Flood Restoration - Roads & Bridges

Share Flood Restoration - Roads & Bridges on Facebook Share Flood Restoration - Roads & Bridges on Twitter Share Flood Restoration - Roads & Bridges on Linkedin Email Flood Restoration - Roads & Bridges link

You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list

You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.


Why was this page designed?

Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.

This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.

Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.

Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.


What process does Council have to go through when we have a 'disaster event'?

When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.

There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)


Major Flood Recovery Works Map

Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.

Click here to view the interactive map.

Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.


Further Information

  1. Report a road hazard or pothole
  2. Information on current delays, accidents and road closures in the Northern Rivers
  3. Register your details to receive flood restoration updates for specific roads via our notification list
  • Pinchin Road repair due to start

    Share Pinchin Road repair due to start on Facebook Share Pinchin Road repair due to start on Twitter Share Pinchin Road repair due to start on Linkedin Email Pinchin Road repair due to start link
    supporting image
    We are continuing to make the most of the good weather to repair the extensive damage to our road network caused by the recent natural disaster.


    One of the many projects we are currently working on is Pinchin Road where the road’s embankment was damaged and a pipe needs to be replaced adjacent to 778 Pinchin Road.


    To allow access for the necessary equipment and to conduct the work, we will need to close the road on Wednesday, 6 July 2022 from 7am to 5pm.


    Signage will be in place to assist motorists with the detour via Keerrong Road.


    Part of the detour passes damaged drainage and pavement which has yet to be restored. Motorists are asked to follow the detour signage and proceed with caution. These damaged sections are scheduled for repair as part of the next stage of works.


    Further updates are available via Council’s Your Say page at https://yoursay.lismore.nsw.gov.au/keerrong-road-works.
    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Corndale Road

    Share Corndale Road on Facebook Share Corndale Road on Twitter Share Corndale Road on Linkedin Email Corndale Road link
    supporting image

    Corndale Road is scheduled to undergo stabilisation repairs on a section of severely damaged road pavement from Tuesday, 5 July 2022. Initially drainage works will be completed, installing table drains and clearing shoulders allowing water to escape the pavement.

    Following these works, there will be a pavement stabilisation crew mobilising on site to rip up the existing damaged pavement. The road material quality will be improved, by mixing 100mm of new material with the existing road base.

    Council expects this work to be completed within 1 week from start to finish, weather permitting.

    Signage will be installed over the coming weeks to advise of 'raising road levels'.

    A single lane road closure will be provided to allow traffic to travel through the site, with the appropriate signage. Please note this work is scheduled to take place during the school holidays.

    If you have questions, please consider utilising the Q+A function of this page. This allows the same information to be shared with our community members. Feedback and questions can also be submitted to Council via email council@lismore.nsw.gov.au or calling (02) 6625 0500.

    We thank the community for their patience as we complete this work.

    loader image
    Didn't receive confirmation?
    Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
    Submitting your comment
    Cancel
  • Current Road Project Updates - June 21 2022

    Share Current Road Project Updates - June 21 2022 on Facebook Share Current Road Project Updates - June 21 2022 on Twitter Share Current Road Project Updates - June 21 2022 on Linkedin Email Current Road Project Updates - June 21 2022 link

    Wallace Road - Geotechnical drilling will be continuing this week, to remedy the landslip 1.3km from Tuntable Creek Road.

    Nimbin Road - Temporary side-track works are in place south of Shipway Road, to reduce traffic stoppages. Design is underway on a complicated site. Please drive with care.

    Tuntable Creek Road - Investigation works continue to establish the feasibility of a side track to facilitate local access to Nimbin north of Rose Road.

    Keerrong Road - The bridge piling has been completed. Bridge construction works are now underway.

    Repentance Creek Road - No further road closures are planned. The road is currently a gravel surface, while asphalt contractor scheduled works are confirmed. Speed has been reduced to 60KM due to loose gravel. Please drive with care.

    Dunoon Road – The road is open, with caution to traffic. Pavement has been placed, with the final stages being the seal to go ahead this week.

    Duncan Road - Funding has been approved to heavy patch stabilise damaged sections, and work has begun.

    The Channon Road- Geotechnical investigations are now complete. Reconstruction will be dependent on design of proposed embankment.

    The Channon Road (Robertson Bridge)- Remediation works of the abutments is planned for the coming weeks. Traffic control will be onsite, motorists are advised to drive with caution.

    Pinchin Road (embankment failure)- Works are scheduled following the completion of Robertson Bridge. Possible road closure may be required, which will be advised closer to the date.

    Works planned for Ross Road (culvert has been cleared) and Black Road (washed out causeway) have now been completed.

  • Fernside Bridge Restriction

    Share Fernside Bridge Restriction on Facebook Share Fernside Bridge Restriction on Twitter Share Fernside Bridge Restriction on Linkedin Email Fernside Bridge Restriction link

    Fernside Bridge has deteriorated significantly since Council received a Level 2 Structure Condition Report of the bridge. This detailed condition assessment was conducted by an independent company, engaged by Lismore City Council. Following the condition assessment, the following immediate recommendations were issued to Council:

    • Implement a load limit of 3.5 tonne (GVM) as a priority.
    • Undertake temporary repairs involving propping the outer foundation piles with a load path from a solid section of the cross beam to a solid section of the piles in order to provide structural support and mitigate any further cantilevering of the cross beams and running deck.

    In the interest of public safety, it was necessary for Council to take immediate action and implement the recommendations as outlined in the consultant’s report.

    As an interim measure, it is proposed to construct a temporary crossing (side-track) which is currently planned to be installed on the downstream side of the current bridge site and will be open to traffic on 29 July 2022.

    The side-track, which will be located within the road reserve, will not be load limited and will provide for heavy vehicle access across the creek, and will be in place until Fernside Bridge is either repaired or replaced, depending on NSW Government grant submission approval.

    Signage has been installed to notify motorists. Further details and updates can be found below in the 'Community Updates' tab. We encourage the Q+A function to be used, so we may share information with those who have similar questions.


    We understand that this information may provide some difficulty for your current circumstances. Please contact Council (02) 6625 0500, or email council@lismore.nsw.gov.au with your contact details and feedback – referencing Fernside Bridge. We would like to work with the community and provide direct up to date details on proposed works.

    https://yoursay.lismore.nsw.gov.au/fernside-bridge-restriction

  • Robson Road Closure

    Share Robson Road Closure on Facebook Share Robson Road Closure on Twitter Share Robson Road Closure on Linkedin Email Robson Road Closure link
    Due to excessive water under the road surface on part of Robson Road, Wyrallah, we have closed part of the road between 91 Robson Rd towards the Tregeagle Road end and 102 Robson Rd towards the Tucki Road end for July 2022.
    This is to allow our road crews to undertake remedial work to install drainage to prevent further deterioration of the road.
    Traffic control is in place and motorists are asked to detour via Wyrallah Road. Residents will be able to access their homes.
    We thank the community for its patience and understanding as we work to improve our road network.
  • Boggumbil Road Closure

    Share Boggumbil Road Closure on Facebook Share Boggumbil Road Closure on Twitter Share Boggumbil Road Closure on Linkedin Email Boggumbil Road Closure link
    With the improved weather Council is conducting emergency repair work on Boggumbil Road which has a soft spot on the road surface that poses a significant risk to motorists.


    This means we will need to close the road this Friday, 17 June and Saturday 18 June, 2022 for emergency works. Works will continue on Monday, 20 June, 2022 however the road will be open with traffic control. Access will be available for Boggumbil residents and school buses.
    Traffic control will be onsite from 7am to 6pm during the days of closure. A road detour will be in place via Rosehill Road, Nimbin Road and Jiggi Road. Please allow additional travel time.


    Further information and updates are posted in the main article: https://yoursay.lismore.nsw.gov.au/road-closure-boggumbil-road

  • Keerrong Road Works

    Share Keerrong Road Works on Facebook Share Keerrong Road Works on Twitter Share Keerrong Road Works on Linkedin Email Keerrong Road Works link

    Lismore City Council is continuing works to repair roads following significant flood damage. Urgent work is required to repair multiple sections of Keerrong Road, which includes a culvert collapse, areas of severe pavement damage and a large landslide.

    The collapsed culvert structure, located north of the intersection with Dudgeon Road will be replaced with a new concrete bridge.

    Works will be undertaken to repair the sealed pavement section approximately 1-3km from Nimbin Road, improving access for road users. These works are temporary as Council is currently seeking funding for the repair and full restoration cannot be completed with current weather conditions.

    Investigations are underway into the large landslide located near The Channon Road end to determine full restoration treatments.

    What do the works involve?

    • Re-shape the sealed pavement section to temporarily restore pavement formation
    • Installing a concrete InQuik bridge structure, 7.2m wide by 16.1m long at the culvert site
    • Geotechnical investigation and design for the large landslide near The Channon Road

    When will the works start?

    Bridge works and temporary road works are expected to be finalised by August 31, 2022.

    These works may be subject to delays due to weather events. Updates will be posted on the online article listed below. A date for the permanent restoration of the sealed pavement sections and the large landslide will be advised once funding had been confirmed.

    What are the traffic adjustments?

    Road users are advised to be aware of works being completed, and to slow down in work zones. Further traffic information will be listed on northernrivers.myroadinfo.com. Please allow additional travel time.

    Where can I find more information?

    Community Updates plus Q&A can be found at the below link.

    https://yoursay.lismore.nsw.gov.au/keerrong-road-works

  • COUNCIL’S IMMEDIATE RESPONSE TO DAMAGED ROAD NETWORK

    Share COUNCIL’S IMMEDIATE RESPONSE TO DAMAGED ROAD NETWORK on Facebook Share COUNCIL’S IMMEDIATE RESPONSE TO DAMAGED ROAD NETWORK on Twitter Share COUNCIL’S IMMEDIATE RESPONSE TO DAMAGED ROAD NETWORK on Linkedin Email COUNCIL’S IMMEDIATE RESPONSE TO DAMAGED ROAD NETWORK link
    This week we have focused on updating the community about the extensive road repair work that lays ahead following the 28 February natural disaster and March flood.
    Council estimates that the flooding disaster caused more than $350 million worth of damage to Council assets and infrastructure.


    Out of that total, the estimated damage to our roads and bridges network is $200 million.


    To put this into perspective, Council assessed that 90% of our 1200km road network had suffered extensive damage.


    There has also been much damage to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network.
    Landslips have also reduced traffic to single lanes on some key access roads.


    Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible.


    Council continues to repair more road damage with new works starting on a weekly basis, thanks to funding and support from State and Federal governments.
    Currently we are working on the following roads:


    - Wyrallah Road
    - Duncan Road
    - Keerrong Road
    - Repentance Creek Road
    - Terania Creek Road
    - Wallace Road
    - Black Road
    - The Channon Road


    You can keep up to date on the progress of works on these roads by going to our Your Say Lismore site www.yoursay.lismore.nsw.gov.au.
    For more significant damage, we need to work with geotechnical engineers and start design and investigation work to deliver restoration. Restoration work of this nature can be quite complex to deliver and is exacerbated by demand for contractors in the area.


    Council will work with state agencies and other local councils in the Northern Rivers to coordinate efforts where possible.
    Council has released a document called the Flood Response report which examines the impact of the 28 February natural disaster and March flood, and Council’s initial response to restore basic services in more detail.


    You can view that document which explains about the wider response beyond just roads by visiting Council’s website at www.lismore.nsw.gov.au under Council & Engagement tab.
  • Repentance Creek Road Closure

    Share Repentance Creek Road Closure on Facebook Share Repentance Creek Road Closure on Twitter Share Repentance Creek Road Closure on Linkedin Email Repentance Creek Road Closure link

    Lismore City Council is continuing works to repair roads following significant flood and consequent landslide damage. Urgent work is required to reconstruct an embankment and replace a pipe on Repentance Creek Road at Turkey Creek adjacent 171 Repentance Creek Road. Unfortunately, due to safety for road users, the road must be fully closed during a portion of the works period.

    What do the works involve?

    • Remove old damaged concrete pipe and replace with larger capacity pipes and headwalls.
    • Reconstruct embankment with rock fill
    • Construct drainage chute to discharge water away from embankment

    When will the works start?

    • 25/05/2022 – Stop/Go traffic control between 6:30am – 6:00pm Monday to Sunday
    • 30/05/2022 – Expect full 24-hour road closure until 13/06/2022 (please monitor electronic signage onsite, and Community Updates tab below for most up to date information)
    • 13/06/2022 – Stop/Go traffic control between 6:30am – 6:00pm Monday to Sunday
    • All closures will allow for pedestrian access through the work site

    These works may be subject to delays due to weather events. If there is a requirement to change these hours, updates will be listed below in 'Community Updates'.

    What are the traffic adjustments?

    A detour will be available through Federal for motorists to remain on the sealed road network. A VMS board will be stationed at the junction of Eureka Road and Repentance Creek Road, and at Dunoon Road to notify road users of the detour. Information will be listed on northernrivers.myroadinfo.com.

    Please allow additional travel time.

    Where can I find more information?

    Community updates and Q&A are listed in the below article.

    https://yoursay.lismore.nsw.gov.au/repentance-creek-road-closure

  • Road Restoration Works - The Channon

    Share Road Restoration Works - The Channon on Facebook Share Road Restoration Works - The Channon on Twitter Share Road Restoration Works - The Channon on Linkedin Email Road Restoration Works - The Channon link

    ***Unfortunately due to ongoing wet weather, the below schedule is being pushed back. Please see Community Updates on the main article HERE for further details***

    Due to significant flood damage, Lismore City Council will be continuing works to repair roads. The following are proposed to take place throughout May and June 2022.

    Location

    Reason

    Traffic Plan

    Duration

    Dates

    Terania Creek Road

    Landslip north of Lawler Road

    Geotechnical investigations using drilling rig, to understand subsurface conditions.

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    5 days

    25th May to 30th May

    Wallace Road

    Landslip 1.3km from Tuntable Creek Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    Full Closure- 8am to 4pm. Fire, Ambulance and Police emergency services vehicles will be accommodated.

    3 days

    30th May to 3rd June

    Black Road

    Causeway washed out

    Core drilling rock to determine strength for future rock anchors

    Road currently closed.

    1 day

    Depending on productivity of the full road closures

    Terania Creek Road

    Landslip between Izzard and Town Road

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    3 days

    Depending on productivity of the full road closures

    The Channon Road

    Landslip behind guardrail

    Geotechnical investigations using drilling rig to understand subsurface conditions

    One lane traffic control during daylight hours.

    2 days

    Depending on productivity of the full road closures

    *All closures will allow for pedestrian access.

Page last updated: 29 Oct 2024, 04:47 PM