notice and thank the community for their understanding.

    Live Traffic Information
    https://www.livetraffic.com/incident-details/174116

  • Flood Restoration - Roads & Bridges Update (June 2024)

    Share Flood Restoration - Roads & Bridges Update (June 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (June 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (June 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (June 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.

    COMPLETED WORKS
    Crofton Road
    Excitingly, road pavement restoration works on Crofton Road were completed on 6 June. The works began in November 2023 to remediate significant damaged caused during the February 2022 natural disaster. Construction involved resealing 3 kilometres of road, installing guideposts, and replacing two culverts. During these works, the road remained open with stop-go traffic conditions, and we would like to thank the community for your patience during this time.
    Dorroughby Road
    After listening to the concerns of residents, work crews organised for contractors to install a new guardrail on Dorroughby Road to improve road safety. Thank you to residents for your positive feedback following the installation.

    CURRENT WORKS
    Blue Knob Road
    Work is underway on the first of four landslip sites along Blue Knob Road. Contractor CMC is currently focused on the site closest to Nimbin, where they are constructing two soil nail walls. Once this stage is underway, they will proceed to establish the second site for excavation. The restoration of all four landslips in this project is anticipated to span 10 months, subject to weather conditions.

    Eureka Road, Graham Road & Haywood Lane
    The side tracks and earthworks are completed at all three sites. On Eureka Road piling is now completed and installation of a new Inquik bridge is planned for early August. Piling commenced on Haywood Lane 26 June and is also scheduled for Inquik bridge installation early August. Following these works, piling will begin mid-July on Graham Road due to essential energy power outage required to commence these works. Throughout construction, road users will continue to utilise the side tracks to minimise traffic disruption.


    Gravel Roads – Multiple Sites
    Efforts persist in grading over 120 kilometres of 53 unsealed gravel roads, which suffered substantial damage due to declared natural disasters in December 2023 and April 2024. The most severely affected roads receive highest priority to expedite critical route restoration. This ambitious project, one of the largest of its kind, involves Council deploying six distinct work crews, strategically clustered geographically to optimise efficiency and resource allocation. Recently, HXR conducted grading on Gungas Road and expressed gratitude to the supportive residents they have encountered to date.


    Leycester Road
    Ongoing efforts are focused on repaving the entire length of Leycester Road, covering approximately 3.6 kilometres from Kyogle Road to Bice Road. Construction entails a granular overlay of the existing road surface, resealing, and upgrades to stormwater drainage. Anticipated to span approximately six months, from July to late December 2024 subject to weather conditions. the construction will impact traffic. During this period, road users will be impacted and can expect delays. During the works, residents will be impacted while construction is carried out under traffic control stop/go arrangement and a reduced speed limit. At times road users may experience long delays necessary to facilitate the construction of the new pavement.

    Newton Drive
    Construction has commenced on a second minor upslope landslip further up Newton Drive. Crews have taken advantage of favourable weather conditions during the past month proceeding to the final cleanup and rehabilitation phase. The remaining work involves sealing the road at the landslip site and the replacement of a single pipe culvert. We extend our gratitude to the community for their patience during the minor disruptions to traffic flow.

    Rogerson Road
    Benefiting from favourable weather conditions, the culvert works on Rogerson Road have advanced. These efforts entail replacing outdated steel drains with new cement pipes. Over the course of the month, the pipes were lifted and positioned in place, and the blinding was poured for the headwalls.


    Stony Chute Road
    Earthworks are now complete and site rehabilitation is underway. Drainage structures are on track to be completed by the end of the month. On drainage completion, final works include road resealing which will involve stop/go traffic control.

    Three Chain Road Quarry
    Located on 12.9 hectares, the formerly abandoned Three Chain Road Quarry has excitingly reopened. The site now serves as a revenue stream to support the creation of a rehabilitated green space and koala habitat. Managed by the Flood Restoration Roads and Bridges team, the quarry is excepting Excavated Natural Material (ENM). Any material disposed must undergo rigorous testing with documented proof of addressing strict environmental standards.


    Terania Creek Road
    Thrillingly, construction works on Bridge 3 are now complete. Crews have moved onto Bridge 2 where a side track is in place and works are underway for new approach slabs and restraint bracket installation. After, crews will relocate to Bridge 1 to construct a side-track early to mid-July and commence approach works.


    Upper Tuntable Falls Road
    Landslip remediation works are nearing completion on Upper Tuntable Falls Road including minor grading and drainage works. Images below illustrate the progress during the past few weeks for remediation at the site.
    FUTURE WORKS

    Urban Drainage
    Approvals have been received for the urban drainage works. The project will soon be tendered to local contractors for pricing, with an anticipated start date in four weeks.

    Gwynne Road
    The pavement repair designs for Gwynne Road, covering the initial 1.2 kilometres from the Jiggi Road intersection, have been finalised. The project will soon be tendered to local contractors for pricing, with an anticipated start date within the next 4 to 6 weeks.

  • Leycester Road - Traffic Alert (June 2024)

    Share Leycester Road - Traffic Alert (June 2024) on Facebook Share Leycester Road - Traffic Alert (June 2024) on Twitter Share Leycester Road - Traffic Alert (June 2024) on Linkedin Email Leycester Road - Traffic Alert (June 2024) link

    Council wishes to advise of upcoming works on Leycester Road. The works will occur for approximately six months,

    from 1 July to 24 December 2024, subject to weather conditions.

    What are the works?

    Following the February 2022 natural disaster, Leycester Road suffered extensive damage. Funding has now been

    secured for repaving the full length of Leycester Road, approximately 3.6 kilometres, from Kyogle Road to Bice Road,

    identified on the below map. Works will involve granular overlay of the existing road surface, resealing and stormwater

    drainage upgrades.

    During works traffic will be impacted as the works will be carried out under Traffic Control stop/go arrangement and a

    reduced speed limit. At times traffic users may experience long delays to allow construction of the new pavement.

    Motorists will be notified of the upcoming roadworks with VMS boards and updated through www.livetraffic.com

    closer to construction commencement. Emergency services vehicles will be accommodated if required. Please adhere

    to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on


    Further Information

    Updates for these works will be posted on our Your Say dedicated Flood Recovery – Roads and Bridges page:

    https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges.

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive

    updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au

    mailto:council@lismore.nsw.gov.au and include the title ‘Leycester Road – June 2024 Update.’

    We apologise in advance for any disruptions you may experience while we carry out this essential work

  • Nimbin's Road to Recovery (June 2024)

    Share Nimbin's Road to Recovery (June 2024) on Facebook Share Nimbin's Road to Recovery (June 2024) on Twitter Share Nimbin's Road to Recovery (June 2024) on Linkedin Email Nimbin's Road to Recovery (June 2024) link

    After more than 12 months of construction the second landslip site along Nimbin Road was completed and open to traffic in both directions in late May 2024.

    NIMBIN ROAD JUNE 2024

    The February 2022 severe weather event significantly affected this essential route, isolating the village and causing substantial damage.

    NIMBIN ROAD POST 2022 FLOODS

    Work to complete repairs on the first stretch of road, about 1km from Nimbin, was completed in December last year and now work has wrapped up on the second slip site, about 4km from the village.


    The engineering and geotechnical requirements of this site required a specialist solution, so Lismore City Council engaged Civil Mining and Construction (CMC) to carry out the work.


    Although there have been difficult ground conditions and delays due to weather, contractor CMC has persevered to get the job done.

    The project includes 318 micro piles and 700 concrete blocks to construct a 160m long retaining structure stabilising this section of Nimbin Road.


    NIMBIN ROAD RECONSTRUCTION WORKS

    These extensive works were carried out under the Disaster Recovery Funding Arrangements (DRFA), jointly funded by the Australian and NSW governments.


    Lismore City Council would like to thank the community for its patience during construction and also CMC for their collaborative approach to the works, to ensure a quality outcome for the community.

    NIMBIN ROAD WORKS COMPLETE

    Nimbin and neighbouring communities can expect road improvements through the grading of multiple unsealed roads with works scheduled aiming to restore safe and accessible transportation routes for residents and visitors alike.


  • Flood Restoration - Roads & Bridges Update (May 2024)

    Share Flood Restoration - Roads & Bridges Update (May 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (May 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (May 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (May 2024) link

    ROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE

    Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.

    Environmental Rescue at Rogerson Road
    What happens when a handful of bats put a major flood restoration project on hold? When it came time to replace three large steel storm water drainage pipes with reinforced concrete pipes ones on Rogerson Road, McKees Hill, project coordinators discovered at least half a dozen micro bats had made a hole in one pipe, their home.

    Myotis Macropus: One of Australia’s most fascinating species because they’re the only bats in Australia to capture fish for food. They have large feet which they use to trawl for food near the water’s surface. Work crews had to play a waiting game until two juvenile bats were old enough to fly. But then the challenge was - how to catch the youngsters and offer them an alternative roosting venue. Eventually patience and thermal imaging cameras confirmed the two young bats took to the skies for the first time, just after sunset on 1st May.

    That night the hole was sealed, and a timber bat box installed as an alternative roost. Four bats settled into their new home but the remaining two had to be caught and housed in the box. Once the culvert work is complete it’s hoped all the bats, and their box will be relocated into the new concrete pipes.

    COMPLETED WORKS
    Crofton Road
    Road pavement restoration works on Crofton Road are on track to be completed by the end of May. Until then the road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.


    Gungas Road
    Works commenced at the end of April on Gungas Road to desilt the creek crossing at Black Sheep. This involved the removal of debris to allow the creek to flow across the full width and reduce the chance of overtopping the crossing in the future.


    Nimbin Road
    Wet weather continued to cause delays to the completion of works on Nimbin Road at the site near Shipway Road. By mid-May the road was open to two-way traffic with the final clean up completed by 24 May 2024. During the past month, works were completed for the construction drainage along the retaining wall and placement of road base layers along the full width of the road. The road has now been sealed with asphalt and guardrails installed.

    Oakey Creek Road
    In May, temporary works were completed at a landslip site along Oakey Creek Road that was identified as a safety hazard.


    CURRENT WORKS
    Multiple Road Works
    The works involve grading over 120km on 53 unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events in December 2023 and April 2024. Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work. For further information visit https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/upcoming-works-grading-for-multiple-unsealed-gravel-roads

    Blue Knob Road
    Works began in late May to rectify the first of two landslip sites on Blue Knob Road. These works will occur for approximately 12 months which will include an additional two sites along Blue Knob Road. The road will remain open under stop go traffic control to have minimal impact on residents.

    Eureka Road, Graham Road & Haywood Lane
    Works have commenced to replace culverts with bridges and all side tracks are in place with existing culverts removed. Future piling work is scheduled to commence in mid-June.

    Newton Drive
    Works on several minor upslope landslips and a single pipe culvert were heavily impacted this month due to weather conditions. Crews are hoping for favourable weather in June to progress the pending works which will to be completed under traffic control and will have minimal impact on the residents in this area.

    Rogerson Road
    Through successful collaboration with environmental professionals the juvenile micro bats were temporary relocated during April. This will allow works to commence replacing the steel drainage pipes with cement ones. Thank you to the community for your understanding and patience while the works continue.

    Stony Chute Road
    Following the February 2022 natural disaster, Stony Chute Road suffered extensive damage. With funding secured restoration works are now underway. The works will continue for approximately three to four weeks from 15May 2024, subject to weather conditions.


    Terania Creek Road – Bridge Updates
    Concrete approaches, scour protection, and guard rail installation are complete for Bridge 3. Final work is due to be complete late May. For Bridges 1 and 2 side track installation is nearing completion with work to recommence in June.

    Upper Tuntable Falls Road
    Landslip remediation works will be complete at the Upper Tuntable Falls slip site this week. Some minor grading and drainage works will continue into June on Upper Tuntable Falls Road, with completion expected mid June.


    FUTURE WORKS
    Gwynne Road
    The design for 1.2 kilometres of new pavement is nearing completion and once finalised the work will be put out to tender with works predicted to begin in approximately 6 weeks.

  • Multiple Unsealed Gravel Roads - Grading Works (May 2024)

    Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Facebook Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Twitter Share Multiple Unsealed Gravel Roads - Grading Works (May 2024) on Linkedin Email Multiple Unsealed Gravel Roads - Grading Works (May 2024) link

    Council wishes to advise of upcoming works on the listed roads below. The works involve grading over 120km of unsealed gravel roads which have been significantly damaged as a result of declared natural disaster events AGRN1101 (December 2023) and AGRN1119 (April 2024).

    What are the works?

    Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first. Council is deploying six separate works crews and efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.

    The works will begin to commence this week, though will not all begin simultaneously due to contractor availability. These works will take approximately three months to complete, weather permitting.

    We understand the importance of these roads to our daily commutes, emergency services, and local economy, and we are committed to restoring them to their optimal condition quickly. Motorists will be notified of road changes via roadside signage. We apologise in advance for any disruptions you may experience while we carry out this essential work.

    Crew 1

    Crew 2

    Priority

    Road Name

    Priority

    Road Name

    1

    Davis Road

    1

    Gungas Road

    2

    Boggumbil Road

    2

    Shipway Road

    3

    Stead Road

    3

    Bishops Creek Road

    4

    Unnamed Lane West off Mountain Top (Georgica)

    4

    Parmenter Road

    5

    Clark Road

    5

    Keerrong Road

    6

    Unnamed Lane West off Clark

    6

    Quilty Road

    7

    Warby Road

    7

    Mulvena Road

    8

    Bertoli Road

    9

    Lodge Road

    10

    Stanger Road

    11

    Blade Road (West)

    12

    Cullen Road

    13

    Suffolk Road

    14

    Blade Road

    Crew 3

    Crew 4

    Priority

    Road Name

    Priority

    Road Name

    1

    Terania Creek Road

    1

    Upper Coopers Creek Road

    2

    Lawler Road

    2

    Minyon Falls Road

    3

    Rankin Road

    3

    Fox Road

    4

    Greengate Road

    4

    Nightcap Range Road

    5

    Unara Road

    5

    Lychee Drive

    6

    Walmsley Road

    6

    Armstrong Road

    7

    Virtue Road

    8

    Behan Access

    9

    Lavis Road

    10

    McKinnon Road

    Crew 5

    Crew 6

    Priority

    Road Name

    Priority

    Road Name

    1

    McInnes Road

    1

    Wallace Road

    2

    Monaltrie Road

    2

    Rose Road

    3

    Bice Road

    3

    Pinchin Road

    4

    Yeager Road

    4

    Izzard Road

    5

    Eastment Lane

    5

    Paterson Road

    6

    McMahon Road

    6

    Arkinstall Road

    7

    Muldoon Road

    8

    Norton Road

    9

    Lavis Road

    10

    McKinnon Road

    We are in the process of assessing various additional roads to be included in the scope of these recovery works. Our goal is to ensure comprehensive restoration and long-term resilience of our unsealed gravel road network. The funding for this engagement is granted by Transport for NSW (TfNSW) under the Disaster Recovery Funding Arrangements (DRFA) guidelines to reconstruct eligible assets to pre-disaster function.


    Works Criteria

    The works have been carefully distributed and prioritised based on the following criteria:

    • Scale of Damage: Roads with the most severe damage have been given the highest priority to ensure that critical routes are restored first.
    • Contractor Availability: We have coordinated with available contractors to expedite the commencement of these essential repairs.
    • Group Locality: Efforts have been made to cluster the works geographically to optimise efficiency and resource allocation.


    Further Information
    This notification will be posted on our Your Say dedicated Flood Recovery – Roads and Bridges page: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges.

    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Unsealed Gravel Roads – May 2024 Update.’

  • Stony Chute Road - Traffic Alert (May 2024)

    Share Stony Chute Road - Traffic Alert (May 2024) on Facebook Share Stony Chute Road - Traffic Alert (May 2024) on Twitter Share Stony Chute Road - Traffic Alert (May 2024) on Linkedin Email Stony Chute Road - Traffic Alert (May 2024) link

    Council wishes to advise of upcoming works on Stony Chute Road. The works will occur for approximately three to four weeks from 15 May 2024, subject to weather conditions.


    The road will remain open with works completed under single lane, stop/go traffic control to have minimal impact on residents. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.

    We apologise in advance for any disruptions you may experience while we carry out this essential work.


    What are the works?
    Following the February 2022 natural disaster, Stony Chute Road suffered extensive damage. Funding has now been secured for restoration works identified on the below map.


    Further Information
    Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email floodrecoveryroadsbridges@lismore.nsw.gov.au and include the title ‘Stony Chute Road – May 2024 Update.’

Page last updated: 23 Jul 2024, 04:48 PM