Flood Restoration - Roads & Bridges
You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.
Why was this page designed?
Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.
This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.
Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.
Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.
What process does Council have to go through when we have a 'disaster event'?
When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.
There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)
Major Flood Recovery Works Map
Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.
Click here to view the interactive map.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Further Information
You will find all the latest repair works for Flood Restoration - Roads and Bridges Program. All current works that have updates are categorised by project name. If viewing via a smartphone, you can find the 'Projects by Road Name' at the bottom of this page.
Why was this page designed?
Since the February 2022 natural disaster, we have had an extended period of wet weather, which has significantly affected our road network. It rained three out of four days between November 2021 and April 2022.
This resulted in 90% of our 1200km road network suffering extensive damage, with an estimated $200 million to rebuild and repair. Significant damage also occurred to many bridges, causeways, reinforced concrete pipes, reinforced concrete box culverts and footpaths across our road network. Some key access roads have been reduced to single lanes due to landslips.
Immediately after flood waters receded, our road crews conducted emergency repairs on more than 80 roads to allow access for residents. Several construction crews worked extended hours to ensure damaged roads were reopened/made safe as soon as possible. As the repairs progress, we will provide more detailed updates on the specific flood-related damage to our road network and information on how you can report damaged roads to Council.
Assessments are underway at the larger and more complex damaged sites. There are specific engineering tasks in some areas which are necessary and will take time. Some sites may see temporary measures such as side-track access, temporary pothole repair and gravel roads before permanent construction works at these locations commence. Planning will continue to ensure works are undertaken as quickly as possible. Priorities are based on public safety with consideration of further damage, maintaining access and links between communities, hierarchy of roads and efficiency of results.
What process does Council have to go through when we have a 'disaster event'?
When we experience a natural disaster such as a flood event, which causes significant damage to our infrastructure, there are a number of steps that Council has to go through, like an insurance claim process. Council identifies, assesses and then makes a claim for the damage from the appropriate funding body. As we do not have the money to pay for these kind of extraordinary events from our day to day budgets. There are strict rules regarding documentation.
There are multiple steps in this process including design investigation, final design, approval, scheduling of work crews and/or engagement of contractors so there can be a long lag time from the actual event to the rectification works being started and completed. The table below shows further details and indicative timings for the steps in this process: (All timings are subject to weather, contractor and material availability)
Major Flood Recovery Works Map
Flood restoration works are critical to repairing damages caused by previous natural disasters and getting life back on track. However, these works can be complex, especially when dealing with large-scale disasters like the February 2022 event. At Lismore City Council, we understand the challenges that come with flood restoration works and are proud to launch this interactive map focusing on major flood recovery works within the Lismore LGA to assist the community with finding efficient, up-to-date information. Please note, timeframes are subject to change in the next few months as the project delivery strategy evolves.
Click here to view the interactive map.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Further Information
-
Koonorigan Road - Maintenance Work (Nov 2023)
Share Koonorigan Road - Maintenance Work (Nov 2023) on Facebook Share Koonorigan Road - Maintenance Work (Nov 2023) on Twitter Share Koonorigan Road - Maintenance Work (Nov 2023) on Linkedin Email Koonorigan Road - Maintenance Work (Nov 2023) linkFollowing the February 2022 natural disaster, Koonorigan Road suffered extensive damage. Council completed temporary works to improve the road surface condition during 2022 as a temporary measure, until permanent pavement rehabilitation works were scheduled.
The funding submission for a permanent restoration works was completed in June 2023, and Council is awaiting on funding approval to commence work. When approved, works will apply to multiple sections that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments.
Council would like to improve the impact on residents and have scheduled road maintenance works for the week commencing 20 November 2023. Geotechnical investigations will also be performed during this period. We would like to thank the community for their continuing patience.
The road will not be closed during the works and motorists will be notified of changes via roadside signage and updated through www.livetraffic.com. Please adhere to all road signs and directions from any traffic controllers.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Koonorigan – Nov 2023 Update.’ -
Wallace Road - Drilling Works (Nov 2023)
Share Wallace Road - Drilling Works (Nov 2023) on Facebook Share Wallace Road - Drilling Works (Nov 2023) on Twitter Share Wallace Road - Drilling Works (Nov 2023) on Linkedin Email Wallace Road - Drilling Works (Nov 2023) linkFollowing the February 2022 natural disaster, Wallace Road suffered extensive damage. Funding has now been secured to complete investigative drilling works using a drilling rig to understand subsurface conditions.
The works will involve closing a section of the road on 20 November 2023, from 8am for 24 hours. The closed section of works is located approximately around 120 and 137 Wallace Road.
A full road closure will be required around the works zone for the day. Motorists will be notified of the closure via roadside signage and updated through www.livetraffic.com. Residents will be able to walk through the work zone to access to their properties but will be unable to drive through the work zone. Cars can be stored either side of the works for this period. Access for emergency services will be accommodated. Please adhere to all road closed signs and directions from any traffic controllers.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Wallace Road – Nov 2023 Update.’ -
Flood Restoration - Roads & Bridges Update (Oct 2023)
Share Flood Restoration - Roads & Bridges Update (Oct 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Oct 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Oct 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Oct 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Keerrong Road
Works were completed during October on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works were carried out over 3 weeks and Council would like to thank the community for their support during the road closure.
Tuntable Creek Road
During October, new road signs were installed to assist with future road closures for Tuntable Creek Road. The extra signs will allow Council to notify residents of closures before reaching the closed site, helping to reduce detour times.
CURRENT WORKS
Crofton Road
This week, the first 500 metres of the road section will undergo restoration. Due to extensive damage, this section will be converted into a gravel road to facilitate the smooth flow of construction vehicles until the works are completed. Additionally, starting next week, pavement restoration works will commence from the other end of the road, and will be carried out for next two months ensuring improvements to enhance the road's overall condition.
Carabeen Place
Funding was secured for works to commence on Carabeen Road in October to repair damages caused during the 2022 natural disaster. The works includes restoring the batter to its original condition with rockfill and ensuring the drainage is adequate for future events.
Nimbin Road
Works are continuing for Nimbin Road, with the Site Km1 recently completing the placement of fine concrete blocks and backfill behind the retaining wall. The next steps are to backfill the underside of the road pavement layers and complete placement of the culvert outlet. Once completed, the road pavement construction will start along with earthworks around the retaining wall. Site Km4 recently completed the installation of 180 piles with the remaining piles to be completed at the beginning of November. Concrete pouring for the first section of the pile cap commenced late October with works currently underway for the first section of the 50m long blinding layer.
FUTURE WORKS
Traffic Barriers
Rural roads in the Lismore Local Government Area will have some of the creek crossings with damaged traffic barriers replaced during November. Approximately 15 crossings will be included as part of the Flood Disaster Recovery Funding Arrangements (DRFA) funding.
Terania Creek Road
Works are schedule to commence at Terania Creek Road on Bridge No. 3 during early November. These works will initially entail construction of a temporary side track next to the bridge so traffic can be detoured. After, works commence on installation of the new concrete bridge approaches. These works are expected to take approximately three to four weeks and will then move only Bridge No. 2, followed by Bridge No. 1. A VMS board will be installed prior to detouring traffic.
Rogerson Road
Funding is now approved for culvert works to Rogerson Road. During the Feb 2022 flood event, the Rogerson Road culvert had corrugated pipes that were severely scoured as well as the pipe bedding being eroded. The corrugated pipes will be replaced with precast concrete pipes to meet current engineering standards. Tendering is about to start for the works and members of our team are meeting with residents to discuss the works and notify them of any interruptions for the road.
-
Tuntable Creek Road - Reopened (29 October 2023)
Share Tuntable Creek Road - Reopened (29 October 2023) on Facebook Share Tuntable Creek Road - Reopened (29 October 2023) on Twitter Share Tuntable Creek Road - Reopened (29 October 2023) on Linkedin Email Tuntable Creek Road - Reopened (29 October 2023) linkTuntable Creek Road – Road Open (29th October 2023)
Tuntable Creek Road has reopened after the shutdown due to rainfall. We apologise to the community for the inconvenience caused and delays in travelling alternative routes.
As the site has not had its permanent repair designed and constructed, a management plan is in place which requires visual inspections, geotechnical instrument readings, surveying monitoring, rain records and photograph evidence.In the event of rainfall exceeding our trigger level or other significant changes the temporary track will be closed again at short notice.
Please contact frp@lismore.nsw.gov.au with the subject ‘Tuntable Creek Road notification list’ to register your contact details to receive updates.
We also have an SMS notification list you can join, simply email your mobile number and name to be added with the subject Tuntable Creek Road SMS List.
To receive updates on Tuntable Creek Road and any other flood restoration roads, please register your contact details via our notification list form.
-
Leycester Road - Gravel Road Maintenance (Oct 2023)
Share Leycester Road - Gravel Road Maintenance (Oct 2023) on Facebook Share Leycester Road - Gravel Road Maintenance (Oct 2023) on Twitter Share Leycester Road - Gravel Road Maintenance (Oct 2023) on Linkedin Email Leycester Road - Gravel Road Maintenance (Oct 2023) linkFollowing the February 2022 natural disaster, Leycester Road suffered extensive damage. Council completed temporary patching works to improve the road surface condition during December 2022. These works involved removing damaged road sections and replacing with gravel road base, with an emulsion sacrificial seal. The temporary patching works were a temporary measure, until permanent pavement rehabilitation works were scheduled.
The funding submission for a permanent pavement rehabilitation was completed in June 2023, and Council is awaiting on funding approval to commence work. We have also asked for priority funding to accelerate these works. When approved, works will apply to multiple sections that have been identified as significantly impacted by the February 2022 natural disaster, based on pre and post disaster assessments.
Council would like to improve the impact on residents while waiting for funding approval and have scheduled further gravel road maintenance works for next week. We would like to thank the community for their continuing patience.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Leycester Road – October 2023 Update.’
-
Tuntable Creek Road - Road Closure (27 October 2023)
Share Tuntable Creek Road - Road Closure (27 October 2023) on Facebook Share Tuntable Creek Road - Road Closure (27 October 2023) on Twitter Share Tuntable Creek Road - Road Closure (27 October 2023) on Linkedin Email Tuntable Creek Road - Road Closure (27 October 2023) linkTuntable Creek Road - Road Closure (27 October 2023)
Tuntable Creek Road will be closed until further notice due to significant rainfall. We apologise for the short notice and thank the community for their understanding during this time.
-
Flood Restoration - Roads & Bridges Update (Sept 2023)
Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Sept 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Sept 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Bungabbee Road
Recently the Bungabbee Road bridge approaches works were completed to repair damages from the 2022 natural disaster. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.
Dudgeon Road BridgeWorks were scheduled and completed last month to repair the flood damaged Bungabbee Road bridge approaches. The works involved re-construction of the damaged approaches and re-instatement of guard rails, drainage, and scour protection around abutments.
Major Flood Recovery Works Map
Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater along with Flood Restoration Building projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.
CURRENT WORKS
Nimbin Road
Works are continuing for the Nimbin Road landslips. Site Km1, located 1 Km from Nimbin has all the concrete works and piling complete with the installation of block wall in progress. This site is on schedule for the road to be fully open before Christmas. Site Km4, located 4 Km’s from Nimbin is currently undergoing construction of gabion walls, these are used for scour protection, which prevents soil from being washed away and helps strengthen the road. The site also has piling in progress with approximately 30% completed.
Keerrong Road
Works have commenced on Keerrong Road for excavation of slipped material and reconstruction of the road embankment. The works are scheduled for approximately 3 weeks, subject to weather, contractor, and material availability. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com. Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.
Geotechnical Investigations
The Lismore City Council (LCC), Flood Recovery – Roads and Bridges team recently secured interim funding for additional geotechnical investigations and survey to commence on several flood affected roads. Initial investigations took place in 2022 to inform the designers about the geological conditions and failure mechanism. This information was used to apply for funding to repair. Additional investigations are now required to inform the final design.
Geotechnical drilling is a type of drilling that is performed as part of the construction process to assist with better understanding a site. Investigations involve collecting rock and soil samples to obtain data regarding surface and subsurface examination. These samples provide valuable insights into the physical properties of the site, enabling engineers to design and construct remediation works to deliver roads that are safer and more durable.
Roads approved for investigations include Bice Road, Bishops Creek Road, Black Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Cross Road, Gungas Road, Johnston Road, Koonorigan Road, Lillian Rock, Martin Road, Mountain Top Road, Oakey Creek Road, Orion Street, Rock Valley Road, Skyline Road, Stanger Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Upper Tuntable Falls Road, Wallace Road, Whian Whian Road, Yeager Road and Zouch Road.
Cawongla Road
Significant changes to the traffic control measures at the Cawongla Road Landslide site, near Martin Road, were recently implemented. It was identified that the site was deemed unsafe due to technical issues with the traffic lights, including repeated battery charge depletion, and concerns about safety. Therefore, the traffic lights previously regulating traffic flow have been replaced with a “Give Way” sign and a “Stop” sign. This decision was prompted by multiple incidents of road users running the red lights, posing a serious safety hazard. The new signage system aims to simplify traffic management while mitigating potential hazards. All signage has been installed as per the amended traffic guidance scheme, and a comprehensive risk assessment was conducted before implementing these changes to ensure the safety of all individuals travelling through the site.
-
Geotechnical Investigations & Survey (Aug 2023)
Share Geotechnical Investigations & Survey (Aug 2023) on Facebook Share Geotechnical Investigations & Survey (Aug 2023) on Twitter Share Geotechnical Investigations & Survey (Aug 2023) on Linkedin Email Geotechnical Investigations & Survey (Aug 2023) linkInterim funding has been approved for geotechnical investigations and survey to commence on the roads identified below. This process will be taking place over the next 4 months.
Commencing - 4th of September
Bice Road, Black Road, Cawongla Road, Gungas Road, Koonorigan Road, Martin Road, Mountain Top Road, Orion Street and Yeager Road.Commencing - 18th of September
Bishops Creek Road, Blue Knob Road, Boyle Road, Cawongla Road, Cosy Camp Road, Lillian Rock, Mountain Top Road, Oakey Creek Road, Rock Valley Road, Skyline Road, Stanger Road, Tuntable Creek Road, Upper Tuntable Falls Road and Zouch Road.
Commencing - 16th of October
Blue Knob Road, Cross Road, Johnston Road, Stony Chute Road, Terania Creek Road, The Channon Road, Tuntable Creek Road, Wallace Road and Whian Whian Road
There will be some implications on traffic during this process, please adhere to all road signs and directions from any traffic controller. We apologise for any inconvenience. Further details will be provided once available.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Geotechnical Investigations & Survey.’
-
Flood Restoration - Roads & Bridges Update (Aug 2023)
Share Flood Restoration - Roads & Bridges Update (Aug 2023) on Facebook Share Flood Restoration - Roads & Bridges Update (Aug 2023) on Twitter Share Flood Restoration - Roads & Bridges Update (Aug 2023) on Linkedin Email Flood Restoration - Roads & Bridges Update (Aug 2023) linkROADS & BRIDGES FLOOD RESTORATION PROJECT UPDATE
Please note, several road and bridge projects progressing concurrently, below are updates for some projects progressing this month. Please check the 'Projects By Name' and select the road name for latest updates. Additionally, if there is a road you would like specific flood restoration updates on, please register your contact details via our notification list form.
COMPLETED WORKS
Terania Creek Road
Council recently completed maintenance work on Terania Creek Road to improve safety for road users. Guideposts were added, debris cleared, and large boulders removed which were partially blocking the road. The Flood Recovery – Roads and Bridges team would like to thank the community for their positive feedback and resilience during the flood restoration process.
Whian Whian Road - Simes BridgesDuring the February 2022 natural disaster, the northern abutment of Simes Bridge on Whian Whian Road was impacted. Temporary works were carried out to restore access and the site is currently limited to one-lane traffic access under a give-way arrangement. The bridge is currently under restrictions and monitoring due to the flood damage. However, it was opened on August 10, to two lanes at reduced speeds to improve travel for residents. The bridge will continue to be sign posted limiting motorists to 40km/hr and speed bumps have been installed on the road entering the bridge.
Major Flood Recovery Works Map
Our interactive map recently underwent upgrades to improve user experience and include other flood recovery departments. Water and wastewater projects have now been implemented into the map and in the coming month the flood restoration buildings will all be included. The map assists the community with finding efficient, up-to-date information about restoration works.
CURRENT WORKS
Nimbin Road
The piling works were completed on August 23rd for Site 1km, approximately 1 Km from Nimbin. The drilling rig has now been relocated to Site 4km, approximately 4 Kms from Nimbin. The concreting of the pile cap, the base of the block retaining wall, has also commenced. Earthworks are now complete, and the piling is due to commence at the 4km site in early September.
FUTURE WORKS
Keerrong Road
Following the February 2022 natural disaster, Keerrong Road suffered extensive damage due to landslips and erosion. Funding has now been secured to complete restoration works. Works are located at Keerrong Road and will begin from 14 September 2023 for approximately 3 weeks, subject to weather, contractor and material availability. The works will include excavation of slipped material and reconstruction of the road embankment. A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com, and on Your Say (details below). Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.
-
Keerrong Road - Flood Restoration Works (Aug 2023)
Share Keerrong Road - Flood Restoration Works (Aug 2023) on Facebook Share Keerrong Road - Flood Restoration Works (Aug 2023) on Twitter Share Keerrong Road - Flood Restoration Works (Aug 2023) on Linkedin Email Keerrong Road - Flood Restoration Works (Aug 2023) linkFollowing the February 2022 natural disaster, Keerrong Road suffered extensive damage due to landslips and erosion. Funding has now been secured to complete restoration works.
Works are located at Keerrong Road and will begin from 14 September 2023 for approximately 3 weeks, subject to weather, contractor and material availability. The works will include excavation of slipped material and reconstruction of the road embankment.
A full road closure will be required around the works zone throughout the works period. A detour is available via Pinchin Road, motorists will be notified ahead of the closure via roadside signage, updated through www.livetraffic.com, and on Your Say (details below). Residents will have access to their properties via Pinchin Road and The Channon Road but will be unable to drive through the landslip work zone. Please adhere to all road closed signs and directions from any traffic controllers.
Further Information
Should you wish to contact us directly with any questions or comments, or register your contact details to receive updates, please call (02) 6625 0500 or email frp@lismore.nsw.gov.au and include the title ‘Keerrong Road – August 2023 Update.’
Major Flood Restoration Works Map
Click the image below to access our interactive map
The easy to navigate map allows users to zoom in and out, switch between damages, and access detailed information about each site. This functionality benefits residents surrounding these damaged site locations by providing critical insights, proposed remediation works and estimated timeframes.
Disclaimer: This tool has been provided by Lismore City Council to provide up to date information on the status of the flood damaged Council assets. The identified locations are the projects considered for EPAR funding provided by the Australian Commonwealth under the DRFA guidelines. The information provided on this tool is general in nature and subject to change based on final design calculations, funding approvals, and changing site circumstances. This data is frequently updated to provide the community with the latest information. When contacting Council, please reference the location damage number.
Live Traffic
Latest information on accidents, delays, road closures and road works in the Northern Rivers - please click here.
Projects By Road Name
- Alphadale Road (2)
- Anderson Road (1)
- Arkinstall Road (1)
- Armstrong Road (1)
- Ashlin Road (2)
- Avondale Avenue (1)
- Axford Road (1)
- Bagotville Road (1)
- Basil Road (1)
- Beardow Road (1)
- Behan Access (1)
- Bent Street (1)
- Bertoli Road (1)
- Bice Road (4)
- Bishops Creek Road (3)
- Black Creek Road (1)
- Black Road (8)
- Blade Road (1)
- Blue Knob Road (16)
- Boatharbour Road (2)
- Boggumbil Road (3)
- Booerie Creek Road (2)
- Boyle Road (3)
- Braidwood Road (1)
- Branch Creek Road (2)
- Brice Road (1)
- Bridge Street (1)
- Broadwater Road (1)
- Browning Road (1)
- Bruxner Crescent (1)
- Bungabbee Road (2)
- Canaiba Road (6)
- Caniaba Road (2)
- Carabeen Place (3)
- Cathcart Street (1)
- Cawongla Road (20)
- Cecil Street (1)
- Clark Road (1)
- Clunes (1)
- Clyde Campbell Carpark (1)
- College Road (1)
- Cook Road (1)
- Coraki Road (4)
- Corndale Road (8)
- Cosy Camp Road (3)
- Cowlong Road (3)
- Crofton Road (13)
- Cross Road (2)
- Cullen Road (1)
- Cusack Road (1)
- Davis Road (2)
- Dorroughby Road (8)
- Dudgeon Road (2)
- Duncan Road (5)
- Dunoon Road (9)
- East Road (2)
- Eastment Road (1)
- Eltham Road (3)
- Emily Street (1)
- Eureka Road (7)
- Fairfull Road (1)
- Fernside Bridge (5)
- Fernside Road (1)
- Fox Road (1)
- Fraser Road (2)
- Gibson Lane (1)
- Gordon Road (1)
- Grace Road (1)
- Graham Road (9)
- Gravel Roads (4)
- Gray Road (2)
- Greengate Road (1)
- Gundarimba Road (2)
- Gundurimba Road (4)
- Gungas Road (9)
- Gwynne Road (6)
- Haywood Lane (7)
- Hensen Bridge (1)
- Henson Bridge (1)
- Hewitt Road (1)
- Houlden Road (1)
- Howards Grass Road (1)
- Humpty Back Road (1)
- Hunters Hill Road (1)
- Industry Drive (3)
- Izzard Road (1)
- Jacobson Road (1)
- James Gibson Road (2)
- James Street (1)
- Jiggi Road (11)
- Johnston Road (12)
- Keerrong Bridge (4)
- Keerrong Road (21)
- Kellas Street (2)
- Kilgin Road (1)
- Koonorigan Road (11)
- Kyogle Road (5)
- Kyogle Street (1)
- Lagoon Grass Road (1)
- Lavis Road (1)
- Lawler Road (1)
- Leeson Road (2)
- Leycester Road (11)
- Lillian Rock Road (3)
- Lodge Road (1)
- Lychee Drive (1)
- Mackie Road (8)
- Magellan Street (2)
- Main Street (1)
- Martin Road (4)
- Mathieson Lane (1)
- McGuinness Road (1)
- McInnes Road (1)
- McKinnon Road (1)
- McMahon Road (1)
- Middleton Way (2)
- Milgate Road (4)
- Minyon Falls Road (1)
- Moffitt Road (1)
- Monaltire Road (1)
- Moras Road (2)
- Mountain Top Road (8)
- Mountain View Drive (1)
- Muldoon Road (1)
- Mulvena Road (1)
- Munro Wharf Road (1)
- News Article (8)
- Newton Drive (8)
- Nightcap Range Road (4)
- Nimbin Road (32)
- Nimbin Street (1)
- Nimoola Road (1)
- Noble Road (1)
- Northcott Road (2)
- Norton Road (1)
- O'Flynn Street (1)
- Oakey Creek Road (9)
- Orion Street (7)
- Parmenter Road (2)
- Paterson Road (2)
- Patterson Road (1)
- Pelican Creek Road (1)
- Phillip Street (1)
- Pinchin Road (14)
- Potessu Road (1)
- Pothole repair (3)
- Pound Street (1)
- Quilty Road (9)
- Quilty Road (1)
- Range Court (1)
- Rankin Road (1)
- Repentance Creek Road (7)
- Richmond Hill Road (5)
- Ridgewood Road (1)
- River Bank Road (2)
- Riverbank Road (4)
- Robb Road (1)
- Robertson Bridge (1)
- Robson Road (1)
- Rock Valley Road (10)
- Rocky Creek Dam Road (1)
- Rogerson Road (9)
- Rose Road (2)
- Rosebank Road (5)
- Rosehill Road (2)
- Ross Road (1)
- Rous Road (2)
- Savins Road (1)
- Sexton Bridge (5)
- Sheehan Road (2)
- Shipway Road (1)
- Sibley Street (1)
- Skyline Road (6)
- Skyline Road South (1)
- Standing Street (1)
- Stanger Road (3)
- Stead Road (1)
- Stony Chute Road (12)
- Suffolk Road (1)
- Swan Bay Road (2)
- Symonds Road (1)
- Tatham Road (5)
- Terania Creek Road (20)
- The Channon Road (9)
- Thorburn Street (1)
- Three Chain Road (1)
- Town Road (8)
- Tregeagle Road (1)
- Trinity Drive (1)
- Tucki Road (4)
- Tuckurimba Road (2)
- Tulk Road (1)
- Tuntable Creek Road (47)
- Tuntable Falls Road (7)
- Ubrihien Street (1)
- Unara Road (1)
- Upper Coopers Creeek Road (1)
- Upper Tuntable Falls Road (9)
- Uralba Street (1)
- Virtue Road (1)
- Wallace Road (14)
- Walmsley Road (1)
- Warby Road (1)
- Webber Road (1)
- Whian Whian Road (8)
- Wilson Street (2)
- Woodlawn Road (4)
- Wybelena Road (2)
- Wyrallah Ferry Road (1)
- Wyrallah Road (10)
- Wyrallah Village (2)
- Yeager Road (4)
- Young Road (1)
- Zouch Road (7)
Latest information relating to the planning, construction and operation of infrastructure projects in NSW on behalf of Transport for NSW
Latest information relating to the planning, construction and operation of infrastructure projects in NSW on behalf of Transport for NSW - please click here.