Flood Restoration - Roads & Bridges
You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.
Why was this page designed?
Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.
This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.
Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.
Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.
What process does Council have to go through when we have a 'disaster event'?
When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.
There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)
Major Flood Recovery Works Map
Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.
Click here to view the interactive map.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Further Information
You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.
Why was this page designed?
Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.
This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.
Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.
Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.
What process does Council have to go through when we have a 'disaster event'?
When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.
There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)
Major Flood Recovery Works Map
Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.
Click here to view the interactive map.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Further Information
-
Magellan Street - Guardrail Works (Apr 2024)
Share Magellan Street - Guardrail Works (Apr 2024) on Facebook Share Magellan Street - Guardrail Works (Apr 2024) on Twitter Share Magellan Street - Guardrail Works (Apr 2024) on Linkedin Email Magellan Street - Guardrail Works (Apr 2024) linkPlease note:
The works for Magellan Street have been delayed. We will notify of commencement dates when reschedule. Thank you to the community for your patience and understanding during these works.
Council wishes to advise of on going works on Magellan Street.
Motorists will be notified of any road changes via roadside signage. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Funding was successfully secured for guardrail installation on several roads throughout the Lismore Shire. New guardrails will be installed on Magellan Street in the location identified on the map below.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Magellan Street – March 2024 Update.’ -
Tuntable Creek Road - Reopened (5 April 2024)
Share Tuntable Creek Road - Reopened (5 April 2024) on Facebook Share Tuntable Creek Road - Reopened (5 April 2024) on Twitter Share Tuntable Creek Road - Reopened (5 April 2024) on Linkedin Email Tuntable Creek Road - Reopened (5 April 2024) linkTuntable Creek Road – Road Open (5 April 2024)
Tuntable Creek Road has reopened, 2pm 5 April 2024, after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.
In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form. -
Tuntable Creek Road - Road Closure (4 April 2024)
Share Tuntable Creek Road - Road Closure (4 April 2024) on Facebook Share Tuntable Creek Road - Road Closure (4 April 2024) on Twitter Share Tuntable Creek Road - Road Closure (4 April 2024) on Linkedin Email Tuntable Creek Road - Road Closure (4 April 2024) linkTuntable Creek Road - Road Closure (4 April 2024)
Tuntable Creek Road between Rose Road and Beardow Road will be closed at 11:00am today until further notice due to significant rainfall.
We apologise for the short notice and thank the community for their understanding.
Live Traffic Information
https://www.livetraffic.com/incident-details/174116 -
Flood Restoration - Roads & Bridges Update (Mar 2024)
Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Mar 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Mar 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Black Road
Temporary repair works were completed on Black Road to restore access to properties for residents. This involved importing some additional rock, stabilising the current structure with no fines concrete, and adding some additional surface material to ensure the crossing remains trafficable while the design for a new structure is under way.
Dorroughby Road
The Dorroughby Road landslip restoration project is now completed with motorists excitingly driving the stretch over road in mid-March. The works involved stabilising the landslip embankment, installing drainage, and constructing a new road pavement. We would like to thank the community for their patience during the construction and the positive feedback we have received from road users who are enjoying this new section of the road.
Industry Drive
During March work crews constructed a gabion wall to improve drainage prevent future erosion on Industry Drive. The works were completed under the watchful eye of nearby preschool children, who demonstrated great anticipation at the fence each day as they watched eagerly what the machinery would do next. A highlight for our crews as they witnessed the children’s smiling faces observing the works. Thank you to the local community for your support during these works.
Johnston Road
Works are now complete on a storm water outlet on Johnston Road. These works included reinstating the rock erosion protection and the concrete around the top of the precast headwall.
Road Maintenance Works - Gwynne Road, Stony Chute Road & Tuntable Falls Road
A busy month for our maintenance crews with staff inspecting and providing maintenance on many roads throughout the region. After listening to community concerns Gwynne Road, Stony Chute Road and Tuntable Falls Road were added as priority maintenance works. To improve road conditions, crews provided pothole repairs on Stony Chute Road and Tuntable Falls Road along with light grading and filling potholes for the sealed section of Gwynne Road.
CURRENT WORKS
Crofton Road
Road pavement restoration works have commenced on Crofton Road for the locations identified below. The works will occur for approximately two to three months, subject to weather conditions. The road will remain open under traffic control to have minimal impact on residents, please allow extra time for delays.
Newton Drive
Works have commenced on several minor upslope landslips and a single pipe culvert. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Nimbin Road
Works are progressing on Nimbin Road at the site near Shipway Road. During the past month, on the southbound lane, work crews have removed the asphalt and base material along with reshaping and installing drainage. The road pavement was also constructed, compacted, and rolled along the full width of the road. Following this, the steel barriers on top of the retaining wall were installed, allowing the traffic to shift back to the northbound lane. Next month, works are scheduled to construction drainage along the retaining wall and complete placement of the road base layers along the full width of the road. This will be followed by sealing and asphalting along the full width of the road, installing guardrails and construction of the gabion basket wall extension ready for the anticipated opening on the road in May.
Milgate Road
Works have commenced on Milgate Road involving road surface and drainage repairs.
Rogerson Road
The team are continuing to implement the appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We will provide further update when available. Thank you to the community for your patience and understanding.
Rosebank Road
Landslip restorations are underway at Rosebank Road. The works involve reinstating the property access track and restoring the batter and table drain along the road edge.
Terania Creek – Bridge Updates
The Terania Creek bridge project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.
Tuntable Creek Road
During March, maintenance works were completed on Tuntable Creek Road from Young Road heading back down the hill approximately 500m. These works involved reshaping of table drains, slashing and minor landslip remediation.
Upper Tuntable Falls Road
Works are underway on two landslip sites on Upper Tuntable Falls Road located near the Tuntable Falls Primary School. During the past month, a site office was established and works commenced to reinstate the existing open drains. Temporary ramps were also constructed to allow trucks entry to the slip area. The works are expected to take 6-8 weeks weather permitting.
Zouch Road
Priority works have commenced for Zouch Road. This will involve with a light grade and repairs to the road surface.
FUTURE WORKS
Gwynne Road
Gwynne Road is currently out to design; the design will take approximately one month. After this, the project will go to tender with work will be starting on the road in approximately 8 weeks.
Magellan Street
New guardrails will be installed on Magellan Street in the location identified on the map below during April. The road will remain open with works completed under single lane traffic control to have minimal impact on road users. -
Crofton Road - Pavement Works (Mar 2024)
Share Crofton Road - Pavement Works (Mar 2024) on Facebook Share Crofton Road - Pavement Works (Mar 2024) on Twitter Share Crofton Road - Pavement Works (Mar 2024) on Linkedin Email Crofton Road - Pavement Works (Mar 2024) linkCouncil wishes to advise of upcoming works on Crofton Road. The works will occur for approximately two to three months, from 2 April 2024, subject to weather conditions.
The road will remain open with works completed under traffic control to have minimal impact on residents, please allow extra time for delays. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers.
What are the works?
Following the February 2022 natural disaster, Crofton Road suffered extensive damage. Funding has now been secured for road pavement restoration works on the locations identified below.Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Crofton Road – March 2024 Update.’We apologise in advance for any disruptions you may experience while we carry out this essential work.
-
Newton Road - Minor Landslip & Culvert Works (Mar 2024)
Share Newton Road - Minor Landslip & Culvert Works (Mar 2024) on Facebook Share Newton Road - Minor Landslip & Culvert Works (Mar 2024) on Twitter Share Newton Road - Minor Landslip & Culvert Works (Mar 2024) on Linkedin Email Newton Road - Minor Landslip & Culvert Works (Mar 2024) linkCouncil wishes to advise of upcoming works on Newton Drive. The works will occur for approximately six to eight weeks, from 2 April 2024, subject to weather conditions.
The road will remain open with works completed under traffic control to have minimal impact on residents. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Following the February 2022 natural disaster, Newton Drive suffered extensive damage. Funding has now been secured for restoration works for several minor landslips and a single pipe culvert identified on the below map. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Newton Drive – Mar 2024 Update.’
We apologise in advance for any disruptions you may experience while we carry out this essential work. -
Upper Tuntable Falls Road - Landslip Remediation Works (Mar 2024)
Share Upper Tuntable Falls Road - Landslip Remediation Works (Mar 2024) on Facebook Share Upper Tuntable Falls Road - Landslip Remediation Works (Mar 2024) on Twitter Share Upper Tuntable Falls Road - Landslip Remediation Works (Mar 2024) on Linkedin Email Upper Tuntable Falls Road - Landslip Remediation Works (Mar 2024) linkCouncil wishes to advise of upcoming works on Upper Tuntable Falls Road. The works will occur for approximately eight weeks, from 25 March, subject to weather conditions.
The road will remain open with works completed under single lane traffic control to have minimal impact on residents. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. Please adhere to all road signs and directions from any traffic controllers and ensure extra care is taken around workers on foot.
What are the works?
Following the February 2022 natural disaster, Upper Tuntable Falls Road suffered extensive damage. Funding has been secured for landslip remediation works on the sites identified on the map below.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Upper Tuntable Falls Road – March 2024 Update.’
We apologise in advance for any disruptions you may experience while we carry out this essential work. -
Flood Restoration - Roads & Bridges Update (Feb 2024)
Share Flood Restoration - Roads & Bridges Update (Feb 2024) on Facebook Share Flood Restoration - Roads & Bridges Update (Feb 2024) on Twitter Share Flood Restoration - Roads & Bridges Update (Feb 2024) on Linkedin Email Flood Restoration - Roads & Bridges Update (Feb 2024) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Geotechnical Investigations
During the last 5 months geotechnical investigations have taken place across the entire Lismore shire region. These works have involved using a drilling rig to understand subsurface conditions at the many landslip, bridge and culvert crossing locations. This information is vital in determining the most appropriate restoration design solution for these locations. All landslip, culvert and bridge geotechnical investigations have now been completed. We would like to thank residents for your patience and resilience during this time.
CURRENT WORKS
Dorroughby Road
The Dorroughby Road landslip restoration is well underway with embankment stabilisation completed last month. Wet weather has extended the closure slightly, however, drainage and road pavement works are scheduled to occur during March. See below progress photos, thank you to all the Dorroughby Road residents for your patience during this time.
Nimbin Road
Works are progressing on Nimbin Road at the site near Shipway Road. The retaining wall construction is now complete, and the road pavement works commenced end of February. Excitingly, traffic has temporarily moved onto the newly constructed northbound lane in preparation for an expected opening in April.
Guardrails Project
During the past month our guardrails project has been underway, replacing or installing new guardrails. This is multisite works to repair traffic barriers at road sections damaged during the 2022 natural disaster. Generally, the sites are at road sections over creek crossings. Each work site will require traffic control and the repair will generally be completed within 2 days. Recently, guardrails were completed on two sites at Nimbin Road, Rock Valley Road, Cawongla Road, Corndale Road and two sites at Boatharbour Road. Other road closures will be updated as scheduled work on Live Traffic.
Tuntable Creek Road
Works are currently underway on Tuntable Creek Road near Young Road. These involve reshaping of table drains, slashing and minor landslip remediation from Young Road heading back down the hill approximately 500m. The works are expected to be completed first week of March, pending weather conditions.
Terania Creek Road
The Terania Creek bridges project is underway for bridge 1, 2 and 3. The bridge approaches and guard rail footings are completed for bridge 1. During early March, work crews will commence final concrete works and installation of lateral restrain brackets for bridge 3.
Newton Drive
Several minor upslope landslips and a single pipe culvert were scheduled to be repaired during February, these works have now been pushed into March due to weather delays. Works will involve scaling of boulders and the clearing and reformation of a table drain to return the road to pre-existing condition. Works will be completed under traffic control and will have minimal impact on the residents in this area.
Rosebank Road
Landslip restoration works were scheduled for completed during February; these works have now been pushed into March due to weather delays. The works involve reinstating the property access track and restoring the batter and table drain along the road edge. Works will be completed under traffic control and will have minimal impact on the residents.
Industry Drive
Works have commenced on Industry Drive to improve drainage works involving the construction of a gabion wall to prevent future erosion. The works will occur for approximately two weeks, from Thursday 29 February, pending weather conditions. For further information, please view the original notice at
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/industry-drive
Rogerson Road
The team have been busy implementing appropriate protocols to ensure the safety of juvenile micro bats. Through successful collaboration with environmental professionals this protected species will be temporary relocated. This will allow the pups to complete their growth cycle during the breeding season and reduce their risk in maturing. We are unsure of the start date at this time. We will provide further update when available. Thank you to the community for your patience and understanding during these works. For further information, please view the original notice at: https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/rogerson-road-culvert-replacement-feb-2024
FUTURE WORKS
Johnston Road
Works will commence to replace a damaged culvert headwall on Johnston Road for approximately two weeks, from 4 March to 18 March 2024, subject to weather conditions. The road will remain open under stop/go traffic control with slight delays expected. For further information, please view the original notice at
https://yoursay.lismore.nsw.gov.au/maintaining-our-roads-and-bridges/news_feed/johnston-road-culvert-works-feb-2023
Eureka Road, Graham Road & Haywood Lane
During the end of February, all three bridges were successfully delivered to Council storage yards. The designs for each site are in the final stages with works schedules being finalised. We apologise in advance for any disruptions you may experience while we carry out this essential work. These works will involve removing the existing infrastructure at each site and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track will be established as a side road. The work duration at each site is expected to be approximately 6 weeks, subject to weather conditions.
Blue Knob Road
Remediation works are planned to commence in April 2024 on several landslips on Blue Knob Road, the two sites currently under temporary traffic control measures. Our primary focus is to ensure the well-being of our community and to efficiently manage the project to minimise disruption. We will notify residents of the exact date and provide further information on the works closer to commencement. The expected duration of the works will be approximately nine months, this estimated period includes the remediation of the total of four landslips.
Leycester Road
Leycester Road design is currently underway with expected completion in May 2024. Works are expected to start on site in August 2024 and will take approximately two months to complete. Funding for these works has been approved.
Oakey Creek Road
Currently there are five major landslips on Oakey Creek Road. Due to the complex nature of these sites, which involves multiple design iterations and reviews from civil, structural, and geotechnical engineers, the designs are expected to be completed by September 2024, with works to commence early in 2025 pending funding approvals.
Stony Chute Road
There are multiple landslips along Stoney Chute Road, seven of these being complex and two being non-complex. Works will commence on the noncomplex sites during April with the expected completion of June 2024. The more complex sites are currently under design with this process anticipated to be completed by August 2024 and works estimated to start towards the end of 2024 pending funding approvals.
Terania Creek Road
Terania Creek Road has multiple landslip sites currently under design with expected completion in September 2024 with works estimated to commence in early 2025 pending funding approval. Currently works are underway on multiple bridges with works anticipated to be completed mid-2024.
Wallace Road
Wallace Road has two major landslips currently under design with this process expected to be completed by the end of June 2024. It is estimated the works will commence towards the end of 2024 pending funding approvals. Please note, we are unable to schedule works until we receive funding approval.
Woodlawn Road
Woodlawn Road design is currently underway with expected completion in May 2024. Works are estimated to start on site in August 2024 and will take approximately three months to complete. Funding for these works has been approved. -
Johnston Road - Culvert Works (Feb 2024)
Share Johnston Road - Culvert Works (Feb 2024) on Facebook Share Johnston Road - Culvert Works (Feb 2024) on Twitter Share Johnston Road - Culvert Works (Feb 2024) on Linkedin Email Johnston Road - Culvert Works (Feb 2024) linkCouncil wishes to advise of upcoming works on Johnston Road. The works will occur for approximately two weeks, from 4 March to 18 March 2024, subject to weather conditions.
The road will remain open under stop/go traffic control with slight delays expected. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Following the February 2022 natural disaster, Johnston Road suffered extensive damage. Funding has now been secured to replace the damaged culvert headwall at the site identified on the below map.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Johnston Road – Feb 2024 Update.’ -
Industry Drive - Upcoming Works (Feb 2024)
Share Industry Drive - Upcoming Works (Feb 2024) on Facebook Share Industry Drive - Upcoming Works (Feb 2024) on Twitter Share Industry Drive - Upcoming Works (Feb 2024) on Linkedin Email Industry Drive - Upcoming Works (Feb 2024) linkCouncil wishes to advise of upcoming works on Industry Drive. The works will occur for approximately two weeks, from Thursday 29 February, pending weather conditions.
The road will remain open, slight delays may occur. Motorists will be notified of road changes via roadside signage and updated through www.livetraffic.com. There will be no impact to Emergency services vehicles. We apologise in advance for any disruptions you may experience while we carry out this essential work.
What are the works?
Funding has been secured to undergo drainage works involving the construction of a gabion wall to prevent future erosion. The location of the works is outlined on the below map.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Industry Drive – Feb 2024 Update.’
Major Flood Restoration Works Map
Click the image below to access our interactive map
The easy to navigate map allows users to zoom in and out, switch between damages, and access detailed information about each site. This functionality benefits residents surrounding these damaged site locations by providing critical insights, proposed remediation works and estimated timeframes.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Live Traffic
Latest information on accidents, delays, road closures and road works in the Northern Rivers - please click here.
Projects By Road Name
- Alphadale Road (2)
- Anderson Road (1)
- Arkinstall Road (1)
- Armstrong Road (1)
- Ashlin Road (2)
- Avondale Avenue (1)
- Axford Road (1)
- Bagotville Road (1)
- Basil Road (1)
- Beardow Road (1)
- Behan Access (1)
- Bent Street (1)
- Bertoli Road (1)
- Bice Road (4)
- Bishops Creek Road (3)
- Black Creek Road (1)
- Black Road (8)
- Blade Road (1)
- Blue Knob Road (16)
- Boatharbour Road (2)
- Boggumbil Road (3)
- Booerie Creek Road (2)
- Boyle Road (3)
- Braidwood Road (1)
- Branch Creek Road (2)
- Brice Road (1)
- Bridge Street (1)
- Broadwater Road (1)
- Browning Road (1)
- Bruxner Crescent (1)
- Bungabbee Road (2)
- Canaiba Road (6)
- Caniaba Road (2)
- Carabeen Place (3)
- Cathcart Street (1)
- Cawongla Road (20)
- Cecil Street (1)
- Clark Road (1)
- Clunes (1)
- Clyde Campbell Carpark (1)
- College Road (1)
- Cook Road (1)
- Coraki Road (4)
- Corndale Road (8)
- Cosy Camp Road (3)
- Cowlong Road (3)
- Crofton Road (13)
- Cross Road (2)
- Cullen Road (1)
- Cusack Road (1)
- Davis Road (2)
- Dorroughby Road (8)
- Dudgeon Road (2)
- Duncan Road (5)
- Dunoon Road (9)
- East Road (2)
- Eastment Road (1)
- Eltham Road (3)
- Emily Street (1)
- Eureka Road (7)
- Fairfull Road (1)
- Fernside Bridge (5)
- Fernside Road (1)
- Fox Road (1)
- Fraser Road (2)
- Gibson Lane (1)
- Gordon Road (1)
- Grace Road (1)
- Graham Road (9)
- Gravel Roads (4)
- Gray Road (2)
- Greengate Road (1)
- Gundarimba Road (2)
- Gundurimba Road (4)
- Gungas Road (9)
- Gwynne Road (6)
- Haywood Lane (7)
- Hensen Bridge (1)
- Henson Bridge (1)
- Hewitt Road (1)
- Houlden Road (1)
- Howards Grass Road (1)
- Humpty Back Road (1)
- Hunters Hill Road (1)
- Industry Drive (3)
- Izzard Road (1)
- Jacobson Road (1)
- James Gibson Road (2)
- James Street (1)
- Jiggi Road (11)
- Johnston Road (12)
- Keerrong Bridge (4)
- Keerrong Road (21)
- Kellas Street (2)
- Kilgin Road (1)
- Koonorigan Road (11)
- Kyogle Road (5)
- Kyogle Street (1)
- Lagoon Grass Road (1)
- Lavis Road (1)
- Lawler Road (1)
- Leeson Road (2)
- Leycester Road (11)
- Lillian Rock Road (3)
- Lodge Road (1)
- Lychee Drive (1)
- Mackie Road (8)
- Magellan Street (2)
- Main Street (1)
- Martin Road (4)
- Mathieson Lane (1)
- McGuinness Road (1)
- McInnes Road (1)
- McKinnon Road (1)
- McMahon Road (1)
- Middleton Way (2)
- Milgate Road (4)
- Minyon Falls Road (1)
- Moffitt Road (1)
- Monaltire Road (1)
- Moras Road (2)
- Mountain Top Road (8)
- Mountain View Drive (1)
- Muldoon Road (1)
- Mulvena Road (1)
- Munro Wharf Road (1)
- News Article (8)
- Newton Drive (8)
- Nightcap Range Road (4)
- Nimbin Road (32)
- Nimbin Street (1)
- Nimoola Road (1)
- Noble Road (1)
- Northcott Road (2)
- Norton Road (1)
- O'Flynn Street (1)
- Oakey Creek Road (9)
- Orion Street (7)
- Parmenter Road (2)
- Paterson Road (2)
- Patterson Road (1)
- Pelican Creek Road (1)
- Phillip Street (1)
- Pinchin Road (14)
- Potessu Road (1)
- Pothole repair (3)
- Pound Street (1)
- Quilty Road (9)
- Quilty Road (1)
- Range Court (1)
- Rankin Road (1)
- Repentance Creek Road (7)
- Richmond Hill Road (5)
- Ridgewood Road (1)
- River Bank Road (2)
- Riverbank Road (4)
- Robb Road (1)
- Robertson Bridge (1)
- Robson Road (1)
- Rock Valley Road (10)
- Rocky Creek Dam Road (1)
- Rogerson Road (9)
- Rose Road (2)
- Rosebank Road (5)
- Rosehill Road (2)
- Ross Road (1)
- Rous Road (2)
- Savins Road (1)
- Sexton Bridge (5)
- Sheehan Road (2)
- Shipway Road (1)
- Sibley Street (1)
- Skyline Road (6)
- Skyline Road South (1)
- Standing Street (1)
- Stanger Road (3)
- Stead Road (1)
- Stony Chute Road (12)
- Suffolk Road (1)
- Swan Bay Road (2)
- Symonds Road (1)
- Tatham Road (5)
- Terania Creek Road (20)
- The Channon Road (9)
- Thorburn Street (1)
- Three Chain Road (1)
- Town Road (8)
- Tregeagle Road (1)
- Trinity Drive (1)
- Tucki Road (4)
- Tuckurimba Road (2)
- Tulk Road (1)
- Tuntable Creek Road (47)
- Tuntable Falls Road (7)
- Ubrihien Street (1)
- Unara Road (1)
- Upper Coopers Creeek Road (1)
- Upper Tuntable Falls Road (9)
- Uralba Street (1)
- Virtue Road (1)
- Wallace Road (14)
- Walmsley Road (1)
- Warby Road (1)
- Webber Road (1)
- Whian Whian Road (8)
- Wilson Street (2)
- Woodlawn Road (4)
- Wybelena Road (2)
- Wyrallah Ferry Road (1)
- Wyrallah Road (10)
- Wyrallah Village (2)
- Yeager Road (4)
- Young Road (1)
- Zouch Road (7)
Latest information relating to the planning, construction and operation of infrastructure projects in NSW on behalf of Transport for NSW
Latest information relating to the planning, construction and operation of infrastructure projects in NSW on behalf of Transport for NSW - please click here.