Flood Restoration - Roads & Bridges

Share Flood Restoration - Roads & Bridges on Facebook Share Flood Restoration - Roads & Bridges on Twitter Share Flood Restoration - Roads & Bridges on Linkedin Email Flood Restoration - Roads & Bridges link

You will find all the latest repair works for Flood Recovery - Roads and Bridges. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list

You will find all the latest repair works for Flood Recovery - Roads and Bridges. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list
  • Koonorigan Road Update

    Share Koonorigan Road Update on Facebook Share Koonorigan Road Update on Twitter Share Koonorigan Road Update on Linkedin Email Koonorigan Road Update link

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access.

    This follows geotechnical investigations taking place, where instruments were installed to monitor progressive movement and to determine the depth of the failure plane. A geotechnical engineer will be engaged to provide a final design to rectify the slip.

    Funding approval has also been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Council has received feedback from a number of local community members and motorists regarding Koonorigan Road, and are looking forward to restoring access. We appreciate your patience as this work continues.

  • Current Road Project Updates July 22 2022

    Share Current Road Project Updates July 22 2022 on Facebook Share Current Road Project Updates July 22 2022 on Twitter Share Current Road Project Updates July 22 2022 on Linkedin Email Current Road Project Updates July 22 2022 link

    Fernside Bridge

    The side-track is still on schedule to be open to traffic by 29th July, pending weather. Additional pipes for higher creek flows have been installed as an added precaution.

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 25th – 29th July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation. (Updated and postponed due to illness in the specialist contracting team)

    Koonorigan Road

    Works are commencing on making a temporary side-track over the slip at Koonorigan Road, suitable for local access. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Regional Roads - Damaged Sealed Roads

    Approval has been received for the proposed scope of work to heavy patch six sections of Nimbin Road. Heavy patching consists of cutting off high shoulders, box out soft spots, overlay gravel where required, stabilise (nominal 1.5% slag/lime), compact, trim and seal. The procurement of a specialist stabilising subcontractor is underway. Scope has also been approved for Blue Knob Road, Dunoon Road, Kyogle Road and Wyrallah Road (excluding the Wyrallah Village). Wyrallah Village will be the subject to a reconstruction as it is not suitable for heavy patching.

    Precinct 1 - Damaged Sealed Roads

    Heavy patching has been approved for Graham Road, Gundurimba Road, River Bank Road, Rous Road, Skyline Road and Tuckurimba Road.

    Wyrallah Road Landslips

    Geotechnical drilling will take place under traffic control lane closures at 257 Wyrallah Road and 896 Wyrallah Road at the end of July.

    Johnston Road (Clunes)

    Geotechnical works will take place on the week of the 1st of August. This road, currently accessible to locals, will be fully closed during the works.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week (subject to weather)

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is still underway.

    Mountain Top Road

    Geotechnical drilling is still underway.

  • Johnston Road Landslip - **Closure Updated to Week of 22nd August 2022**

    Share Johnston Road Landslip - **Closure Updated to Week of 22nd August 2022** on Facebook Share Johnston Road Landslip - **Closure Updated to Week of 22nd August 2022** on Twitter Share Johnston Road Landslip - **Closure Updated to Week of 22nd August 2022** on Linkedin Email Johnston Road Landslip - **Closure Updated to Week of 22nd August 2022** link

    Following the February 28 and March 2022 flooding events, a road embankment landslip has occurred on Johnston Road, approximately 1km from Bangalow Road.

    There is currently an interim road closure in place, allowing local access only. Geotechnical drilling and investigation will commence from Monday 22nd of August for one week (subject to weather and ground conditions) (**Originally planned and communicated for week starting 1st of August 2022. Unforeseen ground conditions and increased project scope on other projects have pushed the schedule for specialist contractors).

    For the safety of motorists, a full road closure at the works site will be in place for the duration of these works. Signage of the Johnston Road closure will be in place to notify motorists and updated through northernrivers.myroadinfo.com.au. Residents will still have access via Bangalow and Eltham Roads.

    Minor surface grade repairs and signposting for longer term traffic arrangements will also take place during this time. On completion of these works, the road will be reopened to one lane of traffic under a give-way arrangement. This arrangement will remain in place for several months until full remediation work commences.

    The geotechnical investigation will determine the detailed design and cost of the repair, which will be included in an application for funding to complete this work. Approval for funding is anticipated to be received by the end of August.

    Construction is planned to be commenced by the end of 2022, subject to approvals, contractor availability and weather.

    Further updates will be shared via this article.

    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Johnston Road’ in your correspondence.

  • Orion Street - Updated Closure 25th - 29th July

    Share Orion Street - Updated Closure 25th - 29th July on Facebook Share Orion Street - Updated Closure 25th - 29th July on Twitter Share Orion Street - Updated Closure 25th - 29th July on Linkedin Email Orion Street - Updated Closure 25th - 29th July link

    Unfortunately the Orion Street road closure is now postponed until Monday 25th – Friday 29th of July (subject to weather and ground conditions). If you could please share this through your networks.

    Geotechnical drilling and instrument installation has started, however unable to continue at this time due to illness within the contracting team. Additional specialised contractors have been sought to carry on this work, and will be arriving to recommence next Monday.

    Signage detailing the closure has been taken down today, and will be reinstalled for the closure re- starting Monday 25th. Details remain the same regarding 24 hour closure during this time, and local access available from the Dawson Street roundabout, with a detour via Conway Street recommended for heavy vehicles.

    We apologise for the inconvenience, and ask for understanding during these unforeseen circumstances. If you would like to provide feedback or have further questions – please do not hesitate to reach out.

  • Flood Recovery Heavy Patching Program

    Share Flood Recovery Heavy Patching Program on Facebook Share Flood Recovery Heavy Patching Program on Twitter Share Flood Recovery Heavy Patching Program on Linkedin Email Flood Recovery Heavy Patching Program link

    Flood Recovery Heavy Patching Program –

    Restoration of road surface, possible change in road level.

    Segments of the following have been identified for heavy patching works to repair flood damage to road surface.

    Precinct 1

    Graham Road

    Gundarimba Road

    River Bank Road

    Rous Road

    Skyline Road

    Tregeagle Road

    Tuckurimba Road

    Tucki Road

    Wybelena Road

    Precinct 2

    Bagotville Road

    Broadwater Road

    Kilgin Road

    Mathieson Lane

    Precinct 3

    Tatham Road

    Precinct 4

    Nimoola Road

    Pelican Creek Road

    Precinct 6

    Back Creek Road

    Precinct 7

    Axford Road

    Martin Road

    McGuinness Road

    Rock Valley Road

    Precinct 8

    Boggumbil Road

    Davis Road

    Jacobson Road

    Jiggi Road

    Potessu Road

    Rosehill Road

    Precinct 9

    Anderson Road

    Basil Road

    Cecil Street

    Crofton Road

    Gungas Road

    Lillian Rock Road

    Moffitt Road

    Sibley Street

    Symonds Road

    Thorburn Street

    Precinct 10

    Booerie Creek Road

    Boyle Road

    Keerrong Road

    Precinct 11

    Koonorigan Road

    Pinchin Road

    Terania Creek Road

    The Channon Road

    Tuntable Creek Road

    Precinct 12

    Dorroughby Road

    Duncan Road

    James Street (Dunoon)

    Middleton Way

    Nightcap Range Road

    Rocky Creek Dam Road

    Precinct 13

    Corndale Road

    Hunters Hill Road

    Grace Road

    James Gibson Road

    Precinct 14

    Boatharbour Road

    Eltham Road

    Humpty Back Road

    Regional Roads

    Blue Knob Road

    Coraki Road

    Dunoon Road

    Nimbin Road

    Wyrallah Road

    Bridge Street (Wyrallah)

    Kyogle Road


    These works are subject to change to due weather conditions, availability of contractors and funding. Updates will be posted on this article.


    Shall you wish to be kept up to date directly, you can register your details via the Your Say ‘Submissions’ tab HERE. Alternately, please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details. Please reference ‘Flood Recovery Heavy Patching Program’.


    How will the works affect traffic?

    Roads will be open to residential access only during the time of works. Traffic controls will be in place, which will cause minor delays and disruptions. Please note roadside signage, updates on myroadinfo and updates in the online Your Say article for communication about temporary disruptions to your property access during this period.


    What do the works involve?

    These roads need to be fixed to improve the structural integrity and driving conditions for road users. Works include cleaning drains and culverts, cutting off high road shoulders, digging out and replacing soft spots with rock. The gravel overlay is placed where required, before stabilising with the addition of slag lime. This is then compacted, trimmed, and sealed. Followed by line marking edge line.


    The road surface may receive a final wearing seal several months after the initial bitumen seal has cured.

    This pavement overlay may potentially change road levels between 0mm to +150mm and resurfacing of the existing road width due to additional layers of new road base material.


    All driveways that intersect the road will match any changes to the road profile. If there are any changes, you will be contacted should your driveway/access need modification. We will also do maintenance to roadside drainage as needed.

    What happens now?

    If you wish to make comment on the works, we ask that you do this by 4pm Monday, 15th August 2022 referring to ‘Flood Recovery Heavy Patching Program’. Feedback can be received via any of the following:

    • Via the ‘Submissions’ tab of this article HERE.
    • Email to council@lismore.nsw.gov.au
    • Call to Council (02) 6625 0500
    • In writing to Lismore City Council, PO Box 23A, Lismore 2480
  • Current Road Project Updates July 14 2022

    Share Current Road Project Updates July 14 2022 on Facebook Share Current Road Project Updates July 14 2022 on Twitter Share Current Road Project Updates July 14 2022 on Linkedin Email Current Road Project Updates July 14 2022 link

    Canaiba Road

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    Orion Street

    Road closure Monday 18th – 22nd July from Keen Street roundabout to Molesworth Street. Local Access Only from Dawson Street. Due to the slumping on Orion Street, geotechnical drilling will be undertaken to determine the depth of the slip plane and options for remediation.

    Koonorigan Road

    Investigations are underway to make a safe passage over the slip, while design is undertaken for a permanent solution. Funding approval has been received to heavy patch the seal on The Channon side of the slip. This work is currently being scheduled.

    Repentance Creek Road

    No further road closures. Due to delays in getting asphalt contractors, a sacrificial seal has been placed on the road surface for the safety of motorists. Works are expected to be fully completed by the end of July. Please drive with care.

    The Channon Road

    Geotechnical investigations have been completed for the slip behind the guardrail. Works will commence once the design of proposed embankment reconstruction is finalised. The scope of works required to heavy patch flood damaged sections of the road has now been approved, with works to commence in the coming weeks.

    The Channon Road (Robertson Bridge)

    Remediation works of the abutments is underway. Traffic control will be present, and motorists are advised to drive carefully.

    Pinchin Road Embankment failure

    Embankment reconstruction works are substantially complete. Pavement repair to commence shortly. Funding approval has been received to heavy patch four sections on Pinchin Road. Scheduling and advance planning of this work is underway.

    Keerrong Road

    Bridge construction works and heavy patching of sealed road is underway. Landslip repair, drainage reconstruction and gravel road resheeting is planned to commence in August.

    Tuntable Creek Road

    Investigation works north of Rose Road are underway to establish the feasibility of a side-track to facilitate local access to Nimbin. Geotechnical investigations are complete for all slips. Undergoing instrument monitoring to determine the remediation of the site.

    Funding approval has been received to heavy patch four sections on Tuntable Creek Road. Scheduling and advance planning of this work is underway.

    Duncan Road- Corndale Road

    Works to heavy patch and stabilise damaged sections are now complete.

    Richmond Hill Road

    Embankment reconstruction works remain underway under traffic light control. Pavement works will start next week

    Nimbin Road (slip north of Stony Chute)

    80% design drawings received and under review. Procurement of contractor proposed for this month.

    Woodlawn Road

    Opened up to one lane. Geotechnical investigations are scheduled for the end of July.

    Stony Chute Road

    Geotechnical drilling has been completed. Inclinometers have been installed and will monitor ground movement over the next month prior to design commencing.

    Cawongla Road

    Geotechnical drilling is underway.

    Mountain Top Road

    Geotechnical drilling is underway.

    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Canaiba Road Slip Works

    Share Canaiba Road Slip Works on Facebook Share Canaiba Road Slip Works on Twitter Share Canaiba Road Slip Works on Linkedin Email Canaiba Road Slip Works link

    Works will begin soon on an embankment slip at the shoulder of Canaiba Road, east of Pelican Creek.

    The slip initially occurred in 2020, and has undergone temporary repairs to ensure safe road user access. Further damage occurred in March 2021 and the previous remediation treatment was revised. Geotechnical investigations have now been completed and design for rockfill embankment have been received. Mobilisation will occur early next week, followed by ongoing works.

    Single lane traffic access will be available for motorists, under traffic light control for a minimum of 3 weeks.

    There are a number of works currently occurring on Canaiba Road to remediate damage. Please adhere to road signage and drive with care.

    We thank the community for their ongoing patience.

  • Orion Street Slumping - Road Closure 18 - 22 July 2022

    Share Orion Street Slumping - Road Closure 18 - 22 July 2022 on Facebook Share Orion Street Slumping - Road Closure 18 - 22 July 2022 on Twitter Share Orion Street Slumping - Road Closure 18 - 22 July 2022 on Linkedin Email Orion Street Slumping - Road Closure 18 - 22 July 2022 link

    Slumping of the road embankment on Orion Street has worsened since the February and March 2022 flooding events. Minor works have since been undertaken to seal the tension cracks and ensure safe passage for vehicles.

    Orion Street will now undergo works to remediate the damage. Geotechnical drilling to determine the depth of the slip plane and options for remediation will be undertaken the week starting 18th July, for minimum 1 week pending the ground conditions.

    To ensure access for necessary equipment and works in this section, a full road 24-hour road closure is required from Monday 18th July until Friday 22nd July 2022 (subject to weather and ground conditions).

    Local access only will be available for Orion Street from Dawson Street. The road will be closed from Molesworth Street to Dawson Street, with detour via Conway Street.

    Signage of the Orion Street closure will be in place to notify motorists and updated through northernrivers.myroadinfo.com.au. Motorists are recommended to use the roads over Fawcett Bridge to access the CBD and surrounds from North Lismore.


    Scheduling of the Orion Street works were planned for the school holiday period. Unfortunately due to the ground conditions following recent wet weather and subsequent availability of specialist drilling contractors, this work was unable to go ahead as planned. To ensure geotechnical drilling and installation of instrumentation to monitor the slump is completed, these works cannot wait for the next school holiday period.

    We are looking forward to providing a long term solution to the Orion Street slumping, and appreciate the patience of our community.

    Further updates will be shared via this online article: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges


    Additionally, to receive updates directly please contact Lismore City Council via email council@lismore.nsw.gov.au or call (02) 6625 0500 to register your details and feedback. Please reference ‘Orion Street Closure’ in your correspondence.

    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Keerrong Bridge Updates

    Share Keerrong Bridge Updates on Facebook Share Keerrong Bridge Updates on Twitter Share Keerrong Bridge Updates on Linkedin Email Keerrong Bridge Updates link

    Landing bridge beams have been installed yesterday at Keerrong Bridge.

    Due to the February 28 disaster and March flooding events, the collapsed culvert structure located north of the intersection with Dudgeon Road is being replaced with a new 7.2m wide by 16.1m long InQuik bridge.

    Works are expected to be finalised by the end of August 2022, pending weather and ground conditions.

    ***Update at August 4th 2022***

    Unsuitable material has been found on the Lismore approach to the bridge, which will have to be removed and replaced. Schedule of works will now be delayed, expected opening remains at the end of August 2022.

    Further details for Keerrong Road works can be found on: https://yoursay.lismore.nsw.gov.au/keerrong-road-works

  • Keerrong Road - Pavement Stabilisation Repair

    Share Keerrong Road - Pavement Stabilisation Repair on Facebook Share Keerrong Road - Pavement Stabilisation Repair on Twitter Share Keerrong Road - Pavement Stabilisation Repair on Linkedin Email Keerrong Road - Pavement Stabilisation Repair link

    Keerrong Road is also scheduled to undergo pavement repairs on some sections of severely damaged areas from Wednesday July 13th 2022. Initially the works will start with drainage remediation to allow water to drain from the pavement. Following these works there will be a pavement stabilisation crew mobilising to site to stabilise the existing pavement. As well as adding an additional 150mm of new road base material to improve the pavements strength.

    This work is a large roads maintenance activity and will take approximately 4 weeks to complete (weather permitting).

    A single lane traffic closure will allow traffic to travel through the worksite. Signage will be in place to notify road users, and updates available on northernrivers.myroadinfo

    We thank the community for their patience as we complete these works.

    For more information on Keerrong Road works, please visit https://yoursay.lismore.nsw.gov.au/keerrong-road-works

Page last updated: 01 May 2024, 04:05 PM